10 U.S.C. § 4252 — Major defense acquisition programs: fac-
Federal law — U.S. Code and appendices · legal_authorities
Page 2719
TITLE 10—ARMED FORCES
§ 4252
title VIII, § 813(e)(2)(B), Oct. 14, 2008, 122 Stat. 4528, pro-
vided that: ‘‘Section 2366b of title 10, United States
Code [now 10 U.S.C. 4251], as added by subsection (a),
shall apply to major defense acquisition programs on
and after March 1, 2008. In the case of the certification
required by [former] paragraph (2) of subsection (a) of
such section, during the period prior to the completion
of the first quadrennial roles and missions review re-
quired by [former] section 118b of title 10, United States
Code, the certification required by that paragraph shall
be that the system is being executed by an entity with
a relevant core competency as identified by the Sec-
retary of Defense.’’
ANALYSIS OF ALTERNATIVES PURSUANT TO MATERIEL
DEVELOPMENT DECISIONS
Pub. L. 116–92, div. A, title VIII, § 832, Dec. 20, 2019, 133
Stat. 1493, provided that:
‘‘(a) TIMELINE.—Not later than 180 days after the date
of the enactment of this Act [Dec. 20, 2019], the Sec-
retary of Defense shall update existing guidance for
analyses of alternatives conducted pursuant to a mate-
riel development decision for a major defense acquisi-
tion program to incorporate the following:
‘‘(1) Study completion within nine months.
‘‘(2) Study guidance issued by the Director, Cost
Assessment and Program Evaluation of a scope de-
signed to provide for reasonable completion of the
study within the nine-month period.
‘‘(3) Procedures for waiver of the timeline require-
ments of this subsection on a case-by-case basis if—
‘‘(A) the subject of the analysis is of extreme
technical complexity;
‘‘(B) collection of additional intelligence is re-
quired to inform the analysis;
‘‘(C) insufficient technical expertise is available
to complete the analysis; or
Source: Supplied 2024 U.S. Code historical extraction · 10 U.S.C. § 4252
Stored review status: historical_2024_not_currentness_verified. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: c8cdea79856e6962735586cd28293d33bbb91917a9868e6523da18a97dc75c50. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:usc2024-a6ab1f3783dfd151be9ac48d
Source file: Laws/federal/codes/united-states-code-2024/title-10/section-4252-major-defense-acquisition-programs-fac--86bbe758f5.md
Pages: Not recorded – Not recorded
Passage SHA-256: ab80aaf917af23783f82fa13baf8a76ed13eee25f0000851f32854459e3bf0d2
Source location: USCODE-2024-title10-subtitleA-partV-subpartF-chap322-subchapIII-sec4252.pdf
Stored source content
Page 2719
TITLE 10—ARMED FORCES
§ 4252
title VIII, § 813(e)(2)(B), Oct. 14, 2008, 122 Stat. 4528, pro-
vided that: ‘‘Section 2366b of title 10, United States
Code [now 10 U.S.C. 4251], as added by subsection (a),
shall apply to major defense acquisition programs on
and after March 1, 2008. In the case of the certification
required by [former] paragraph (2) of subsection (a) of
such section, during the period prior to the completion
of the first quadrennial roles and missions review re-
quired by [former] section 118b of title 10, United States
Code, the certification required by that paragraph shall
be that the system is being executed by an entity with
a relevant core competency as identified by the Sec-
retary of Defense.’’
ANALYSIS OF ALTERNATIVES PURSUANT TO MATERIEL
DEVELOPMENT DECISIONS
Pub. L. 116–92, div. A, title VIII, § 832, Dec. 20, 2019, 133
Stat. 1493, provided that:
‘‘(a) TIMELINE.—Not later than 180 days after the date
of the enactment of this Act [Dec. 20, 2019], the Sec-
retary of Defense shall update existing guidance for
analyses of alternatives conducted pursuant to a mate-
riel development decision for a major defense acquisi-
tion program to incorporate the following:
‘‘(1) Study completion within nine months.
‘‘(2) Study guidance issued by the Director, Cost
Assessment and Program Evaluation of a scope de-
signed to provide for reasonable completion of the
study within the nine-month period.
‘‘(3) Procedures for waiver of the timeline require-
ments of this subsection on a case-by-case basis if—
‘‘(A) the subject of the analysis is of extreme
technical complexity;
‘‘(B) collection of additional intelligence is re-
quired to inform the analysis;
‘‘(C) insufficient technical expertise is available
to complete the analysis; or
‘‘(D) the Secretary determines that there [are]
other sufficient reasons for delay of the analysis.
‘‘(b) REPORTING.—If an analysis of alternatives can-
not be completed within the allotted time, or a waiver
is used, the Secretary shall report to the congressional
defense committees [Committees on Armed Services
and Appropriations of the Senate and the House of Rep-
resentatives] the following information:
‘‘(1) For a waiver, the basis for use of the waivers,
including the reasons why the study cannot be com-
pleted within the allotted time.
‘‘(2) For a study estimated to take more than nine
months—
‘‘(A) an estimate of when the analysis will be
completed;
‘‘(B) an estimate of any additional costs to com-
plete the analysis; and
‘‘(C) other relevant information pertaining to the
analysis and its completion.
‘‘(c) REPORT ON ANALYSES OF ALTERNATIVES.—
‘‘(1) ASSESSMENT.—
‘‘(A) IN
GENERAL.—The Under Secretary of De-
fense for Acquisition and Sustainment shall engage
with an independent entity, including under the
Program for Acquisition Innovation Research, to
assess the conduct of analyses of alternatives.
‘‘(B) ELEMENTS.—The assessment required under
subparagraph (A) shall—
‘‘(i) assess the time required to complete anal-
yses of alternatives within the Department of De-
fense completed over the last five fiscal years, as
compared with best practices;
‘‘(ii) provide recommendations and policy op-
tions to improve analyses of alternatives; and
‘‘(iii) discuss any other matters as identified by
the Under Secretary.
‘‘(C) ACCESS TO DATA.—The Under Secretary shall
ensure that the independent entity is provided ac-
cess to the data, information, and resources nec-
essary to complete the required analyses and as-
sessment.
‘‘(2) REPORT.—Not later than one year after the
date of the enactment of this Act, the Under Sec-
retary shall submit to the congressional defense com-
mittees a report including the assessment required
under paragraph (1) and a review and assessment by
the Under Secretary of the findings made in the as-
sessment.’’
MILESTONE A DECISIONS
Pub. L. 114–92, div. A, title VIII, § 802(d)(2), Nov. 25,
2015, 129 Stat. 880, provided that: ‘‘The Chief of the
Armed Force concerned shall advise the milestone deci-
sion authority for a major defense acquisition program
of the Chief’s views on cost, schedule, technical feasi-
bility, and performance trade-offs that have been made
with regard to the program, as provided in section
2366a(a)(2) of title 10, United States Code [now 10 U.S.C.
4251(a)(2)], as amended by section 823 of this Act, prior
to a Milestone A decision on the program.’’
GUIDANCE
Pub. L. 112–81, div. A, title VIII, § 801(d), Dec. 31, 2011,
125 Stat. 1483, provided that: ‘‘Not later than 120 days
after the date of the enactment of this Act [Dec. 31,
2011], the Secretary of Defense shall issue guidance im-
plementing the amendments made by subsections (a)
and (b) [amending this section and section 2366b of this
title], and subsection (c) [set out as a note preceding
section 4321 of this title], in a manner that is con-
sistent across the Department of Defense.’’
