Browse Arkansas Code titles and sections
33 U.S.C. § 2215 — Flood control and other purposes
Federal law — U.S. Code and appendices · legal_authorities
**(a) Flood control**
(1) **General rule** — The non-Federal interests for a project with costs assigned to flood control (other than a nonstructural project) shall—
(A) pay 5 percent of the cost of the project assigned to flood control during construction of the project;
(B) provide all lands, easements, rights-of-way, and dredged material disposal areas required only for flood control and perform all related necessary relocations; and
(C) provide that portion of the joint costs of lands, easements, rights-of-way, dredged material disposal areas, and relocations which is assigned to flood control.
(2) **35 percent minimum contribution** — If the value of the contributions required under paragraph (1) of this subsection is less than 35 percent of the cost of the project assigned to flood control, the non-Federal interest shall pay during construction of the project such additional amounts as are necessary so that the total contribution of the non-Federal interests under this subsection is equal to 35 percent of the cost of the project assigned to flood control.
(3) **50 percent maximum** — The non-Federal share under paragraph (1) shall not exceed 50 percent of the cost of the project assigned to flood control. The preceding sentence does not modify the requirement of paragraph (1)(A) of this subsection.
(4) **Deferred payment of amount exceeding 30 percent** — If the total amount of the contribution required under paragraph (1) of this subsection exceeds 30 percent of the cost of the project assigned to flood control, the non-Federal interests may pay the amount of the excess to the Secretary over a 15-year period (or such shorter period as may be agreed to by the Secretary and the non-Federal interests) beginning on the date construction of the project or
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2215
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: edc1926cc44d9f856407bedd4bbecec8cc5977298d09b58d81323a3ae003ccb0. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_7f0962f8aab845159a182656
Source file: Laws/federal/codes/united-states-code/title-33/section-2215-flood-control-and-other-purposes--9a6433bcbf.md
Pages: Not recorded – Not recorded
Passage SHA-256: 3fb3021eaf3d3b093c018898396c95b04467e674c5d6cab57d9e16fb2cfb7081
Source location: Title 33, Chapter 36, § 2215; chapter-036-water-resources-development.md
Stored source content
**(a) Flood control**
(1) **General rule** — The non-Federal interests for a project with costs assigned to flood control (other than a nonstructural project) shall—
(A) pay 5 percent of the cost of the project assigned to flood control during construction of the project;
(B) provide all lands, easements, rights-of-way, and dredged material disposal areas required only for flood control and perform all related necessary relocations; and
(C) provide that portion of the joint costs of lands, easements, rights-of-way, dredged material disposal areas, and relocations which is assigned to flood control.
(2) **35 percent minimum contribution** — If the value of the contributions required under paragraph (1) of this subsection is less than 35 percent of the cost of the project assigned to flood control, the non-Federal interest shall pay during construction of the project such additional amounts as are necessary so that the total contribution of the non-Federal interests under this subsection is equal to 35 percent of the cost of the project assigned to flood control.
(3) **50 percent maximum** — The non-Federal share under paragraph (1) shall not exceed 50 percent of the cost of the project assigned to flood control. The preceding sentence does not modify the requirement of paragraph (1)(A) of this subsection.
(4) **Deferred payment of amount exceeding 30 percent** — If the total amount of the contribution required under paragraph (1) of this subsection exceeds 30 percent of the cost of the project assigned to flood control, the non-Federal interests may pay the amount of the excess to the Secretary over a 15-year period (or such shorter period as may be agreed to by the Secretary and the non-Federal interests) beginning on the date construction of the project or separable element is completed, at an interest rate determined pursuant to [section 2216 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2216&num=0&edition=prelim). The preceding sentence does not modify the requirement of paragraph (1)(A) of this subsection.
