10 U.S.C. § 4271 — Program cost, fielding, and performance
Federal law — U.S. Code and appendices · legal_authorities
Page 2725
TITLE 10—ARMED FORCES
§ 4271
Sec.
4272.
Independent technical risk assessments.
4273.
Performance assessments and root cause
analyses.
4274.
[Reserved].
4275.
[Reserved].
4276.
[Reserved].
Editorial Notes
AMENDMENTS
2021—Pub. L. 117–81, div. A, title XVII, § 1701(r)(1)(A),
Dec. 27, 2021, 135 Stat. 2149, amended Pub. L. 116–283,
div. A, title XVIII. § 1847(a), Jan. 1, 2021, 134 Stat. 4253,
which added this analysis, by substituting ‘‘[Reserved]’’
for ‘‘Acquisition-related functions of chiefs: adherence
to requirements in major defense acquisition pro-
grams’’ in item 4274.
§ 4271. Program cost, fielding, and performance
goals in planning major defense acquisition
programs
(a) PROGRAM COST AND FIELDING TARGETS.—(1)
Before funds are obligated for technology devel-
opment, systems development, or production of
a major defense acquisition program, the des-
ignated milestone decision authority for the
program shall ensure, by establishing the goals
described in paragraph (2), that the program
will—
(A) be affordable;
(B) incorporate program planning that an-
ticipates the evolution of capabilities to meet
changing threats, technology insertion, and
interoperability; and
(C) be fielded when needed.
(2) The goals described in this paragraph are
goals for—
(A)
the
procurement
unit
cost
and
sustainment cost (referred to in this section as
the ‘‘program cost targets’’);
(B) the date for initial operational capa-
bility (referred to in this section as the ‘‘field-
ing target’’); and
(C) technology maturation, prototyping, and
a modular open system approach to evolve
system capabilities and improve interoper-
ability.
(b) DEFINITIONS.—In this section:
(1) The term ‘‘procurement unit cost’’ has
the meaning provided in section 435
Source: Supplied 2024 U.S. Code historical extraction · 10 U.S.C. § 4271
Stored review status: historical_2024_not_currentness_verified. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: 75177af749ff242174bcaf44a07a02640e6ea0f9b5c319b2554d37fa477028d0. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:usc2024-f7af05106941d824c34afddb
Source file: Laws/federal/codes/united-states-code-2024/title-10/section-4271-program-cost-fielding-and-performance--39d1d5b479.md
Pages: Not recorded – Not recorded
Passage SHA-256: 499fcff35fa4cb03afa9969e2414389dd23619111e6b13a5e2ced80726762750
Source location: USCODE-2024-title10-subtitleA-partV-subpartF-chap322-subchapIV-sec4271.pdf
Stored source content
Page 2725
TITLE 10—ARMED FORCES
§ 4271
Sec.
4272.
Independent technical risk assessments.
4273.
Performance assessments and root cause
analyses.
4274.
[Reserved].
4275.
[Reserved].
4276.
[Reserved].
Editorial Notes
AMENDMENTS
2021—Pub. L. 117–81, div. A, title XVII, § 1701(r)(1)(A),
Dec. 27, 2021, 135 Stat. 2149, amended Pub. L. 116–283,
div. A, title XVIII. § 1847(a), Jan. 1, 2021, 134 Stat. 4253,
which added this analysis, by substituting ‘‘[Reserved]’’
for ‘‘Acquisition-related functions of chiefs: adherence
to requirements in major defense acquisition pro-
grams’’ in item 4274.
§ 4271. Program cost, fielding, and performance
goals in planning major defense acquisition
programs
(a) PROGRAM COST AND FIELDING TARGETS.—(1)
Before funds are obligated for technology devel-
opment, systems development, or production of
a major defense acquisition program, the des-
ignated milestone decision authority for the
program shall ensure, by establishing the goals
described in paragraph (2), that the program
will—
(A) be affordable;
(B) incorporate program planning that an-
ticipates the evolution of capabilities to meet
changing threats, technology insertion, and
interoperability; and
(C) be fielded when needed.