§ 4252. Major defense acquisition programs: fac-
tors to be considered before Milestone B ap-
proval
(a) RESPONSIBILITIES.—Before granting Mile-
stone B approval for a major defense acquisition
program or major subprogram, the milestone de-
cision authority for the program or subprogram
shall ensure that—
(1) information about the program or subpro-
gram is sufficient to warrant entry of the pro-
gram or subprogram into the engineering and
manufacturing development phase;
(2) appropriate trade-offs among cost, sched-
ule, technical feasibility, and performance ob-
jectives have been made to ensure that the
program or subprogram is affordable when
considering the per-unit cost and the total
life-cycle cost, and the Secretary of the mili-
tary department concerned and the Chief of
the armed force concerned concur with these
trade-offs; and
(3) there are sound plans for progression of
the program or subprogram to the production
phase.
(b) FACTORS TO BE CONSIDERED FOR MILESTONE
B APPROVAL.—A major defense acquisition pro-
gram or major subprogram may not receive
Milestone B approval until the milestone deci-
sion authority confirms the following factors
were considered in the decision to grant Mile-
stone B approval:
(1) The program or subprogram has received
a preliminary design review and a formal post-
preliminary design review or an equivalent as-
sessment was conducted.
(2) The technology in the program or subpro-
gram has been demonstrated in a relevant en-
vironment.
(3) The program or subprogram is affordable
when considering the ability of the Depart-
ment of Defense to accomplish the program’s
or subprogram’s general mission using alter-
native systems.
(4) Reasonable lifecycle cost and schedule es-
timates have been developed to execute, with
Page 2720
TITLE 10—ARMED FORCES
§ 4252
the concurrence of the Director of Cost Assess-
ment and Program Evaluation, the plan under
the program or subprogram.
(5) The estimated procurement unit cost for
the program or subprogram and the estimated
date for initial operational capability for the
baseline description for the program or sub-
program (under section 4214 of this title) have
been established.
(6) Funding is expected to be available to
execute the product development and produc-
tion plan for the program or subprogram, con-
sistent with the estimates described in para-
graph (4) for the program or subprogram.
(7) Appropriate market research has been
conducted prior to technology development,
including market research of commercial
products,
commercial
services,
and
non-
developmental items (as defined in section 110
of title 41).
(8) The Department of Defense has com-
pleted an analysis of alternatives with respect
to the program or subprogram, or in lieu of an
analysis of alternatives, early experimen-
tation with a combatant commander has been
conducted.
(9) The Joint Requirements Oversight Coun-
cil has accomplished its duties with respect to
the program or subprogram pursuant to sec-
tion 181(b) of this title, including an analysis
of the operational requirements for the pro-
gram or subprogram.
(10) Life-cycle sustainment planning has
identified and evaluated relevant sustainment
cost elements, factors, risks, and gaps that are
likely to drive readiness of the system as well
as operating and supporting costs.
(11) An estimate has been made of the re-
quirements for core logistics capabilities and
the associated sustaining workloads required
to support such requirements.
(12) The program or subprogram complies
with all relevant policies, regulations, and di-
rectives of the Department of Defense.
(13) Appropriate actions are planned for the
acquisition of technical data required to sup-
port the program or subprogram.
(14) The program or subprogram has an ap-
proved life cycle sustainment plan required
under section 4324(b) of this title.
(15) In the case of a naval vessel program or
subprogram, such program or subprogram is in
compliance with the requirements of section
8669b of this title.
(c) WRITTEN RECORD OF MILESTONE DECISION.—
The milestone decision authority shall issue a
written record of decision at the time that Mile-
stone B approval is granted. The record shall
confirm compliance with subsection (b) and spe-
cifically state that the milestone decision au-
thority considered the factors described in sub-
section (b) prior to the decision to grant mile-
stone approval. The milestone decision author-
ity shall retain records of the basis for the mile-
stone decision.
(d) CHANGES
TO
BASIS
FOR
MILESTONE
AP-
PROVAL.—(1) The program manager for a major
defense acquisition program that has received a
written record of the milestone decision under
subsection (c) shall immediately notify the
milestone decision authority of any changes to
the program or a designated major subprogram
of such program that—
(A) alter the substantive basis for the deci-
sion of the milestone decision authority relat-
ing to any component of such decision speci-
fied in subsection (b); or
(B) otherwise cause the program or subpro-
gram to deviate significantly from the mate-
rial provided to the milestone decision author-
ity in support of such decision.
(2) Upon receipt of information under para-
graph (1), the milestone decision authority may
rescind Milestone B approval if the milestone
decision authority determines that such ap-
proval is no longer valid.
(e) SUBMISSIONS
TO CONGRESS
ON MILESTONE
B.—
(1) NOTIFICATION.—Not later than 15 days
after granting Milestone B approval for a
major defense acquisition program or major
subprogram, the milestone decision authority
for the program or subprogram shall provide
to the congressional defense committees and,
in the case of intelligence or intelligence-re-
lated activities, the congressional intelligence
committees a written record of the milestone
decision.
(2) ADDITIONAL INFORMATION.—(A) At the re-
quest of any of the congressional defense com-
mittees or, in the case of intelligence or intel-
ligence-related activities, the congressional
intelligence committees, the milestone deci-
sion authority shall submit to the committee
an explanation of the basis for the decision to
grant Milestone B approval with respect to a
major defense acquisition program or major
subprogram, or further information or under-
lying documentation.
(B) The explanation or additional informa-
tion shall be submitted in unclassified form,
but may include a classified annex.
(f) DEFINITIONS.—In this section:
(1) The term ‘‘milestone decision authority’’,
with respect to a major defense acquisition
program, means the official within the Depart-
ment of Defense designated with the overall
responsibility and authority for acquisition
decisions for the program, including authority
to approve entry of the program into the next
phase of the acquisition process.
(2) The term ‘‘Milestone B approval’’ has the
meaning
provided
that
term
in
section
4172(e)(7) of this title.
(3) The term ‘‘core logistics capabilities’’
means the core logistics capabilities identified
under section 2464(a) of this title.
(4) The term ‘‘congressional intelligence
committees’’ has the meaning given that term
in section 437(c) of this title.
(5) The term ‘‘written record of milestone
decision’’, with respect to a major defense ac-
quisition program or a major subprogram,
means a document signed by the milestone de-
cision authority that formalizes approved
entry of the program or subprogram into the
next phase of the acquisition process.
(Added Pub. L. 109–163, div. A, title VIII, § 801(a),
Jan. 6, 2006, 119 Stat. 3366, § 2366a; amended Pub.
L. 109–364, div. A, title VIII, § 805, Oct. 17, 2006,
120 Stat. 2314; Pub. L. 110–181, div. A, title VIII,
Page 2721
TITLE 10—ARMED FORCES
§ 4252
§ 812, Jan. 28, 2008, 122 Stat. 219; renumbered
§ 2366b, Pub. L. 110–417, [div. A], title VIII,
§ 813(a), (b), Oct. 14, 2008, 122 Stat. 4527; Pub. L.