**(b) Projects using nonstructural, natural, or nature-based features**
(1) **In general** — The non-Federal share of the cost of a flood risk management or hurricane and storm damage risk reduction measure using a nonstructural feature, or a natural feature or nature-based feature (as those terms are defined in [section 2289a(a) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2289a/a&num=0&edition=prelim)), shall be 35 percent of the cost of such measures. The non-Federal interests for any such measures shall be required to provide all lands, easements, rights-of-way, dredged material disposal areas, and relocations necessary for the project, but shall not be required to contribute any amount in cash during construction for a nonstructural feature if the costs of land, easements, rights-of-way, dredged material disposal areas, and relocations for such feature are estimated to exceed 35 percent.
(2) **Non-Federal contribution in excess of 35 percent** — At any time during construction of a project, if the Secretary determines that the costs of land, easements, rights-of-way, dredged material disposal areas, and relocations for the project, in combination with other costs contributed by the non-Federal interests, will exceed 35 percent, any additional costs for the project (not to exceed 65 percent of the total costs of the project) shall be a Federal responsibility and shall be contributed during construction as part of the Federal share.
**(c) Other purposes** The non-Federal share of the cost assigned to other project purposes shall be as follows:
(1) hydroelectric power: 100 percent, except that the marketing of such power and the recovery of costs of constructing, operating, maintaining, and rehabilitating such projects shall be in accordance with existing law: Provided, That after November 17, 1986, the Secretary shall not submit to Congress any proposal for the authorization of any water resources project that has a hydroelectric power component unless such proposal contains the comments of the appropriate Power Marketing Administrator designated pursuant to [section 7152 of title 42](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7152&num=0&edition=prelim) concerning the appropriate Power Marketing Administration’s ability to market the hydroelectric power expected to be generated and not required in the operation of the project under the applicable Federal power marketing law, so that, 100 percent of operation, maintenance and replacement costs, 100 percent of the capital investment allocated to the purpose of hydroelectric power (with interest at rates established pursuant to or prescribed by applicable law), and any other costs assigned in accordance with law for return from power revenues can be returned within the period set for the return of such costs by or pursuant to such applicable Federal power marketing law;
(2) municipal and industrial water supply: 100 percent;
(3) agricultural water supply: 35 percent;
(4) recreation, including recreational navigation: 50 percent of separable costs and, in the case of any harbor or inland harbor or channel project, 50 percent of joint and separable costs allocated to recreational navigation;
(5) hurricane and storm damage reduction: 35 percent;
(6) aquatic plant control: 50 percent of control operations; and
(7) environmental protection and restoration: 35 percent; except that nothing in this paragraph shall affect or limit the applicability of [section 2283 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2283&num=0&edition=prelim).
**(d) Certain other costs assigned to project purposes**
(1) **Construction** — Costs of constructing projects or measures for beach erosion control and water quality enhancement shall be assigned to appropriate project purposes listed in subsections (a), (b), and (c) and shall be shared in the same percentage as the purposes to which the costs are assigned, except that all costs assigned to benefits to privately owned shores (where use of such shores is limited to private interests) or to prevention of losses of private lands shall be borne by non-Federal interests and all costs assigned to the protection of federally owned shores shall be borne by the United States.
(2) **Periodic nourishment**
(A) *In general* — In the case of a project authorized for construction after December 31, 1999, except for a project for which a District Engineer’s Report is completed by that date, the non-Federal cost of the periodic nourishment of the project, or any measure for shore protection or beach erosion control for the project, that is carried out—
(i) after January 1, 2001, shall be 40 percent;
(ii) after January 1, 2002, shall be 45 percent; and
(iii) after January 1, 2003, shall be 50 percent.
(B) *Benefits to privately owned shores* — All costs assigned to benefits of periodic nourishment projects or measures to privately owned shores (where use of such shores is limited to private interests) or to prevention of losses of private land shall be borne by the non-Federal interest.
(C) *Benefits to federally owned shores* — All costs assigned to the protection of federally owned shores for periodic nourishment measures shall be borne by the United States.
**(e) Applicability**
(1) **In general** — This section applies to any project (including any small project which is not specifically authorized by Congress and for which the Secretary has not approved funding before November 17, 1986), or separable element thereof, on which physical construction is initiated after April 30, 1986, as determined by the Secretary, except as provided in paragraph (2). For the purpose of the preceding sentence, physical construction shall be considered to be initiated on the date of the award of a construction contract.
