16 U.S.C. § 839f — Administrative provisions
Federal law — U.S. Code and appendices · legal_authorities
**(a) Contract authority** Subject to the provisions of this chapter, the Administrator is authorized to contract in accordance with section 2(f) of the Bonneville Project Act of 1937 ([16 U.S.C. 832a(f)](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section832a/f&num=0&edition=prelim)). Other provisions of law applicable to such contracts on December 5, 1980, shall continue to be applicable.
**(b) Executive and administrative functions of Administrator of Bonneville Power Administration; sound and businesslike implementation of chapter** The Administrator shall discharge the executive and administrative functions of his office in accordance with the policy established by the Bonneville Project Act of 1937 ([16 U.S.C. 832](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section832&num=0&edition=prelim) and following), section 7152(a)(2) and (3) of title 42, and this chapter. The Secretary of Energy, the Council, and the Administrator shall take such steps as are necessary to assure the timely implementation of this chapter in a sound and businesslike manner. Nothing in this chapter shall be construed by the Secretary, the Administrator, or any other official of the Department of Energy to modify, alter, or otherwise affect the requirements and directives expressed by the Congress in section 7152(a)(2) and (3) of title 42 or the operations of such officials as they existed prior to December 5, 1980.
**(c) Limitations and conditions on contracts for sale or exchange of electric power for use outside Pacific Northwest** Any contract of the Administrator for the sale or exchange of electric power for use outside the Pacific Northwest shall be subject to limitations and conditions corresponding to those provided in sections 2 and
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 839f
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: d7b3629d6b55ed967a6ba8b5aa1162ab0ade3538151342419e3523fe9d078a68. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_e603526b46b5225286d25ccd
Source file: Laws/federal/codes/united-states-code/title-16/section-839f-administrative-provisions--431dfb64f9.md
Pages: Not recorded – Not recorded
Passage SHA-256: 1685b16f0e6ad19dceada53d3b891caa08e0dd889ac6542dd99225ceed811167
Source location: Title 16, Chapter 12H, § 839f; chapter-12h-pacific-northwest-electric-power-planning-and-conservation.md
Stored source content
**(a) Contract authority** Subject to the provisions of this chapter, the Administrator is authorized to contract in accordance with section 2(f) of the Bonneville Project Act of 1937 ([16 U.S.C. 832a(f)](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section832a/f&num=0&edition=prelim)). Other provisions of law applicable to such contracts on December 5, 1980, shall continue to be applicable.
**(b) Executive and administrative functions of Administrator of Bonneville Power Administration; sound and businesslike implementation of chapter** The Administrator shall discharge the executive and administrative functions of his office in accordance with the policy established by the Bonneville Project Act of 1937 ([16 U.S.C. 832](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section832&num=0&edition=prelim) and following), section 7152(a)(2) and (3) of title 42, and this chapter. The Secretary of Energy, the Council, and the Administrator shall take such steps as are necessary to assure the timely implementation of this chapter in a sound and businesslike manner. Nothing in this chapter shall be construed by the Secretary, the Administrator, or any other official of the Department of Energy to modify, alter, or otherwise affect the requirements and directives expressed by the Congress in section 7152(a)(2) and (3) of title 42 or the operations of such officials as they existed prior to December 5, 1980.