111–23, title I, § 101(d)(4), title II, §§ 201(f), 205(a),
May 22, 2009, 123 Stat. 1710, 1720, 1724; Pub. L.
111–383, div. A, title VIII, §§ 813(d)(1), 814(c), title
IX, § 901(j)(4), title X, § 1075(k)(1), Jan. 7, 2011, 124
Stat. 4265, 4266, 4324, 4378; Pub. L. 112–81, div. A,
title VIII, §§ 801(b), (e)(2), 819(b), Dec. 31, 2011, 125
Stat. 1483, 1484, 1501; Pub. L. 112–239, div. A, title
III, § 322(e)(2), title IX, § 904(e)(2), Jan. 2, 2013, 126
Stat. 1695, 1867; Pub. L. 113–66, div. A, title VIII,
§§ 821(a), 822(a), title X, § 1091(b)(1), Dec. 26, 2013,
127 Stat. 809, 876; Pub. L. 114–92, div. A, title
VIII, § 824(a), Nov. 25, 2015, 129 Stat. 903; Pub. L.
114–328, div. A, title VIII, §§ 805(a)(3), 807(e),
808(b), 843, Dec. 23, 2016, 130 Stat. 2255, 2262, 2263,
2290; Pub. L. 115–91, div. A, title VIII, §§ 835(b)(1),
838(a)(1), Dec. 12, 2017, 131 Stat. 1471, 1474; Pub. L.
115–232, div. A, title VIII, § 831(b)(3), Aug. 13, 2018,
132 Stat. 1857; Pub. L. 116–92, div. A, title VIII,
§ 833, Dec. 20, 2019, 133 Stat. 1494; renumbered
§ 4252 and amended Pub. L. 116–283, div. A, title
VIII, § 802(b), title XVIII, §§ 1847(d)(2), 1883(b)(2),
Jan. 1, 2021, 134 Stat. 3732, 4255, 4294; Pub. L.
117–81, div. A, title XVII, § 1701(o)(6)(C)(iii), Dec.
27, 2021, 135 Stat. 2147; Pub. L. 118–159, div. A,
title VIII, § 807, Dec. 23, 2024, 138 Stat. 1974.)
Editorial Notes
AMENDMENTS
2024—Pub. L. 118–159, § 807(1), substituted ‘‘factors to
be considered before’’ for ‘‘certification required be-
fore’’ in section catchline.
Subsec. (a). Pub. L. 118–159, § 807(4), added subsec. (a).
Former subsec. (a) redesignated (b).
Subsec. (b). Pub. L. 118–159, § 807(3), (5), redesignated
subsec. (a) as (b) and amended it generally. Prior to
amendment, subsec. related to certifications and deter-
minations required for Milestone B approval.
Subsec. (c). Pub. L. 118–159, § 807(6), added subsec. (c).
Former subsec. (c) redesignated (e).
Subsec. (d). Pub. L. 118–159, § 807(7)(A), substituted
‘‘Basis for Milestone Approval’’ for ‘‘Certifications or
Determination’’ in heading.
Pub. L. 118–159, § 807(2), (3), redesignated subsec. (b) as
(d) and struck out former subsec. (d) which related to
waiver of the certification and determination require-
ments to a major defense acquisition program in order
to meet critical national security objectives.
Subsec. (d)(1). Pub. L. 118–159, § 807(7)(B)(i), in intro-
ductory provisions, substituted ‘‘a written record of the
milestone decision under subsection (c)’’ for ‘‘certifi-
cations or a determination under subsection (a)’’.
Subsec. (d)(1)(A). Pub. L. 118–159, § 807(7)(B)(ii), sub-
stituted ‘‘decision of the milestone decision authority’’
for ‘‘certifications or determination of the milestone
decision authority’’ and ‘‘decision specified in sub-
section (b)’’ for ‘‘certifications or determination speci-
fied in paragraph (1), (2), or (3) of subsection (a)’’.
Subsec. (d)(1)(B). Pub. L. 118–159, § 807(7)(B)(iii), sub-
stituted ‘‘such decision’’ for ‘‘such certifications or de-
termination’’.
Subsec. (d)(2). Pub. L. 118–159, § 807(7)(C), struck out
‘‘withdraw the certifications or determination con-
cerned or’’ after ‘‘milestone decision authority may’’
and substituted ‘‘approval is’’ for ‘‘certifications, deter-
mination, or approval are’’.
Subsec. (e). Pub. L. 118–159, § 807(3), (8), redesignated
subsec. (c) as (e) and amended it generally. Prior to
amendment, subsec. related to submission to Congress
of brief summary reports on Milestone B. Former sub-
sec. (e) struck out.
Pub. L. 118–159, § 807(2), struck out subsec. (e). Text
read as follows: ‘‘Any budget request, budget justifica-
tion material, budget display, reprogramming request,
Selected Acquisition Report, or other budget docu-
mentation or performance report submitted by the Sec-
retary of Defense to the President regarding a major
defense acquisition program receiving a waiver pursu-
ant to subsection (d) shall prominently and clearly in-
dicate that such program has not fully satisfied the
certification requirements of this section until such
time as the milestone decision authority makes the de-
termination that such program has satisfied all such
certification requirements.’’
Subsec. (f). Pub. L. 118–159, § 807(2), (3), redesignated
subsec. (g) as (f) and struck out former subsec. (f). Prior
to amendment, text of subsec. (f) read as follows: ‘‘The
milestone decision authority may not delegate the cer-
tification requirement under subsection (a) or the au-
thority to waive any component of such requirement
under subsection (d).’’
Subsec. (f)(4) to (6). Pub. L. 118–159, § 807(9), added par.
(5), redesignated par. (6) as (4), and struck out former
pars. (4) and (5) which defined the terms fielding target
and major system component, respectively.
2021—Pub. L. 116–283, § 1847(d)(2)(A), renumbered sec-
tion 2366b of this title as this section.
Subsec. (a)(2). Pub. L. 116–283, § 1847(d)(2)(B)(i), sub-
stituted ‘‘section 4272’’ for ‘‘section 2448b’’.
Subsec. (a)(3)(D). Pub. L. 116–283, § 1847(d)(2)(B)(ii)(I),
substituted ‘‘section 4214 of this title’’ for ‘‘section
2435’’ and ‘‘section 4271(a)’’ for ‘‘section 2448a(a)’’.
Subsec. (a)(3)(N). Pub. L. 116–283, § 1847(d)(2)(B)(ii)(II),
substituted ‘‘section 4402(e)’’ for ‘‘section 2446b(e)’’.
Pub. L. 116–283, § 802(b)(1)(A), struck out ‘‘and’’ after
‘‘met;’’.
Subsec. (a)(3)(O). Pub. L. 116–283, § 802(b)(1)(B), which
directed amendment of subpar. (O) by substituting
‘‘; and’’ for period at the end, was executed by making
the substitution for semicolon at end to reflect the
probable intent of Congress.
Subsec. (a)(3)(P). Pub. L. 116–283, § 1883(b)(2), sub-
stituted ‘‘section 4324(b)’’ for ‘‘section 2337(b)’’.
Pub. L. 116–283, § 802(b)(1)(C), added subpar. (P).