(2) **Exceptions** — This section shall not apply to the Yazoo Basin, Mississippi, Demonstration Erosion Control Program, authorized by Public Law 98–8, or to the Harlan, Kentucky, or Barbourville, Kentucky, elements of the project authorized by section 202 of Public Law 96–367.
**(f) “Separable element” defined** For purposes of this Act, the term “separable element” means a portion of a project—
(1) which is physically separable from other portions of the project; and
(2) which—
(A) achieves hydrologic effects, or
(B) produces physical or economic benefits,
which are separately identifiable from those produced by other portions of the project.
**(g) Deferral of payment**
(1) With respect to the projects listed in paragraph (2), no amount of the non-Federal share required under this section shall be required to be paid during the three-year period beginning on November 17, 1986.
(2) The projects referred to in paragraph (1) are the following:
(A) Boeuf and Tensas Rivers, Tensas Basin, Louisiana and Arkansas, authorized by the Flood Control Act of 1946;
(B) Eight Mile Creek, Arkansas, authorized by Public Law 99–88; and
(C) Rocky Bayou Area, Yazoo Backwater Area, Yazoo Basin, Mississippi, authorized by the Flood Control Act approved August 18, 1941.
**(h) Assigned joint and separable costs** The share of the costs specified under this section for each project purpose shall apply to the joint and separable costs of construction of each project assigned to that purpose, except as otherwise specified in this Act.
**(i) Lands, easements, rights-of-way, dredged material disposal areas, and relocations** Except as provided under [section 2283(c) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2283/c&num=0&edition=prelim), the non-Federal interests for a project to which this section applies shall provide all lands, easements, rights-of-way, and dredged material disposal areas required for the project and perform all necessary relocations, except to the extent limited by any provision of this section. The value of any contribution under the preceding sentence shall be included in the non-Federal share of the project specified in this section.
**(j) Agreement**
(1) **Requirement for agreement**
(A) *In general* — Any project to which this section applies (other than a project for hydroelectric power) shall be initiated only after non-Federal interests have entered into binding agreements with the Secretary to pay 100 percent of the operation, maintenance, and replacement and rehabilitation costs of the project, to pay the non-Federal share of the costs of construction required by this section, and to hold and save the United States free from damages due to the construction or operation and maintenance of the project, except for damages due to the fault or negligence of the United States or its contractors.
(B) *Inclusion* — An agreement under subparagraph (A) shall include a brief description and estimation of the anticipated operations, maintenance, and replacement and rehabilitation costs of the non-Federal interest for the project.
(2) **Elements of agreement** — The agreement required pursuant to paragraph (1) shall be in accordance with the requirements of [section 1962d–5b of title 42](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section1962d–5b&num=0&edition=prelim) and shall provide for the rights and duties of the United States and the non-Federal interest with respect to the construction, operation, and maintenance of the project, including, but not limited to, provisions specifying that, in the event the non-Federal interest fails to provide the required non-Federal share of costs for such work, the Secretary—
(A) shall terminate or suspend work on the project unless the Secretary determines that continuation of the work is in the interest of the United States or is necessary in order to satisfy agreements with other non-Federal interests in connection with the project; and
(B) may terminate or adjust the rights and privileges of the non-Federal interest to project outputs under the terms of the agreement.
**(k) Payment options**
(1) **In general** — Except as otherwise provided in this section, the Secretary may permit the full non-Federal contribution to be made without interest during construction of the project or separable element, or with interest at a rate determined pursuant to [section 2216 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2216&num=0&edition=prelim) over a period of not more than thirty years from the date of completion of the project or separable element. Repayment contracts shall provide for recalculation of the interest rate at five-year intervals.