**(c) Limitations and conditions on contracts for sale or exchange of electric power for use outside Pacific Northwest** Any contract of the Administrator for the sale or exchange of electric power for use outside the Pacific Northwest shall be subject to limitations and conditions corresponding to those provided in sections 2 and 3 of the Act of August 31, 1964 ([16 U.S.C. 837a](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section837a&num=0&edition=prelim) and 837b) for any contract for the sale, delivery, or exchange of hydroelectric energy or peaking capacity generated within the Pacific Northwest for use outside the Pacific Northwest. In applying such sections for the purposes of this subsection, the term “surplus energy” shall mean electric energy for which there is no market in the Pacific Northwest at any rate established for the disposition of such energy, and the term “surplus peaking capacity” shall mean electric peaking capacity for which there is no demand in the Pacific Northwest at the rate established for the disposition of such capacity. The authority granted, and duties imposed upon, the Secretary by sections 5 and 7 of such Act ([16 U.S.C. 837e](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section837e&num=0&edition=prelim) and 837f) [[16 U.S.C. 837d](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section837d&num=0&edition=prelim) and 837f] shall also apply to the Administrator in connection with resources acquired by the Administrator pursuant to this chapter. The Administrator shall, in making any determination, under any contract executed pursuant to [section 839c of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839c&num=0&edition=prelim), of the electric power requirements of any Pacific Northwest customer, which is a non-Federal entity having its own generation, exclude, in addition to hydroelectric generated energy excluded from such requirements pursuant to section 3(d) of such Act ([16 U.S.C. 837b(d)](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section837b/d&num=0&edition=prelim)), any amount of energy included in the resources of such customer for service to firm loads in the region if (1) such amount was disposed of by such customer outside the region, and (2) as a result of such disposition, the firm energy requirements of such customer or other customers of the Administrator are increased. Such amount of energy shall not be excluded, if the Administrator determines that through reasonable measures such amount of energy could not be conserved or otherwise retained for service to regional loads. The Administrator may sell as replacement for any amount of energy so excluded only energy that would otherwise be surplus.
**(d) Disposition of power which does not increase amount of firm power Administrator is obligated to provide to any customer** No restrictions contained in subsection (c) shall limit or interfere with the sale, exchange or other disposition of any power by any utility or group thereof from any existing or new non-Federal resource if such sale, exchange or disposition does not increase the amount of firm power the Administrator would be obligated to provide to any customer. In addition to the directives contained in subsections (i)(1)(B) and (i)(3) and subject to:
(1) any contractual obligations of the Administrator,
(2) any other obligations under existing law, and
(3) the availability of capacity in the Federal transmission system,
the Administrator shall provide transmission access, load factoring, storage and other services normally attendant thereto to such utilities and shall not discriminate against any utility or group thereof on the basis of independent development of such resource in providing such services.
**(e) Judicial review; suits**
(1) For purposes of sections 701 through 706 of title 5, the following actions shall be final actions subject to judicial review—
(A) adoption of the plan or amendments thereto by the Council under [section 839b of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839b&num=0&edition=prelim), adoption of the program by the Council, and any determination by the Council under [section 839b(h) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839b/h&num=0&edition=prelim);
(B) sales, exchanges, and purchases of electric power under [section 839c of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839c&num=0&edition=prelim);
(C) the Administrator’s acquisition of resources under [section 839d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d&num=0&edition=prelim);
(D) implementation of conservation measures under [section 839d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d&num=0&edition=prelim);
(E) execution of contracts for assistance to sponsors under [section 839d(f) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d/f&num=0&edition=prelim);
(F) granting of credits under [section 839d(h) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d/h&num=0&edition=prelim);
(G) final rate determinations under [section 839e of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839e&num=0&edition=prelim); and
(H) any rule prescribed by the Administrator under [section 839e(m)(2) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839e/m/2&num=0&edition=prelim).
(2) The record upon review of such final actions shall be limited to the administrative record compiled in accordance with this chapter. The scope of review of such actions without a hearing or after a hearing shall be governed by [section 706 of title 5](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section706&num=0&edition=prelim), except that final determinations regarding rates under [section 839e of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839e&num=0&edition=prelim) shall be supported by substantial evidence in the rulemaking record required by [section 839e(i) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839e/i&num=0&edition=prelim) considered as a whole. The scope of review of an action under [section 839d(c) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d/c&num=0&edition=prelim) shall be governed by [section 706 of title 5](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section706&num=0&edition=prelim). Nothing in this section shall be construed to require a hearing pursuant to section 554, 556, or 557 of title 5.
(3) Nothing in this section shall be construed to preclude judicial review of other final actions and decisions by the Council or Administrator.
(4) For purposes of this subsection—
(A) major resources shall be deemed to be acquired upon publication in the Federal Register pursuant to [section 839d(c)(4)(B) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d/c/4/B&num=0&edition=prelim);
(B) resources, other than major resources, shall be deemed to be acquired upon execution of the contract therefor;
(C) conservation measures shall be deemed to be implemented upon execution of the contract or grant therefor; and
(D) rate determinations pursuant to [section 839e of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839e&num=0&edition=prelim) shall be deemed final upon confirmation and approval by the Federal Energy Regulatory Commission.