Subsec. (c)(1)(A). Pub. L. 116–283, § 1847(d)(2)(C)(i)(I),
substituted ‘‘section 4271(a)’’ for ‘‘section 2448a(a)’’.
Subsec. (c)(1)(C). Pub. L. 116–283, § 1847(d)(2)(C)(i)(II),
substituted ‘‘section 3221(b)(6)’’ for ‘‘section 2334(a)(6)’’
in introductory provisions.
Subsec. (c)(1)(E). Pub. L. 116–283, § 1847(d)(2)(C)(i)(III),
substituted ‘‘section 4272’’ for ‘‘section 2448b’’.
Subsec. (c)(1)(H). Pub. L. 116–283, § 1883(b)(2), sub-
stituted ‘‘section 4324’’ for ‘‘section 2337’’.
Pub. L. 116–283, § 802(b)(2)(B), added subpar. (H).
Former subpar. (H) redesignated (I).
Subsec. (c)(1)(I). Pub. L. 116–283, § 802(b)(2)(A), redesig-
nated subpar. (H) as (I).
Subsec. (c)(2)(A). Pub. L. 116–283, § 1847(d)(2)(C)(ii), as
amended by Pub. L. 117–81, § 1701(o)(6)(C)(iii), sub-
stituted ‘‘section 4351’’ for ‘‘section 2432’’.
Subsec. (d)(3). Pub. L. 116–283, § 1847(d)(2)(D), sub-
stituted ‘‘section 4377’’ for ‘‘section 2433a(c)’’ in intro-
ductory provisions.
Subsec. (g)(1). Pub. L. 116–283, § 1847(d)(2)(E)(i), redes-
ignated par. (3) as (1) and struck out former par. (1)
which defined ‘‘major defense acquisition program’’.
Subsec. (g)(2). Pub. L. 116–283, § 1847(d)(2)(E)(i), (ii), re-
designated
par.
(4)
as
(2),
substituted
‘‘section
4172(e)(7)’’ for ‘‘section 2366(e)(7)’’, and struck out
former par. (2) which defined ‘‘designated major subpro-
gram’’.
Subsec. (g)(3). Pub. L. 116–283, § 1847(d)(2)(E)(i), redes-
ignated par. (5) as (3). Former par. (3) redesignated (1).
Subsec. (g)(4). Pub. L. 116–283, § 1847(d)(2)(E)(i), (iii),
redesignated par. (6) as (4) and substituted ‘‘section
4271(a)’’ for ‘‘section 2448a(a)’’. Former par. (4) redesig-
nated (2).
Subsec. (g)(5). Pub. L. 116–283, § 1847(d)(2)(E)(i), (iv),
redesignated par. (7) as (5) and substituted ‘‘section
4401(b)(3)’’ for ‘‘section 2446a(b)(3)’’. Former par. (5) re-
designated (3).
Subsec. (g)(6) to (8). Pub. L. 116–283, § 1847(d)(2)(E)(i),
redesignated pars. (6) to (8) as (4) to (6), respectively.
Page 2722
TITLE 10—ARMED FORCES
§ 4252
2019—Subsec. (a)(5). Pub. L. 116–92 added par. (5).
2018—Subsec. (a)(3)(D). Pub. L. 115–232, § 831(b)(3)(A),
struck out ‘‘Secretary of Defense after a request for
such increase or delay by the’’ before ‘‘milestone deci-
sion authority’’.
Subsec. (c)(1)(A). Pub. L. 115–232, § 831(b)(3)(B), struck
out ‘‘by the Secretary of Defense’’ after ‘‘established’’.
2017—Subsec. (a)(3)(O). Pub. L. 115–91, § 835(b)(1), added
subpar. (O).
Subsec. (c)(1)(G), (H). Pub. L. 115–91, § 838(a)(1), added
subpar. (G) and redesignated former subpar. (G) as (H).
2016—Subsec. (a)(2). Pub. L. 114–328, § 807(e)(1), sub-
stituted ‘‘technical risk assessment conducted under
section 2448b of this title’’ for ‘‘assessment by the As-
sistant Secretary of Defense for Research and Engi-
neering, in consultation with the Deputy Assistant
Secretary of Defense for Developmental Test and Eval-
uation’’.
Subsec. (a)(3)(B). Pub. L. 114–328, § 843(1), substituted
‘‘life-cycle cost;’’ for ‘‘acquisition cost in the context of
the total resources available during the period covered
by the future-years defense program submitted during
the fiscal year in which the certification is made;’’.
Subsec. (a)(3)(C). Pub. L. 114–328, § 807(e)(2)(A), struck
out ‘‘and’’ at end.
Subsec. (a)(3)(D). Pub. L. 114–328, § 807(e)(2)(C), added
subpar. (D). Former subpar. (D) redesignated (E).
Subsec. (a)(3)(E). Pub. L. 114–328, § 843(2), which di-
rected amendment of subpar. (D) by substituting ‘‘fund-
ing is expected to be available to execute the product
development and production plan for the program,’’ for
‘‘funding is’’ and all that followed through ‘‘made,’’,
was executed by making the substitution for ‘‘funding
is available to execute the product development and
production plan under the program, through the period
covered by the future-years defense program submitted
during the fiscal year in which the certification is
made,’’ in subpar. (E), to reflect the probable intent of
Congress and the amendment by Pub. L. 114–328,
§ 807(e)(2)(B). See below.
Pub. L. 114–328, § 807(e)(2)(B), redesignated subpar. (D)
as (E). Former subpar. (E) redesignated (F).
Subsec. (a)(3)(F) to (L). Pub. L. 114–328, § 807(e)(2)(B),
redesignated subpars. (E) to (K) as (F) to (L), respec-
tively. Former subpar. (L) redesignated (M).
Subsec. (a)(3)(M). Pub. L. 114–328, § 807(e)(2)(B), redes-
ignated subpar. (L) as (M). Former subpar. (M) redesig-
nated (N).
Pub. L. 114–328, § 805(a)(3), added subpar. (M).
Subsec. (a)(3)(N). Pub. L. 114–328, § 807(e)(2)(B), redes-
ignated subpar. (M) as (N).
Subsec. (c). Pub. L. 114–328, § 808(b)(1), amended sub-
sec. (c) generally. Prior to amendment, text read as fol-
lows:
‘‘(1) The certifications and determination under sub-
section (a) with respect to a major defense acquisition
program shall be submitted to the congressional de-
fense committees with the first Selected Acquisition
Report submitted under section 2432 of this title after
completion of the certification.
‘‘(2) The milestone decision authority shall retain
records of the basis for the certifications and deter-
mination under paragraphs (1), (2), and (3) of subsection
(a).
‘‘(3) At the request of any of the congressional de-
fense committees, the Secretary of Defense shall sub-
mit to the committee an explanation of the basis for
the certifications and determination under paragraphs
(1), (2), and (3) of subsection (a) with respect to a major
defense acquisition program. The explanation shall be
submitted in unclassified form, but may include a clas-
sified annex.’’
Subsec. (g)(6) to (8). Pub. L. 114–328, § 808(b)(2), added
pars. (6) to (8).
2015—Pub. L. 114–92 amended section generally. Prior
to amendment, section related to certification required
before Milestone B approval of major defense acquisi-
tion programs.