(2) **Renegotiation of terms**
(A) *In general* — At the request of a non-Federal interest, the Secretary and the non-Federal interest may renegotiate the terms and conditions of an eligible deferred payment, including—
(i) permitting the non-Federal contribution to be made without interest, pursuant to paragraph (1);
(ii) recalculation of the interest rate;
(iii) full or partial forgiveness of interest accrued during the period of construction; and
(iv) a credit against construction interest for a non-Federal investment that benefits the completion or performance of the project or separable element.
(B) *Eligible deferred payment* — An eligible deferred payment agreement under subparagraph (A) is an agreement for which—
(i) the non-Federal contribution was made with interest;
(ii) the period of project construction exceeds 10 years from the execution of a project partnership agreement or appropriation of funds; and
(iii) the construction interest exceeds $45,000,000.
(3) **Credit for non-Federal contribution**
(A) *In general* — The Secretary is authorized to credit any costs incurred by the non-Federal interest (including in-kind contributions) to remedy a design or construction deficiency of a covered project or separable element toward the non-Federal share of the cost of the covered project, if the Secretary determines the remedy to be integral to the completion or performance of the covered project.
(B) *Credit of costs* — If the non-Federal interest incurs costs or in-kind contributions for a project to remedy a design or construction deficiency of a project or separable element which has a 100 percent Federal cost share, and the Secretary determines the remedy to be integral to the completion or performance of the project, the Secretary is authorized to credit such costs to any interest accrued on a deferred non-Federal contribution.
(4) **Treatment of pre-payment**
(A) *In general* — Notwithstanding a deferred payment agreement with a non-Federal interest, the Secretary shall accept, without interest of any type, the repayment of a non-Federal contribution for any eligible deferred payment described in paragraph (2)(B) for which—
(i) the non-Federal interest made a payment of at least $200,000,000 for that eligible deferred payment agreement on or before September 30, 2021;
(ii) the non-Federal interest made a payment of an additional $200,000,000 for that eligible deferred payment agreement on or before September 30, 2023; and
(iii) the non-Federal interest repays the balance of remaining principal by June 1, 2032.
(B) *Repayment options* — Repayment of a non-Federal interest’s contribution under subparagraph (A)(iii) may be satisfied through the provision by the non-Federal interest of fish and wildlife mitigation for one or more projects or separable elements, if the Secretary determines that—
(i) the non-Federal interest has incurred costs for the provision of mitigation that—
(I) equal or exceed the amount of the required repayment; and
(II) are in excess of any required non-Federal interest’s contribution for the project or separable element for which the mitigation is provided; and
(ii) the mitigation is integral to the project for which it is provided.
(C) *Refund of credit* — Any agreement made that applied credits to satisfy the terms of a pre-payment made under subsection (k)(4)(A) that resulted in total payment in excess of the amount now required under subsection (k)(4)(A) shall be modified to indicate that the excess credits continue to apply toward any remaining principal of the respective project, or at the request of the non-Federal interest, the agreement shall be modified to retroactively transfer back those excess credits to the non-Federal interest such that those credits may be applied by the non-Federal interest to any cost-shared project identified by the non-Federal interest.
(5) **Congressional notification**
(A) *In general* — Upon receipt of a request for a renegotiation of terms by a non-Federal interest under paragraph (2), the Secretary shall submit to the Committee on Transportation and Infrastructure of the House and the Committee on Environment and Public Works of the Senate a report 30 days after enactment and quarterly thereafter regarding the status of the request.
(B) *Sense of Congress* — It is the sense of Congress that the Secretary should respond to any request for a renegotiation of terms submitted under paragraph (2) in a timely manner.
**(l) Delay of payment**
(1) **Initial payment** — At the request of any non-Federal interest the Secretary may permit such non-Federal interest to delay the initial payment of any non-Federal contribution under this section or [section 2211 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2211&num=0&edition=prelim) for up to one year after the date when construction is begun on the project for which such contribution is to be made. Any such delay in initial payment shall be subject to interest charges for up to six months at a rate determined pursuant to [section 2216 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2216&num=0&edition=prelim).