(5) Suits to challenge the constitutionality of this chapter, or any action thereunder, final actions and decisions taken pursuant to this chapter by the Administrator or the Council, or the implementation of such final actions, whether brought pursuant to this chapter, the Bonneville Project Act [[16 U.S.C. 832](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section832&num=0&edition=prelim) et seq.], the Act of August 31, 1964 ([16 U.S.C. 837–837h](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section837–837h&num=0&edition=prelim)), or the Federal Columbia River Transmission System Act ([16 U.S.C. 838](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section838&num=0&edition=prelim) and following), shall be filed in the United States court of appeals for the region. Such suits shall be filed within ninety days of the time such action or decision is deemed final, or, if notice of the action is required by this chapter to be published in the Federal Register, within ninety days from such notice, or be barred. In the case of a challenge of the plan or programs or amendments thereto, such suit shall be filed within sixty days after publication of a notice of such final action in the Federal Register. Such court shall have jurisdiction to hear and determine any suit brought as provided in this section. The plan and program, as finally adopted or portions thereof, or amendments thereto, shall not thereafter be reviewable as a part of any other action under this chapter or any other law. Suits challenging any other actions under this chapter shall be filed in the appropriate court.
**(f) Tax treatment of interest on governmental obligations** For purposes of enabling the Administrator to acquire resources necessary to meet the firm load of public bodies, cooperatives, and Federal agencies from a governmental unit at a cost no greater than the cost which would be applicable in the absence of such acquisition, the exemption from gross income of interest on certain governmental obligations provided in section 103(a)(1) 11 See References in Text note below. of title 26 shall not be affected by the Administrator’s acquisition of such resources if—
(1) the Administrator, prior to contracting for such acquisition, certifies to his reasonable belief, that the persons for whom the Administrator is acquiring such resources for sale pursuant to [section 839c of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839c&num=0&edition=prelim) are public bodies, cooperatives, and Federal agencies, unless the Administrator also certifies that he is unable to acquire such resources without selling a portion thereof to persons who are not exempt persons (as defined in section 103(b) 1 of title 26), and
(2) based upon such certification, the Secretary of the Treasury determines in accordance with applicable regulations that less than a major portion of the resource is to be furnished to persons who are not exempt persons (as defined in section 103(b) 1 of title 26).
The certification under paragraph (1) shall be made in accordance with this subsection and a procedure and methodology approved by the Secretary of the Treasury. For purposes of this subsection, the term “major portion” shall have the meaning provided by regulations issued by the Secretary of the Treasury.
**(g) Review of rates for sale of power to Administrator by investor-owned utility customers** When reviewing rates for the sale of power to the Administrator by an investor-owned utility customer under section 839c(c) or 839d of this title, the Federal Energy Regulatory Commission shall, in accordance with [section 824h of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section824h&num=0&edition=prelim)—
(1) convene a joint State board, and
(2) invest such board with such duties and authority as will assist the Commission in its review of such rates.
**(h) Companies which own or operate facilities for the generation of electricity primarily for sale to Administrator**
(1) No “company” (as defined in section 79b(a)(2) 1 of title 15), which owns or operates facilities for the generation of electricity (together with associated transmission and other facilities) primarily for sale to the Administrator under [section 839d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d&num=0&edition=prelim) shall be deemed an “electric utility company” (as defined in section 79b(a)(3) 1 of title 15), within the meaning of any provision or provisions of chapter 2C 1 of title 15, if at least 90 per centum of the electricity generated by such company is sold to the Administrator under [section 839d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d&num=0&edition=prelim), and if—
(A) the organization of such company is consistent with the policies of section 79a(b) and (c) 1 of title 15, as determined by the Securities and Exchange Commission, with the concurrence of the Administrator, at the time of such organization; and
(B) participation in any facilities of such “company” has been offered to public bodies and cooperatives in the region pursuant to [section 839d(m) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d/m&num=0&edition=prelim).
(2) The Administrator shall include in any contract for the acquisition of a major resource from such “company” provisions limiting the amount of equity investment, if any, in such “company” to that which the Administrator determines will be consistent with achieving the lowest attainable power costs attributable to such major resource.