2013—Subsec. (a)(3)(D). Pub. L. 112–239, § 904(e)(2), sub-
stituted ‘‘the Assistant Secretary of Defense for Re-
search and Engineering, in consultation with the Dep-
uty Assistant Secretary of Defense for Developmental
Test and Evaluation’’ for ‘‘the Assistant Secretary of
Defense for Research and Engineering’’.
Subsec. (a)(3)(F). Pub. L. 112–239, § 322(e)(2), as amend-
ed by Pub. L. 113–66, § 1091(b)(1), substituted ‘‘core logis-
tics capabilities’’ for ‘‘core depot-level maintenance
and repair capabilities, as well as the associated logis-
tics capabilities’’.
Subsec. (a)(3)(G), (H). Pub. L. 113–66, § 821(a), added
subpar. (G) and redesignated former subpar. (G) as (H).
Subsec. (a)(4). Pub. L. 113–66, § 822(a), added par. (4).
2011—Pub. L. 112–81, § 801(e)(2)(A), struck out ‘‘or Key
Decision Point B’’ after ‘‘Milestone B’’ in section
catchline.
Subsec. (a). Pub. L. 112–81, § 801(e)(2)(B), struck out
‘‘, or Key Decision Point B approval in the case of a
space program,’’ after ‘‘Milestone B approval’’ in intro-
ductory provisions.
Subsec. (a)(3)(D). Pub. L. 111–383, § 901(j)(4), sub-
stituted ‘‘Assistant Secretary of Defense for Research
and Engineering’’ for ‘‘Director of Defense Research
and Engineering’’.
Subsec. (a)(3)(E) to (G). Pub. L. 112–81, § 801(b)(1),
added subpars. (E) and (F) and redesignated former sub-
par. (E) as (G).
Subsec. (b)(1). Pub. L. 111–383, § 814(c)(1)(A), sub-
stituted ‘‘any changes to the program or a designated
major subprogram of such program’’ for ‘‘any changes
to the program’’ in introductory provisions.
Subsec. (b)(1)(B). Pub. L. 111–383, § 814(c)(1)(B), sub-
stituted ‘‘otherwise cause the program or subprogram’’
for ‘‘otherwise cause the program’’.
Subsec. (b)(2). Pub. L. 112–81, § 801(e)(2)(C), struck out
‘‘(or Key Decision Point B approval in the case of a
space program)’’ after ‘‘Milestone B approval’’.
Subsec. (d)(1). Pub. L. 112–81, § 801(e)(2)(C), struck out
‘‘(or Key Decision Point B approval in the case of a
space program)’’ after ‘‘Milestone B approval’’ in two
places.
Pub. L. 111–383, § 813(d)(1)(A), substituted ‘‘(as speci-
fied in paragraph (1), (2), or (3) of subsection (a))’’ for
‘‘(as specified in paragraph (1) or (2) of subsection (a))’’.
Subsec. (d)(2)(B). Pub. L. 111–383, § 1075(k)(1), which di-
rected amendment of directory language of Pub. L.
111–23, § 205(a)(1)(B), resulting in substitution of ‘‘para-
graphs (1), (2), and (3)’’ for ‘‘paragraphs (1) and (2)’’ in
text, was not executed because of the prior identical
amendment by Pub. L. 111–383, § 813(d)(1)(B). See below.
Pub. L. 111–383, § 813(d)(1)(B), substituted ‘‘specified in
paragraphs (1), (2), and (3) of subsection (a)’’ for ‘‘speci-
fied in paragraphs (1) and (2) of subsection (a)’’.
Subsec. (d)(3). Pub. L. 112–81, § 819(b), added par. (3).
Subsec. (g)(2) to (4). Pub. L. 111–383, § 814(c)(2), added
par. (2) and redesignated former pars. (2) and (3) as (3)
and (4), respectively. Former par. (4) redesignated (5).
Subsec. (g)(5). Pub. L. 112–81, § 801(b)(2), added par. (5)
and struck out former par. (5) which read as follows:
‘‘The term ‘Key Decision Point B’ means the official
program initiation of a National Security Space pro-
gram of the Department of Defense, which triggers a
formal review to determine maturity of technology and
the program’s readiness to begin the preliminary sys-
tem design.’’
Pub. L. 111–383, § 814(c)(2)(A), redesignated par. (4) as
(5).
2009—Subsec. (a)(1)(B). Pub. L. 111–23, § 201(f), inserted
‘‘appropriate trade-offs among cost, schedule, and per-
formance objectives have been made to ensure that’’
before ‘‘the program is affordable’’.
Subsec. (a)(1)(C). Pub. L. 111–23, § 101(d)(4), inserted
‘‘, with the concurrence of the Director of Cost Assess-
ment and Program Evaluation,’’ before ‘‘the product’’.
Subsec. (a)(1)(D). Pub. L. 111–23, § 205(a)(3)(A), struck
out ‘‘and’’ at end.
Subsec. (a)(2), (3). Pub. L. 111–23, § 205(a)(3)(B), (C),
added par. (2) and redesignated former par. (2) as (3).
Subsec. (a)(3)(D). Pub. L. 111–23, § 205(a)(3)(D)(i), sub-
stituted ‘‘, as determined by the Milestone Decision
Authority on the basis of an independent review and as-
Page 2723
TITLE 10—ARMED FORCES
§ 4252
sessment by the Director of Defense Research and Engi-
neering; and’’ for semicolon.
Subsec. (a)(3)(E), (F). Pub. L. 111–23, § 205(a)(3)(D)(ii),
(iii), redesignated subpar. (F) as (E) and struck out
former subpar. (E) which read as follows: ‘‘the program
demonstrates a high likelihood of accomplishing its in-
tended mission; and’’.
Subsec. (d). Pub. L. 111–23, § 205(a)(1), designated ex-
isting provisions as par. (1) and substituted par. (2) for
‘‘Whenever the milestone decision authority makes
such a determination and authorizes such a waiver, the
waiver, the determination, and the reasons for the de-
termination shall be submitted in writing to the con-
gressional defense committees within 30 days after the
waiver is authorized.’’
Subsecs. (e) to (g). Pub. L. 111–23, § 205(a)(2), added
subsec. (e) and redesignated former subsecs. (e) and (f)
as (f) and (g), respectively.
2008—Pub. L. 110–417, § 813(a), (b), renumbered section
2366a of this title as this section.
Subsec. (a). Pub. L. 110–181, § 812(1), amended subsec.
(a) generally. Prior to amendment, subsec. (a) consisted
of pars. (1) to (10) relating to required certifications by
milestone decision authority for major defense acquisi-
tion program to receive Milestone B approval, or Key
Decision Point B approval in the case of a space pro-
gram.
Subsec. (b). Pub. L. 110–181, § 812(3), added subsec. (b).
Former subsec. (b) redesignated (c).
Subsec. (c). Pub. L. 110–181, § 812(4), designated exist-
ing provisions as par. (1) and added par. (2).
Pub. L. 110–181, § 812(2), redesignated subsec. (b) as (c).
Former subsec. (c) redesignated (d).