(2) **Interest**
(A) *In general* — At the request of any non-Federal interest, the Secretary may waive the accrual of interest on any non-Federal cash contribution under this section or [section 2211 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2211&num=0&edition=prelim) for a project for a period of not more than 1 year if the Secretary determines that—
(i) the waiver will contribute to the ability of the non-Federal interest to make future contributions; and
(ii) the non-Federal interest is in good standing under terms agreed to under subsection (k)(1).
(B) *Limitations* — The Secretary may grant not more than 1 waiver under subparagraph (A) for the same project.
**(m) Ability to pay**
(1) **In general** — Any cost-sharing agreement under this section for a feasibility study, or for construction of an environmental protection and restoration project, a flood control project, a project for navigation, storm damage protection, shoreline erosion, hurricane protection, or recreation, or an agricultural water supply project, shall be subject to the ability of the non-Federal interest to pay.
(2) **Criteria** — The Secretary shall determine the ability of a non-Federal interest to pay under this subsection by considering—
(A) per capita income data for the county or counties in which the project is to be located;
(B) the per capita non-Federal cost of construction of the project for the county or counties in which the project is to be located;
(C) the financial capabilities of the non-Federal interest for the project;
(D) the extent to which the non-Federal interest is an economically disadvantaged community (as defined pursuant to section 160 of the Water Resources Development Act of 2020 ([33 U.S.C. 2201](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2201&num=0&edition=prelim) note)); and
(E) any additional criteria relating to the non-Federal interest’s financial ability to carry out its cost-sharing responsibilities determined appropriate by the Secretary.
(3) **Procedures** — For purposes of carrying out paragraph (2), the Secretary shall develop procedures—
(A) to allow a non-Federal interest to identify the amount such non-Federal interest would likely be able to pay; and
(B) for a non-Federal interest to submit a request to the Secretary to reduce the required non-Federal share.
(4) **Non-Federal share** — Notwithstanding subsection (a), the Secretary may reduce the requirement that a non-Federal interest make a cash contribution for any project that is determined to be eligible for a reduction in the non-Federal share under criteria and procedures in effect under paragraphs (1), (2), and (3).
(5) **Exception** — This subsection shall not apply to project costs greater than the national economic development plan.
(6) **Report**
(A) *In general* — Not less frequently than annually, the Secretary shall submit to the Committee on Transportation and Infrastructure of the House of Representatives and the Committee on Environment and Public Works of the Senate a report describing all determinations of the Secretary under this subsection regarding the ability of a non-Federal interest to pay.
(B) *Contents* — The Secretary shall include in each report required under subparagraph (A) a description, for the applicable year, of—
(i) requests by a non-Federal interest to reduce the non-Federal share required in a cost-sharing agreement, including—
(I) the name of the non-Federal interest that submitted to the Secretary a request for a determination under this subsection; and
(II) the name and location of the project;
(ii) the determination of the Secretary with respect to each such request;
(iii) the basis for each such determination; and
(iv) the adjusted share of the costs of the project of the non-Federal interest, if applicable.
(C) *Inclusion in chief’s report* — The Secretary may include a determination to reduce the non-Federal share required in a cost-sharing agreement for construction of a project in the report of the Chief of Engineers for the project.
**(n) Non-Federal contributions**
(1) **Prohibition on solicitation of excess contributions** — The Secretary may not—
(A) solicit contributions from non-Federal interests for costs of constructing authorized water resources projects or measures in excess of the non-Federal share assigned to the appropriate project purposes listed in subsections (a), (b), and (c); or
(B) condition Federal participation in such projects or measures on the receipt of such contributions.
(2) **Limitation on statutory construction** — Nothing in this subsection shall be construed to affect the Secretary’s authority under section 903(c).11 See References in Text note below.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) In general** In the case of a flood risk management or coastal storm risk management project in a region of moderate or high seismic hazard, for the purpose of a benefit-cost analysis for the project, the Secretary shall not include in that analysis any additional design and construction costs resulting from addressing seismic concerns.
**(b) Savings provision** Except with respect to the benefit-cost analysis, the additional costs referred to in subsection (a) shall be—
(1) included in the total project cost; and
(2) subject to cost-share requirements otherwise applicable to the project.