(3) In the case of any “company” which meets the requirements of paragraph (1), the Administrator, with the concurrence of such Commission, shall approve all significant contracts entered into by, and between, such “company” and any sponsor company or any subsidiary of such sponsor company which are determined to be consistent with the policies of section 79a(b) and (c) 1 of title 15 at the time such contracts are entered into. The Administrator and the Securities and Exchange Commission shall exercise such approval authority within sixty days after receipt of such contracts. Such contracts shall not be effective without such approval.
(4) Paragraph (1) of this subsection shall continue to apply to any such “company” unless the Administrator or the Securities and Exchange Commission, or both, through periodic review, (A) determine at any time that the “company” no longer operates in a manner consistent with the policies of section 79a(b) and (c) 1 of title 15 and in accordance with this subsection, and (B) notify the “company” in writing of such preliminary determination. This subsection shall cease to apply to such “company” thirty days after receipt of notification of a final determination thereof. A final determination shall be made only after public notice of the preliminary determination and after a hearing completed not later than sixty days from the date of publication of such notice. Such final determination shall be made within thirty days after the date of completion of such hearing.
**(i) Electric power acquisition or disposition**
(1) At the request and expense of any customer or group of customers of the Administrator within the Pacific Northwest, the Administrator shall, to the extent practicable—
(A) acquire any electric power required by (i) any customer or group of customers to enable them to replace resources determined to serve firm load under [section 839c(b) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839c/b&num=0&edition=prelim), or (ii) direct service industrial customers to replace electric power that is or may be curtailed or interrupted by the Administrator (other than power the Administrator is obligated to replace), with the cost of such replacement power to be distributed among the direct service industrial customers requesting such power; and
(B) dispose of, or assist in the disposal of, any electric power that a customer or group of customers proposes to sell within or without the region at rates and upon terms specified by such customer or group of customers, if such disposition is not in conflict with the Administrator’s other marketing obligations and the policies of this chapter and other applicable laws.
(2) In implementing the provisions of subparagraphs (A) and (B) of paragraph (1), the Administrator may prescribe policies and conditions for the independent acquisition or disposition of electric power by any direct service industrial customer or group of such customers for the purpose of assuring each direct service industrial customer an opportunity to participate in such acquisition or disposition.
(3) The Administrator shall furnish services including transmission, storage, and load factoring unless he determines such services cannot be furnished without substantial interference with his power marketing program, applicable operating limitations or existing contractual obligations. The Administrator shall, to the extent practicable, give priority in making such services available for the marketing, within and without the Pacific Northwest, of capability from projects under construction on December 5, 1980, if such capability has been offered for sale at cost, including a reasonable rate of return, to the Administrator pursuant to this chapter and such offer is not accepted within one year.
**(j) Retail rate designs which encourage conservation and efficient use of electric energy, installation of consumer-owned renewable resources, and rate research and development**
(1) The Council, as soon as practicable after December 5, 1980 shall prepare, in consultation with the Administrator, the customers, appropriate State regulatory bodies, and the public, a report and shall make recommendations with respect to the various retail rate designs which will encourage conservation and efficient use of electric energy and the installation of consumer-owned renewable resources on a cost-effective basis, as well as areas for research and development for possible application to retail utility rates within the region. Studies undertaken pursuant to this subsection shall not affect the responsibilities of any customer or the Administrator which may exist under the Public Utility Regulatory Policies Act of 1978.
(2) Upon request, and solely on behalf of customers so requesting, the Administrator is authorized to (A) provide assistance in analyzing and developing retail rate structures that will encourage cost-effective conservation and the installation of cost-effective consumer-owned renewable resources; (B) provide estimates of the probable power savings and the probable amount of billing credits under [section 839d(h) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839d/h&num=0&edition=prelim) that might be realized by such customers as a result of adopting and implementing such retail rate structures; and (C) solicit additional information and analytical assistance from appropriate State regulatory bodies and the Administrator’s other customers.