(2) The goals described in this paragraph are
goals for—
(A)
the
procurement
unit
cost
and
sustainment cost (referred to in this section as
the ‘‘program cost targets’’);
(B) the date for initial operational capa-
bility (referred to in this section as the ‘‘field-
ing target’’); and
(C) technology maturation, prototyping, and
a modular open system approach to evolve
system capabilities and improve interoper-
ability.
(b) DEFINITIONS.—In this section:
(1) The term ‘‘procurement unit cost’’ has
the meaning provided in section 4351(a)(2) of
this title.
(2) The term ‘‘initial capabilities document’’
has the meaning provided in section 4251(d)(1)
of this title.
(Added Pub. L. 114–328, div. A, title VIII,
§ 807(a)(1), Dec. 23, 2016, 130 Stat. 2260, § 2448a;
amended Pub. L. 115–232, div. A, title VIII,
§ 831(a), Aug. 13, 2018, 132 Stat. 1857; renumbered
§ 4271 and amended Pub. L. 116–283, div. A, title
XVIII, § 1847(e)(1), Jan. 1, 2021, 134 Stat. 4256;
Pub.
L.
117–81,
div.
A,
title
XVII,
§ 1701(o)(6)(C)(iv), Dec. 27, 2021, 135 Stat. 2147.)
Editorial Notes
AMENDMENTS
2021—Pub. L. 116–283, § 1847(e)(1), renumbered section
2448a of this title as the section.
Subsec. (b)(1). Pub. L. 116–283, § 1847(e)(1)(A), as
amended by Pub. L. 117–81, § 1701(o)(6)(C)(iv), sub-
stituted ‘‘section 4351(a)(2)’’ for ‘‘section 2432(a)(2)’’.
Subsec. (b)(2). Pub. L. 116–283, § 1847(e)(1)(B), sub-
stituted ‘‘section 4251(d)(1)’’ for ‘‘section 2366a(d)(2)’’.
2018—Subsec. (a)(1). Pub. L. 115–232, § 831(a)(1), (2), in
introductory provisions, substituted ‘‘designated mile-
stone decision authority for the program shall ensure,
by establishing the goals described in paragraph (2),
that the program’’ for ‘‘Secretary of Defense shall en-
sure, by establishing the goals described in paragraph
(2), that the milestone decision authority for the major
defense acquisition program approves a program that’’.
Subsecs. (b), (c). Pub. L. 115–232, § 831(a)(3), (4), redes-
ignated subsec. (c) as (b) and struck out former subsec.
(b). Prior to amendment, text of subsec. (b) read as fol-
lows: ‘‘The responsibilities of the Secretary of Defense
in subsection (a) may be delegated only to the Deputy
Secretary of Defense.’’
Statutory Notes and Related Subsidiaries
EFFECTIVE DATE OF 2021 AMENDMENT
Amendment by Pub. L. 117–81 applicable as if in-
cluded in the enactment of title XVIII of Pub. L. 116–283
as enacted, see section 1701(a)(2) of Pub. L. 117–81, set
out in a note preceding section 3001 of this title and
note below.
Amendment by Pub. L. 116–283 effective Jan. 1, 2022,
with additional provisions for delayed implementation
and applicability of existing law, see section 1801(d) of
Pub. L. 116–283, set out as a note preceding section 3001
of this title.
EFFECTIVE DATE
Pub. L. 114–328, div. A, title VIII, § 807(a)(2), Dec. 23,
2016, 130 Stat. 2261, provided that: ‘‘[Former] Sub-
chapter III of chapter 144B of title 10, United States
Code [see 10 U.S.C. 4271, 4272], as added by paragraph (1),
shall apply with respect to major defense acquisition
programs that reach Milestone A after October 1, 2017.’’
PROGRAM COST AND FIELD TARGETS
Pub. L. 114–328, div. A, title IX, § 925(b), Dec. 23, 2016,
130 Stat. 2361, as amended by Pub. L. 115–232, div. A,
title VIII, § 831(b)(4), Aug. 13, 2018, 132 Stat. 1857, pro-
vided that: ‘‘The Secretary of Defense shall establish a
process to develop program cost and fielding targets
pursuant to section 2448a of title 10, United States Code
[now 10 U.S.C. 4271], that—
‘‘(1) is co-chaired by the designated milestone deci-
sion authority for the major defense acquisition pro-
gram and the Vice Chief of Staff of the armed force
concerned or, in the case of a program for which an
alternate milestone decision authority is designated
under section 2430(d)(2) of such title [now 10 U.S.C.