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2216
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
In any case in which a project under the jurisdiction of the Secretary is budgeted under a different business line than the business line under which the project was originally authorized, the Secretary shall ensure that the project is carried out in accordance with any requirements that apply to the business line under which the project was originally authorized.
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2201
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Resiliency assessment**
(1) **In general** — Not later than 180 days after December 27, 2020, and in conjunction with the development of procedures under [section 1962–4 of title 42](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section1962–4&num=0&edition=prelim), the Secretary is directed to review, and where appropriate, revise the existing planning guidance documents and regulations of the Corps of Engineers on the assessment of the effects of sea level rise or inland flooding on future water resources development projects to ensure that such guidance documents and regulations are based on the best available, peer-reviewed science and data on the current and future effects of sea level rise or inland flooding on relevant communities.
(2) **Coordination** — In carrying out this subsection, the Secretary shall—
(A) coordinate the review with the Engineer Research and Development Center, other Federal and State agencies, and other relevant entities; and
(B) to the maximum extent practicable and where appropriate, utilize data provided to the Secretary by such agencies.
**(b) Assessment of benefits from addressing sea level rise and inland flooding resiliency in feasibility reports**
(1) **In general** — Upon the request of a non-Federal interest, in carrying out a feasibility study for a project for flood risk mitigation, hurricane and storm damage risk reduction, or ecosystem restoration under [section 2282 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2282&num=0&edition=prelim), the Secretary shall consider whether the need for the project is predicated upon or exacerbated by conditions related to sea level rise or inland flooding.
(2) **Addressing sea level rise and inland flooding
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2283
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
For purposes of this Act, the term “Secretary” means the Secretary of the Army.
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2211
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Notwithstanding any other provision of law, jurisdiction over matters transferred to the Department of Energy from the Energy Research and Development Administration which on the effective date of such transfer were required by law, regulation, or administrative order to be made on the record after an opportunity for an agency hearing may be assigned to the Federal Energy Regulatory Commission or retained by the Secretary at his discretion.
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7152
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
The Council is authorized to delegate to any member or employee of the Council its administrative functions under [section 1962a–4 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section1962a-4&num=0&edition=prelim) and the detailed administration of the grant program under subchapter III.
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 1962d–5b
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Preparation of reports**
(1) **In general** — In the case of any water resources project-related study authorized to be undertaken by the Secretary that results in recommendations concerning a project or the operation of a project and that requires specific authorization by Congress in law or otherwise, the Secretary shall prepare a feasibility report, subject to [section 2215 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2215&num=0&edition=prelim).
(2) **Contents of feasibility reports** — A feasibility report shall describe, with reasonable certainty, the economic, environmental, and social benefits and detriments of the recommended plan and alternative plans considered by the Secretary and the engineering features (including hydrologic and geologic information), the public acceptability, and the purposes, scope, and scale of the recommended plan. A feasibility report shall also include the views of other Federal agencies and non-Federal agencies with regard to the recommended plan, a description of a nonstructural alternative to the recommended plan when such plan does not have significant nonstructural features, and a description of the Federal and non-Federal participation in such plan, and shall demonstrate that States, other non-Federal interests, and Federal agencies have been consulted in the development of the recommended plan. A feasibility report shall include a preliminary analysis of the Federal interest and the costs, benefits, and environmental impacts of the project.
(3) **Applicability** — This subsection shall not apply to—
(A) any study with respect to which a report has been submitted to Congress before November 17, 1986;
(B) any study for a project, which project is authorized for construc
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2282c
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) In general** Not later than February 1 of each year, the Secretary shall develop and submit to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives an annual report, to be entitled “Report to Congress on Future Water Resources Development”, that identifies the following:
(1) **Feasibility reports** — Each feasibility report that meets the criteria established in subsection (c)(1)(A).
(2) **Proposed feasibility studies** — Any proposed feasibility study submitted to the Secretary by a non-Federal interest pursuant to subsection (b) that meets the criteria established in subsection (c)(1)(A).