Subsec. (d). Pub. L. 110–181, § 812(5), substituted ‘‘au-
thority may, at the time of Milestone B approval (or
Key Decision Point B approval in the case of a space
program) or at the time that such milestone decision
authority withdraws a certification or rescinds Mile-
stone B approval (or Key Decision Point B approval in
the case of a space program) pursuant to subsection
(b)(2), waive’’ for ‘‘authority may waive’’ and ‘‘para-
graph (1) or (2)’’ for ‘‘paragraph (1), (2), (3), (4), (5), (6),
(7), (8), or (9)’’.
Pub. L. 110–181, § 812(2), redesignated subsec. (c) as (d).
Former subsec. (d) redesignated (e).
Subsec. (e). Pub. L. 110–181, § 812(6), substituted ‘‘sub-
section (d)’’ for ‘‘subsection (c)’’.
Pub. L. 110–181, § 812(2), redesignated subsec. (d) as (e).
Former subsec. (e) redesignated (f).
Subsec. (f). Pub. L. 110–181, § 812(2), redesignated sub-
sec. (e) as (f).
2006—Subsec.
(a)(1)
to
(7).
Pub.
L.
109–364,
§ 805(a)(1)–(3), added par. (1) and redesignated former
pars. (1) to (6) as (2) to (7), respectively. Former par. (7)
redesignated (10).
Subsec. (a)(8), (9). Pub. L. 109–364, § 805(a)(4), (5), added
pars. (8) and (9).
Subsec. (a)(10). Pub. L. 109–364, § 805(a)(1), redesig-
nated par. (7) as (10).
Subsec. (c). Pub. L. 109–364, § 805(b), substituted ‘‘(5),
(6), (7), (8), or (9)’’ for ‘‘(5), or (6)’’.
Statutory Notes and Related Subsidiaries
EFFECTIVE DATE OF 2021 AMENDMENT
Amendment by Pub. L. 117–81 applicable as if in-
cluded in the enactment of title XVIII of Pub. L. 116–283
as enacted, see section 1701(a)(2) of Pub. L. 117–81, set
out in a note preceding section 3001 of this title and
note below.
Amendment by sections 1847(d)(2) and 1883(b)(2) of
Pub. L. 116–283 effective Jan. 1, 2022, with additional
provisions for delayed implementation and applica-
bility of existing law, see section 1801(d) of Pub. L.
116–283, set out as a note preceding section 3001 of this
title.
EFFECTIVE DATE OF 2017 AMENDMENT
Pub. L. 115–91, div. A, title VIII, § 835(b)(2), Dec. 12,
2017,
131
Stat.
1471,
provided
that:
‘‘Section
2366b(a)(3)(O) of title 10, United States Code [now 10
U.S.C. 4252(a)(3)(O)], as added by paragraph (1), shall
apply with respect to any major defense acquisition
program receiving Milestone B approval on or after the
date occurring one year after the date of the enactment
of this Act [Dec. 12, 2017].’’
EFFECTIVE DATE OF 2013 AMENDMENT
Pub. L. 113–66, div. A, title VIII, § 821(b), Dec. 26, 2013,
127 Stat. 809, provided that: ‘‘The amendments made by
subsection (a) [amending this section] shall take effect
on the date of the enactment of this Act [Dec. 26, 2013],
and shall apply with respect to major defense acquisi-
tion programs which are subject to Milestone B ap-
proval on or after the date occurring six months after
the date of the enactment of this Act.’’
Pub. L. 113–66, div. A, title X, § 1091(b), Dec. 26, 2013,
127 Stat. 876, provided in part that the amendment
made by section 1091(b)(1) is effective as of Jan. 2, 2013,
and as if included in Pub. L. 112–239 as enacted.
Amendment by section 322(e)(2) of Pub. L. 112–239 ef-
fective Dec. 31, 2011, immediately after enactment of
Pub. L. 112–81, see section 322(f) of Pub. L. 112–239, set
out as an note under section 4251 of this title.
EFFECTIVE DATE OF 2011 AMENDMENT
Pub. L. 111–383, div. A, title VIII, § 813(d)(1), Jan. 7,
2011, 124 Stat. 4265, provided that the amendment made
by section 813(d)(1) is effective as of May 22, 2009.
Amendment by section 901(j)(4) of Pub. L. 111–383 ef-
fective Jan. 1, 2011, see section 901(p) of Pub. L. 111–383,
set out as a note under section 131 of this title.
Pub. L. 111–383, div. A, title X, § 1075(k), Jan. 7, 2011,
124 Stat. 4378, provided that the amendment made by
section 1075(k)(1) is effective as of May 22, 2009, and as
if included in Pub. L. 111–23 as enacted.
RESPONSIBILITY FOR CONDUCTING ASSESSMENTS
Pub. L. 115–91, div. A, title VIII, § 838(a)(3), Dec. 12,
2017, 131 Stat. 1474, provided that: ‘‘For purposes of the
sufficiency assessments required by section 2366b(c)(1)
[now 10 U.S.C. 4252(c)(1)] and section 2366c(a)(4) [now 10
U.S.C. 4253(a)(4)] of such title [meaning title 10, United
States Code], as added by paragraphs (1) and (2), with
respect to a major defense acquisition program—
‘‘(A) if the milestone decision authority for the pro-
gram is the service acquisition executive of the mili-
tary department that is managing the program, the
sufficiency assessment shall be conducted by the sen-
ior official within the military department with re-
sponsibility for developmental testing; and
‘‘(B) if the milestone decision authority for the pro-
gram is the Under Secretary of Defense for Acquisi-
tion and Sustainment, the sufficiency assessment
shall be conducted by the senior Department of De-
fense official with responsibility for developmental
testing.’’
GUIDANCE
Pub. L. 115–91, div. A, title VIII, § 838(a)(4), Dec. 12,
2017, 131 Stat. 1475, provided that: ‘‘Within one year
after the date of the enactment of this Act [Dec. 12,
2017], the senior Department of Defense official with re-
sponsibility for developmental testing shall develop
guidance for the sufficiency assessments required by
section 2366b(c)(1) and section 2366c(a)(4) of title 10,
United States Code [now 10 U.S.C. 4252(c)(1) and
4253(a)(4)], as added by paragraphs (1) and (2). At a min-
imum, the guidance shall require—
‘‘(A) for the sufficiency assessment required by sec-
tion 2366b(c)(1) of such title [now 10 U.S.C. 4252(c)(1)],
that the assessment address the sufficiency of—
‘‘(i) the developmental test and evaluation plan;
‘‘(ii) the developmental test and evaluation
schedule, including a comparison to historic analo-
gous systems;
‘‘(iii) the developmental test and evaluation re-
sources (facilities, personnel, test assets, data ana-
lytics tools, and modeling and simulation capabili-
ties);
Page 2724
TITLE 10—ARMED FORCES
§ 4253
‘‘(iv) the risks of developmental test and produc-
tion concurrency; and
‘‘(v) the developmental test criteria for entering
the production phase; and
‘‘(B) for the sufficiency assessment required by sec-
tion 2366c(a)(4) of such title [now 10 U.S.C. 4253(a)(4)],
that the assessment address—
‘‘(i) the sufficiency of the developmental test and
evaluation completed;
‘‘(ii) the sufficiency of the plans and resources
available for remaining developmental test and
evaluation;
‘‘(iii) the risks identified during developmental
testing to the production and deployment phase;
‘‘(iv) the sufficiency of the plans and resources for
remaining developmental test and evaluation; and
‘‘(v) the readiness of the system to perform sched-
uled initial operational test and evaluation.’’