4204(b)], the Vice Chairman of the Joint Chiefs of
Staff;
‘‘(2) is supported by—
‘‘(A) the Joint Staff, to provide expertise on joint
military capabilities, capability gaps, and perform-
ance requirements;
‘‘(B) the Office of Cost Assessment and Program
Evaluation, to provide expertise in resource alloca-
tion, operations research, systems analysis, and
cost estimation; and
‘‘(C) other Department of Defense organizations
determined appropriate by the Secretary; and
‘‘(3) ensures that appropriate trade-offs are made
among life-cycle cost, schedule, and performance ob-
jectives and procurement quantity objectives.’’
CONFIGURATION STEERING BOARDS FOR COST CONTROL
UNDER MAJOR DEFENSE ACQUISITION PROGRAMS
Pub. L. 110–417, [div. A], title VIII, § 814, Oct. 14, 2008,
122 Stat. 4528, as amended by Pub. L. 114–92, div. A, title
VIII, § 830, Nov. 25, 2015, 129 Stat. 912; Pub. L. 115–91, div.
A, title VIII, § 826, Dec. 12, 2017, 131 Stat. 1467; Pub. L.
116–92, div. A, title IX, § 902(67), Dec. 20, 2019, 133 Stat.
1550, provided that:
‘‘(a) CONFIGURATION
STEERING
BOARDS.—Each Sec-
retary of a military department shall establish one or
Page 2726
TITLE 10—ARMED FORCES
§ 4272
more boards (to be known as a ‘Configuration Steering
Board’) for the major defense acquisition programs of
such department.
‘‘(b) COMPOSITION.—
‘‘(1) CHAIR.—Each Configuration Steering Board
under this section shall be chaired by the service ac-
quisition executive of the military department con-
cerned.
‘‘(2) PARTICULAR
MEMBERS.—Each Configuration
Steering Board under this section shall include a rep-
resentative of the following:
‘‘(A) The Office of the Under Secretary of Defense
for Research and Engineering.
‘‘(B) The Office of the Under Secretary of Defense
for Acquisition and Sustainment.
‘‘(C) The Chief of Staff of the Armed Force con-
cerned.
‘‘(D) Other Armed Forces, as appropriate.
‘‘(E) The Joint Staff.
‘‘(F) The Comptroller of the military department
concerned.
‘‘(G) The military deputy to the service acquisi-
tion executive concerned.
‘‘(H) The program executive officer for the major
defense acquisition program concerned.
‘‘(I) Other senior representatives of the Office of
the Secretary of Defense and the military depart-
ment concerned, as appropriate.
‘‘(c) RESPONSIBILITIES.—
‘‘(1)
IN
GENERAL.—The
Configuration
Steering
Board for a major defense acquisition program under
this section shall be responsible for the following:
‘‘(A) Monitoring changes in program require-
ments and ensuring the Chief of Staff of the Armed
Force concerned, in consultation with the Sec-
retary of the military department concerned, ap-
proves of any proposed changes that could have an
adverse effect on program cost or schedule.
‘‘(B) Preventing unnecessary changes to program
requirements and system configuration that could
have an adverse impact on program cost or sched-
ule.
‘‘(C) Mitigating the adverse cost and schedule im-
pact of any changes to program requirements or
system configuration that may be required.
‘‘(D) Ensuring that the program delivers as much
planned capability as possible, at or below the rel-
evant program baseline.
‘‘(2)
DISCHARGE
OF
RESPONSIBILITIES.—In
dis-
charging its responsibilities under this section with
respect to a major defense acquisition program, a
Configuration Steering Board shall—
‘‘(A) review and approve or disapprove any pro-
posed changes to program requirements or system
configuration that have the potential to adversely
impact program cost or schedule; and
‘‘(B) review and recommend proposals to reduce
program requirements that have the potential to
improve program cost or schedule in a manner con-
sistent with program objectives.
‘‘(3) PRESENTATION OF RECOMMENDATIONS ON REDUC-
TION IN REQUIREMENTS.—Any recommendation for a
proposed reduction in requirements that is made by a
Configuration Steering Board under paragraph (2)(B)
shall be presented to appropriate organizations of the
Joint Staff and the military departments responsible
for such requirements for review and approval in ac-
cordance with applicable procedures.