(3) **Proposed modifications** — Any proposed modification to an authorized water resources development project or feasibility study that meets the criteria established in subsection (c)(1)(A) that—
(A) is submitted to the Secretary by a non-Federal interest pursuant to subsection (b); or
(B) is identified by the Secretary for authorization.
(4) **Programmatic modifications** — Any programmatic modification for an environmental infrastructure assistance program.
**(b) Requests for proposals**
(1) **Publication** — Not later than May 1 of each year, the Secretary shall publish in the Federal Register a notice requesting proposals from non-Federal interests for proposed feasibility studies, proposed modifications to authorized water resources development projects and feasibility studies, and proposed modifications for an environmental infrastructure program to be included in the annual report.
(2) **Deadline for requests** — The Secretary shall include in each notice required by this subsection a requirement that non-Federal interests submit to the Secretary any proposals de
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2282f
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) In general** The Secretary may carry out studies and projects to—
(1) reduce flood and hurricane and storm damage hazards; or
(2) restore the natural functions and values of rivers and shorelines throughout the United States.
**(b) Studies and projects**
(1) **Authority**
(A) *Studies* — In carrying out subsection (a), the Secretary may carry out studies to identify appropriate measures for—
(i) the reduction of flood and hurricane and storm damage hazards, including measures for erosion mitigation and bank stabilization; or
(ii) the conservation and restoration of the natural functions and values of rivers and shorelines.
(B) *Projects* — Subject to subsection (f)(2), in carrying out subsection (a), the Secretary may design and implement projects described in subsection (a).
(2) **Consultation and coordination** — The studies and projects carried out under this section shall be conducted, to the maximum extent practicable, in consultation and coordination with the Federal Emergency Management Agency and other appropriate Federal agencies, and in consultation and coordination with appropriate State and local agencies and tribes.
(3) **Nonstructural approaches** — The studies and projects shall emphasize, to the maximum extent practicable and appropriate, nonstructural approaches to preventing or reducing flood and hurricane and storm damages, including the use of natural features or nature-based features.
(4) **Participation** — The studies and projects shall be conducted, to the maximum extent practicable, in cooperation with State and local agencies and tribes to ensure the coordination of local flood and hurricane and storm damage reduction or riverine, shoreline, and wetland restoration studies with projects that conserve, restore, and m
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2335
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Short title; Congressional declaration of intent**
(1) This section may be cited as the “Upper Mississippi River Management Act of 1986”.
(2) To ensure the coordinated development and enhancement of the Upper Mississippi River system, it is hereby declared to be the intent of Congress to recognize that system as a nationally significant ecosystem and a nationally significant commercial navigation system. Congress further recognizes that the system provides a diversity of opportunities and experiences. The system shall be administered and regulated in recognition of its several purposes.
**(b) Definitions** For purposes of this section—
(1) the terms “Upper Mississippi River system” and “system” mean those river reaches having commercial navigation channels on the Mississippi River main stem north of Cairo, Illinois; the Minnesota River, Minnesota; Black River, Wisconsin; Saint Croix River, Minnesota and Wisconsin; Illinois River and Waterway, Illinois; and Kaskaskia River, Illinois;
(2) the term “Master Plan” means the comprehensive master plan for the management of the Upper Mississippi River system, dated January 1, 1982, prepared by the Upper Mississippi River Basin Commission and submitted to Congress pursuant to Public Law 95–502;
(3) the term “GREAT I, GREAT II, and GRRM studies” means the studies entitled “GREAT Environmental Action Team—GREAT I—A Study of the Upper Mississippi River”, dated September 1980, “GREAT River Environmental Action Team—GREAT II—A Study of the Upper Mississippi River”, dated December 1980, and “GREAT River Resource Management Study”, dated September 1982; and
(4) the term “Upper Mississippi River Basin Association” means an association of the States of Illinois, Iowa, Minnesota, Missouri, and Wisconsin, formed for the purpos
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 652
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.