MILESTONE B DECISIONS
Pub. L. 114–92, div. A, title VIII, § 802(d)(3), Nov. 25,
2015, 129 Stat. 880, provided that: ‘‘The Chief of the
Armed Force concerned shall advise the milestone deci-
sion authority for a major defense acquisition program
of the Chief’s views on cost, schedule, technical feasi-
bility, and performance trade-offs that have been made
with regard to the program, as provided in section
2366b(b)(3) of title 10, United States Code [now 10 U.S.C.
4252(b)(3)], as amended by section 824 of this Act, prior
to a Milestone B decision on the program.’’
FORMAL REVIEW PROCESS FOR BANDWIDTH
REQUIREMENTS
Pub. L. 110–417, [div. A], title X, § 1047(d), Oct. 14, 2008,
122 Stat. 4603, as amended by Pub. L. 111–84, div. A, title
X, § 1033, Oct. 28, 2009, 123 Stat. 2449; Pub. L. 115–232, div.
A, title VIII, § 813(c), Aug. 13, 2018, 132 Stat. 1851, pro-
vided that: ‘‘The Secretary of Defense and the Director
of National Intelligence shall, as part of the Milestone
B or Key Decision Point B approval process for any
major defense acquisition program or major system ac-
quisition program, establish a formal review process to
ensure that—
‘‘(A) the bandwidth requirements needed to support
such program are or will be met; and
‘‘(B) a determination will be made with respect to
how to meet the bandwidth requirements for such
program.’’
§ 4253. Major defense acquisition programs: sub-
missions to Congress on Milestone C
(a) BRIEF SUMMARY REPORT.—Not later than 15
days after granting Milestone C approval for a
major defense acquisition program, the mile-
stone decision authority for the program shall
provide to the congressional defense committees
and, in the case of intelligence or intelligence-
related activities, the congressional intelligence
committees a brief summary report that con-
tains the following:
(1) The estimated cost and schedule for the
program established by the military depart-
ment concerned, including—
(A) the dollar values estimated for the pro-
gram acquisition unit cost, average procure-
ment unit cost, and total life-cycle cost; and
(B) the planned dates for initial oper-
ational test and evaluation and initial oper-
ational capability.
(2) The independent estimated cost for the
program
established
pursuant
to
section
3221(b)(6) of this title, and any independent es-
timated schedule for the program, including—
(A) the dollar values estimated for the pro-
gram acquisition unit cost, average procure-
ment unit cost, and total life-cycle cost; and
(B) the planned dates for initial oper-
ational test and evaluation and initial oper-
ational capability.
(3) A summary of any production, manufac-
turing, and fielding risks associated with the
program.
(4) An assessment of the sufficiency of the
developmental test and evaluation completed,
including the use of automated data analytics
or modeling and simulation tools and meth-
odologies.
(b) ADDITIONAL INFORMATION.—At the request
of any of the congressional defense committees
or, in the case of intelligence or intelligence-re-
lated activities, the congressional intelligence
committees, the milestone decision authority
shall submit to the committee further informa-
tion or underlying documentation for the infor-
mation in a brief summary report submitted
under subsection (a), including the independent
cost and schedule estimates and the independent
technical risk assessments referred to in that
subsection.
(c) CONGRESSIONAL INTELLIGENCE COMMITTEES
DEFINED.—In this section, the term ‘‘congres-
sional intelligence committees’’ has the mean-
ing given that term in section 437(c) of this title.
(Added Pub. L. 114–328, div. A, title VIII,
§ 808(c)(1), Dec. 23, 2016, 130 Stat. 2265, § 2366c;
amended Pub. L. 115–91, div. A, title VIII,
§ 838(a)(2), Dec. 12, 2017, 131 Stat. 1474; renum-
bered § 4253 and amended Pub. L. 116–283, div. A,
title XVIII, § 1847(d)(3), Jan. 1, 2021, 134 Stat.
4256.)
Editorial Notes
AMENDMENTS
2021—Pub. L. 116–283 renumbered section 2366c of this
title as this section and, in subsec. (a)(2), substituted
‘‘section 3221(b)(6)’’ for ‘‘section 2334(a)(6)’’ in introduc-
tory provisions. Section was inserted after section 4252
of this title, as renumbered by par. (2) of section 1847(d)
of Pub. L. 116–283, to reflect the probable intent of Con-
gress, notwithstanding language directing this section
be inserted after section 4252 of this title ‘‘as trans-
ferred and redesignated by paragraph (3)’’ of section
1847(d).
2017—Subsec. (a)(4). Pub. L. 115–91 added par. (4).
Statutory Notes and Related Subsidiaries
EFFECTIVE DATE OF 2021 AMENDMENT
Amendment by Pub. L. 116–283 effective Jan. 1, 2022,
with additional provisions for delayed implementation
and applicability of existing law, see section 1801(d) of
Pub. L. 116–283, set out as a note preceding section 3001
of this title.
RESPONSIBILITY FOR CONDUCTING ASSESSMENTS;
GUIDANCE
For provisions designating officials responsible for
conducting assessments and provisions requiring guid-
ance for assessments under subsec. (a)(4) of this sec-
tion, see section 838(a)(3), (4) of Pub. L. 115–91, set out
as notes under section 4252 of this title.
SUBCHAPTER IV—ADDITIONAL PROVISIONS
APPLICABLE SPECIFICALLY TO MAJOR
DEFENSE ACQUISITION PROGRAMS
Sec.
4271.
Program cost, fielding, and performance goals
in planning major defense acquisition pro-
grams.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Responsibilities.—** Before granting Milestone A approval for a major defense acquisition program or a major subprogram, the milestone decision authority for the program or subprogram shall ensure that—
(1) information about the program or subprogram is sufficient to warrant entry of the program or subprogram into the risk reduction phase;
(2) the cost, schedule, technical feasibility, and performance trade-offs that have been made with regard to the program do not overly constrain future trade space; and
(3) there are sound plans for progression of the program or subprogram to the development phase.
**(b) Factors to Be Considered for Milestone a Approval.—** A major defense acquisition program or subprogram may not receive Milestone A approval or otherwise be initiated prior to Milestone B approval until the milestone decision authority confirms that the following factors were considered in the decision to grant Milestone A approval:
(1) The program or subprogram fulfills an approved requirements document.
(2) The program or subprogram has conducted appropriate market research.
(3) With respect to any identified areas of risk, there is a plan to reduce the risk.
(4) Planning for sustainment has been addressed.
(5) An analysis of alternatives has been performed consistent with study guidance developed by the Director of Cost Assessment and Program Evaluation, or in lieu of an analysis of alternatives, early experimentation with a combatant commander has been conducted.
(6) A life cycle cost estimate for the program or subprogram has been submitted by the component and that the level of resources required to complete the technology maturation and risk reduction phase of the program is sufficient for successful program execution.
(7) The program or subpro
Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 4251
Stored review status: release_metadata_unconfirmed. The source passage cites 10 U.S.C. § 4251. This identifies an authority to review, not proof of applicability.
Federal law — U.S. Code and appendices · legal_authorities
Page 2716
TITLE 10—ARMED FORCES
§ 4251
major weapon system, or sustainment of a
major weapon system, negotiates a price for
technical data to be delivered under a contract
for
such
development,
production,
or
sustainment.