‘‘(4) ANNUAL CONSIDERATION OF EACH MAJOR DEFENSE
ACQUISITION PROGRAM.—
‘‘(A) ANNUAL
MEETING.—Except as provided in
subparagraph (B), the Secretary of the military de-
partment concerned shall ensure that a Configura-
tion Steering Board under this section meets to
consider each major defense acquisition program of
such military department at least once each year.
‘‘(B) EXCEPTION.—If the service acquisition execu-
tive of the military department concerned deter-
mines, in writing, that there have been no changes
to the program requirements of a major defense ac-
quisition program during the preceding year, the
Configuration Steering Board for such major de-
fense acquisition program is not required to meet
as described in subparagraph (A).
‘‘(5) CERTIFICATION
OF
COST
AND
SCHEDULE
DEVI-
ATIONS
DURING
SYSTEM
DESIGN
AND
DEVELOPMENT.—
For a major defense acquisition program that re-
ceived an initial Milestone B approval during fiscal
year 2008, a Configuration Steering Board may not
approve any proposed alteration to program require-
ments or system configuration if such an alteration
would—
‘‘(A) increase the cost (including any increase for
expected inflation or currency exchange rates) for
system development and demonstration by more
than 25 percent; or
‘‘(B) extend the schedule for key events by more
than 15 percent of the total number of months be-
tween the award of the system development and
demonstration contract and the scheduled Mile-
stone C approval date,
unless the Under Secretary of Defense for Research
and Engineering and the Under Secretary of Defense
for Acquisition and Sustainment jointly certify to
the congressional defense committees [Committees
on Armed Services and Appropriations of the Senate
and the House of Representatives], and include in the
certification supporting rationale, that approving
such alteration to program requirements or system
configuration is in the best interest of the Depart-
ment of Defense despite the cost and schedule im-
pacts to system development and demonstration of
such program.
‘‘(d) APPLICABILITY.—
‘‘(1) IN GENERAL.—The requirements of this section
shall apply with respect to any major defense acquisi-
tion program that is commenced before, on, or after
the date of the enactment of this Act [Oct. 14, 2008].
‘‘(2) CURRENT PROGRAMS.—In the case of any major
defense acquisition program that is ongoing as of the
date of the enactment of this Act, a Configuration
Steering Board under this section shall be established
for such program not later than 60 days after the date
of the enactment of this Act.
‘‘(e) GUIDANCE
ON AUTHORITIES
OF PROGRAM MAN-
AGERS AFTER MILESTONE B.—
‘‘(1) [Amended section 853(d)(2) of Pub. L. 109–364,
formerly set out as a note under section 2430 of this
title.]
‘‘(2) APPLICABILITY.—The Secretary of Defense shall
modify the guidance described in section 853(d) of the
John Warner National Defense Authorization Act for
Fiscal Year 2007 [Pub. L. 109–364, formerly set out as
a note under section 2430 of this title] in order to
take into account the amendment made by paragraph
(1) not later than 60 days after the date of the enact-
ment of this Act [Oct. 14, 2008].
‘‘(f) MAJOR DEFENSE ACQUISITION PROGRAM DEFINED.—
In this section, the term ‘major defense acquisition
program’ has the meaning given that term in section
2430(a) of title 10, United States Code [now 10 U.S.C.
4201].’’
§ 4272. Independent technical risk assessments
(a) IN GENERAL.—With respect to a major de-
fense acquisition program, the Secretary of De-
fense shall conduct or approve independent tech-
nical risk assessments before any decision to
grant Milestone B approval for the program pur-
suant to section 4252 of this title, any decision
to enter into low-rate initial production or full-
rate production, or at any other time considered
appropriate by the Secretary, that includes the
identification of any critical technologies or
manufacturing processes that have not been suc-
cessfully demonstrated in a relevant environ-
ment.