(Added Pub. L. 115–91, div. A, title VIII,
§ 835(a)(1), Dec. 12, 2017, 131 Stat. 1471, § 2439;
amended Pub. L. 115–232, div. A, title VIII, § 867,
Aug. 13, 2018, 132 Stat. 1901; renumbered § 4236,
Pub. L. 116–283, div. A, title XVIII, § 1847(c)(3),
Jan. 1, 2021, 134 Stat. 4254.)
Editorial Notes
AMENDMENTS
2021—Pub. L. 116–283 renumbered section 2439 of this
title as this section.
2018—Pub.
L.
115–232,
§ 867(4),
substituted
‘‘, production, or sustainment’’ for ‘‘or production’’ in
section catchline.
Pub. L. 115–232, § 867(1)–(3), inserted ‘‘, to the max-
imum extent practicable,’’ after ‘‘shall ensure’’ and
substituted ‘‘production of a major weapon system, or
sustainment of a major weapon system’’ for ‘‘or for the
production
of
a
major
weapon
system’’
and
‘‘, production, or sustainment’’ for ‘‘or production’’.
Statutory Notes and Related Subsidiaries
EFFECTIVE DATE OF 2021 AMENDMENT
Amendment by Pub. L. 116–283 effective Jan. 1, 2022,
with additional provisions for delayed implementation
and applicability of existing law, see section 1801(d) of
Pub. L. 116–283, set out as a note preceding section 3001
of this title.
EFFECTIVE DATE
Pub. L. 115–91, div. A, title VIII, § 835(a)(3), Dec. 12,
2017, 131 Stat. 1471, provided that: ‘‘Section 2439 of title
10, United States Code [now 10 U.S.C. 4236], as added by
paragraph (1), shall apply with respect to any contract
for engineering and manufacturing development of a
major weapon system, or for the production of a major
weapon system, for which the contract solic
Source: Supplied 2024 U.S. Code historical extraction · 10 U.S.C. § 4251
Stored review status: historical_2024_not_currentness_verified. The source passage cites 10 U.S.C. § 4251. This identifies an authority to review, not proof of applicability.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Responsibilities.—** Before granting Milestone B approval for a major defense acquisition program or major subprogram, the milestone decision authority for the program or subprogram shall ensure that—
(1) information about the program or subprogram is sufficient to warrant entry of the program or subprogram into the engineering and manufacturing development phase;
(2) appropriate trade-offs among cost, schedule, technical feasibility, and performance objectives have been made to ensure that the program or subprogram is affordable when considering the per-unit cost and the total life-cycle cost, and the Secretary of the military department concerned and the Chief of the armed force concerned concur with these trade-offs; and
(3) there are sound plans for progression of the program or subprogram to the production phase.
**(b) Factors to Be Considered for Milestone B Approval.—** A major defense acquisition program or major subprogram may not receive Milestone B approval until the milestone decision authority confirms the following factors were considered in the decision to grant Milestone B approval:
(1) The program or subprogram has received a preliminary design review and a formal post-preliminary design review or an equivalent assessment was conducted.
(2) The technology in the program or subprogram has been demonstrated in a relevant environment.
(3) The program or subprogram is affordable when considering the ability of the Department of Defense to accomplish the program’s or subprogram’s general mission using alternative systems.
(4) Reasonable lifecycle cost and schedule estimates have been developed to execute, with the concurrence of the Director of Cost Assessment and Program Evaluation, the plan under the program or subprogram.
(5) The estimated
Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 4252
Stored review status: release_metadata_unconfirmed. Same stored citation; legal effect and authority still require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Brief Summary Report.—** Not later than 15 days after granting Milestone C approval for a major defense acquisition program, the milestone decision authority for the program shall provide to the congressional defense committees and, in the case of intelligence or intelligence-related activities, the congressional intelligence committees a brief summary report that contains the following:
(1) The estimated cost and schedule for the program established by the military department concerned, including—
(A) the dollar values estimated for the program acquisition unit cost, average procurement unit cost, and total life-cycle cost; and
(B) the planned dates for initial operational test and evaluation and initial operational capability.
(2) The independent estimated cost for the program established pursuant to [section 3221(b)(6) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section3221/b/6&num=0&edition=prelim), and any independent estimated schedule for the program, including—
(A) the dollar values estimated for the program acquisition unit cost, average procurement unit cost, and total life-cycle cost; and
(B) the planned dates for initial operational test and evaluation and initial operational capability.
(3) A summary of any production, manufacturing, and fielding risks associated with the program.
(4) An assessment of the sufficiency of the developmental test and evaluation completed, including the use of automated data analytics or modeling and simulation tools and methodologies.
**(b) Additional Information.—** At the request of any of the congressional defense committees or, in the case of intelligence or intelligence-related activities, the congressional intelligence committees, the milestone decision author
Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 4253
Stored review status: release_metadata_unconfirmed. The source passage cites 10 U.S.C. § 4253. This identifies an authority to review, not proof of applicability.
Federal law — U.S. Code and appendices · legal_authorities
Page 2724
TITLE 10—ARMED FORCES
§ 4253
‘‘(iv) the risks of developmental test and produc-
tion concurrency; and
‘‘(v) the developmental test criteria for entering
the production phase; and
‘‘(B) for the sufficiency assessment required by sec-
tion 2366c(a)(4) of such title [now 10 U.S.C. 4253(a)(4)],
that the assessment address—
‘‘(i) the sufficiency of the developmental test and
evaluation completed;
‘‘(ii) the sufficiency of the plans and resources
available for remaining developmental test and
evaluation;
‘‘(iii) the risks identified during developmental
testing to the production and deployment phase;
‘‘(iv) the sufficiency of the plans and resources for
remaining developmental test and evaluation; and
‘‘(v) the readiness of the system to perform sched-
uled initial operational test and evaluation.’’
MILESTONE B DECISIONS
Pub. L. 114–92, div. A, title VIII, § 802(d)(3), Nov. 25,
2015, 129 Stat. 880, provided that: ‘‘The Chief of the
Armed Force concerned shall advise the milestone deci-
sion authority for a major defense acquisition program
of the Chief’s views on cost, schedule, technical feasi-
bility, and performance trade-offs that have been made
with regard to the program, as provided in section
2366b(b)(3) of title 10, United States Code [now 10 U.S.C.
4252(b)(3)], as amended by section 824 of this Act, prior
to a Milestone B decision on the program.’’
FORMAL REVIEW PROCESS FOR BANDWIDTH
REQUIREMENTS
Pub. L. 110–417, [div. A], title X, § 1047(d), Oct. 14, 2008,
122 Stat. 4603, as amended by Pub. L. 111–84, div. A, title
X, § 1033, Oct. 28, 2009, 123 Stat. 2449; Pub. L. 115–232, div.
A, title VIII, § 813(c), Aug. 13, 2018, 132 Stat. 1851, pro-
vided that: ‘‘The Secretary of Defense and the Director
of National Intelligence shall, as pa
Source: Supplied 2024 U.S. Code historical extraction · 10 U.S.C. § 4253
Stored review status: historical_2024_not_currentness_verified. The source passage cites 10 U.S.C. § 4253. This identifies an authority to review, not proof of applicability.