(b) GUIDANCE.—The Secretary shall issue guid-
ance and a framework for the conduct, execu-
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Definition.—** Except as provided under subsection (b), in this part, the term “major defense acquisition program” means a Department of Defense acquisition program that is not a highly sensitive classified program (as determined by the Secretary of Defense) and—
(1) that is designated by the Secretary of Defense as a major defense acquisition program; or
(2) in the case of a program that is not a program for the acquisition of an automated information system (either a product or a service), that is estimated by the Secretary of Defense to require—
(A) an eventual total expenditure for research, development, test, and evaluation of more than $1,000,000,000 (based on fiscal year 2024 constant dollars); or
(B) an eventual total expenditure for procurement, including all planned increments or spirals, of more than $4,500,000,000 (based on fiscal year 2024 constant dollars).
**(b) Exceptions.—** In this part, the term “major defense acquisition program” does not include the following:
(1) An acquisition program or project that is carried out using the rapid fielding or rapid prototyping acquisition pathway under [section 3602 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section3602&num=0&edition=prelim).
(2) An acquisition program for a defense business system (as defined in [section 2222(i)(1) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section2222/i/1&num=0&edition=prelim)) carried out using the acquisition guidance issued pursuant to section 883(e) of the National Defense Authorization Act for Fiscal Year 2016 (Public Law 114–92; [10 U.S.C. 2223a](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section2223a&num=0&edition=prelim) note).11 See References in
Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 4201
Stored review status: release_metadata_unconfirmed. The source passage cites 10 U.S.C. § 4201. This identifies an authority to review, not proof of applicability.
Federal law — U.S. Code and appendices · legal_authorities
Page 2694
TITLE 10—ARMED FORCES
§ 4201
Sec.
4204.
Milestone decision authority.
4205.
Weapon systems for which procurement fund-
ing requested in budget: development and
procurement schedules.
Editorial Notes
PRIOR PROVISIONS
A prior chapter 321 ‘‘RESEARCH AND DEVELOP-
MENT GENERALLY’’, consisting of reserved section
4201, was repealed by Pub. L. 116–283, div. A, title XVIII,
§ 1841(a)(1)(A), Jan. 1, 2021, 134 Stat. 4242.
Statutory Notes and Related Subsidiaries
ENHANCED DOMESTIC CONTENT REQUIREMENT FOR
MAJOR DEFENSE ACQUISITION PROGRAMS
Pub. L. 118–31, div. A, title VIII, § 835, Dec. 22, 2023, 137
Stat. 338, provided that:
‘‘(a) ASSESSMENT REQUIRED.—
‘‘(1) IN GENERAL.—Not later than one year after the
date of the enactment of this Act [Dec. 22, 2023], the
Secretary of Defense shall submit to the congres-
sional defense committees [Committees on Armed
Services and Appropriations of the Senate and the
House of Representatives] a report assessing the do-
mestic source content of procurements carried out in
connection with a major defense acquisition program.
‘‘(2) INFORMATION
REPOSITORY.—The Secretary of
Defense shall establish an information repository for
the collection and analysis of information related to
domestic source content for products the Secretary
deems critical, where such information can be used
for continuous data analysis and program manage-
ment activities.
‘‘(b) ENHANCED DOMESTIC CONTENT REQUIREMENT.—
‘‘(1) IN GENERAL.—Except as provided in paragraph
(2), for purposes of chapter 83 of title 41, United
States Code, manufactured articles, materials, or
supplies procured in connection with a major defense
acquisition program are manufactured substantially
all from articles, materials, or supplies mined, pro-
duced, or manufac
Source: Supplied 2024 U.S. Code historical extraction · 10 U.S.C. § 4201
Stored review status: historical_2024_not_currentness_verified. The source passage cites 10 U.S.C. § 4201. This identifies an authority to review, not proof of applicability.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Service Acquisition Executive.—** The milestone decision authority for a major defense acquisition program reaching Milestone A after October 1, 2016, shall be the service acquisition executive of the military department that is managing the program, unless the Secretary of Defense designates, under subsection (b), another official to serve as the milestone decision authority.
**(b) Designation of Alternate Milestone Decision Authority.—** The Secretary of Defense may designate an alternate milestone decision authority for a program with respect to which any of the following applies:
(1) Subject to subsection (f), the Secretary determines that the program is addressing a joint requirement.
(2) The Secretary determines that the program is best managed by a Defense Agency.
(3) The program has incurred a unit cost increase greater than the significant cost threshold or critical cost threshold under sections 4371 through 4375 of this title.
(4) The program is critical to a major interagency requirement or technology development effort, or has significant international partner involvement.
(5) The Secretary determines that an alternate official serving as the milestone decision authority will best provide for the program to achieve desired cost, schedule, and performance outcomes.
**(c) Reversion to Service Acquisition Executive.—**
(1) After designating an alternate milestone decision authority under subsection (b) for a program, the Secretary of Defense may revert the position of milestone decision authority for the program back to the service acquisition executive upon request of the Secretary of the military department concerned. A decision on the request shall be made within 180 days after receipt of the request from the Secretary of the military departmen
Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 4204
Stored review status: release_metadata_unconfirmed. The source passage cites 10 U.S.C. § 4204. This identifies an authority to review, not proof of applicability.
Federal law — U.S. Code and appendices · legal_authorities
Page 2697
TITLE 10—ARMED FORCES
§ 4204
Jan. 1, 2021, 134 Stat. 4251; Pub. L. 117–81, div. A,
title XVII, § 1701(o)(6)(B)(ii), Dec. 27, 2021, 135
Stat. 2147.)
Editorial Notes
AMENDMENTS
2021—Pub. L. 116–283, § 1846(g)(2), substituted ‘‘this
subpart’’ for ‘‘this chapter’’ wherever appearing.
Pub. L. 116–283, § 1846(g), renumbered section 2430a of
this title as this section.
Subsec. (d). Pub. L. 116–283, § 1846(g)(1), as amended by
Pub. L. 117–81, § 1701(o)(6)(B)(ii), substituted ‘‘section
4351(a)’’ for ‘‘section 2432(a)’’ in introductory provi-
sions.
2016—Subsec. (a)(1)(B). Pub. L. 114–328, which directed
substitution of ‘‘major defense acquisition program re-
quires the delivery of two or more increments or
blocks’’ for ‘‘major defense acquisition program to pur-
chase satellites requires the delivery of satellites in
two or more increments or blocks’’ in par. (1)(B), was
executed by making the substitution in par. (1)(B) of
subsec. (a), to reflect the probable intent of Congress.
2011—Subsec. (a)(1). Pub. L. 112–81 designated existing
provisions as subpar. (A) and added subpar. (B).
Subsec. (b). Pub. L. 111–383 designated existing provi-
sions as par. (1), redesignated former pars. (1) and (2) as
subpars. (A) and (B), respectively, of par. (1), inserted
‘‘(other than as provided in paragraph (2))’’ before semi-
colon in subpar. (A), and added par. (2).
Statutory Notes and Related Subsidiaries
EFFECTIVE DATE OF 2021 AMENDMENT
Amendment by Pub. L. 117–81 applicable as if in-
cluded in the enactment of title XVIII of Pub. L. 116–283
as enacted, see section 1701(a)(2) of Pub. L. 117–81, set
out in a note preceding section 3001 of this title and
note below.
Amendment by Pub. L. 116–283 effective Jan. 1, 2022,
with additional provisions for delaye
Source: Supplied 2024 U.S. Code historical extraction · 10 U.S.C. § 4204
Stored review status: historical_2024_not_currentness_verified. The source passage cites 10 U.S.C. § 4204. This identifies an authority to review, not proof of applicability.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Program Cost and Fielding Targets.—**
(1) Before funds are obligated for technology development, systems development, or production of a major defense acquisition program, the designated milestone decision authority for the program shall ensure, by establishing the goals described in paragraph (2), that the program will—
(A) be affordable;
(B) incorporate program planning that anticipates the evolution of capabilities to meet changing threats, technology insertion, and interoperability; and
(C) be fielded when needed.
(2) The goals described in this paragraph are goals for—
(A) the procurement unit cost and sustainment cost (referred to in this section as the “program cost targets”);
(B) the date for initial operational capability (referred to in this section as the “fielding target”); and
(C) technology maturation, prototyping, and a modular open system approach to evolve system capabilities and improve interoperability.
**(b) Definitions.—** In this section:
(1) The term “procurement unit cost” has the meaning provided in [section 4351(a)(2) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section4351/a/2&num=0&edition=prelim).
(2) The term “initial capabilities document” has the meaning provided in [section 4251(d)(1) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section4251/d/1&num=0&edition=prelim).