**(k) Executive position for conservation and renewable resources** There is hereby established within the administration an executive position for conservation and renewable resources. Such executive shall be appointed by the Administrator and shall be assigned responsibility for conservation and direct-application renewable resource programs (including the administration of financial assistance for such programs). Such position is hereby established in the senior executive service in addition to the number of such positions heretofore established in accordance with other provisions of law applicable to such positions.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Information required to be gathered** Each electric utility shall periodically gather information under such rules (promulgated by the Commission) as the Commission determines necessary to allow determination of the costs associated with providing electric service. For purposes of this section, and for purposes of any consideration and determination respecting the standard established by [section 2621(d)(2) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section2621/d/2&num=0&edition=prelim), such costs shall be separated, to the maximum extent practicable, into the following components: customer cost component, demand cost component, and energy cost component. Rules under this subsection shall include requirements for the gathering of the following information with respect to each electric utility—
(1) the costs of serving each electric consumer class, including costs of serving different consumption patterns within such class, based on voltage level, time of use, and other appropriate factors;
(2) daily kilowatt demand load curves for all electric consumer classes combined representative of daily and seasonal differences in demand, and daily kilowatt demand load curves for each electric consumer class for which there is a separate rate, representative of daily and seasonal differences in demand;
(3) annual capital, operating, and maintenance costs—
(A) for transmission and distribution services, and
(B) for each type of generating unit; and
(4) costs of purchased power, including representative daily and seasonal differences in the amount of such costs.
Such rules shall provide that information required to be gathered under this section shall be presented in such categories and such detail as may be necessary to carr
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 2601
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Without regard to the limitations specified in sections 837a and 837b of this title, the Secretary may enter into contracts for the exchange with areas other than the Pacific Northwest of (1) surplus energy during the Pacific Northwest storage refill period, (2) any hydroelectric energy during the Pacific Northwest storage refill period which will be returned to the Pacific Northwest in equal amounts during the same Pacific Northwest refill period or the succeeding storage drawdown period, (3) any hydroelectric energy which will be returned to the Pacific Northwest in equal amounts during the same Pacific Northwest storage drawdown period, (4) hydroelectric peaking capacity, or (5) surplus peaking capacity for energy. All benefits from such exchanges, including resulting increases of firm power, shall be shared equitably by the areas involved, having regard to the secondary energy and other contributions made by each.
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 837d
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Composition of boards; force and effect of proceedings** The Commission may refer any matter arising in the administration of this subchapter to a board to be composed of a member or members, as determined by the Commission, from the State or each of the States affected or to be affected by such matter. Any such board shall be vested with the same power and be subject to the same duties and liabilities as in the case of a member of the Commission when designated by the Commission to hold any hearings. The action of such board shall have such force and effect and its proceedings shall be conducted in such manner as the Commission shall by regulations prescribe. The board shall be appointed by the Commission from persons nominated by the State commission of each State affected or by the Governor of such State if there is no State commission. Each State affected shall be entitled to the same number of representatives on the board unless the nominating power of such State waives such right. The Commission shall have discretion to reject the nominee from any State, but shall thereupon invite a new nomination from that State. The members of a board shall receive such allowances for expenses as the Commission shall provide. The Commission may, when in its discretion sufficient reason exists therefor, revoke any reference to such a board.
**(b) Cooperation with State commissions** The Commission may confer with any State commission regarding the relationship between rate structures, costs, accounts, charges, practices, classifications, and regulations of public utilities subject to the jurisdiction of such State commission and of the Commission; and the Commission is authorized, under such rules and regulations as it shall prescribe, to hold joint hearings with any State
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 824h
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Pacific Northwest Electric Power and Conservation Planning Council; establishment and operation as regional agency**
(1) The purposes of this section are to provide for the prompt establishment and effective operation of the Pacific Northwest Electric Power and Conservation Planning Council, to further the purposes of this chapter by the Council promptly preparing and adopting (A) a regional conservation and electric power plan and (B) a program to protect, mitigate, and enhance fish and wildlife, and to otherwise expeditiously and effectively carry out the Council’s responsibilities and functions under this chapter.
(2) To achieve such purposes and facilitate cooperation among the States of Idaho, Montana, Oregon, and Washington, and with the Bonneville Power Administration, the consent of Congress is given for an agreement described in this paragraph and not in conflict with this chapter, pursuant to which—
(A) there shall be established a regional agency known as the “Pacific Northwest Electric Power and Conservation Planning Council” which (i) shall have its offices in the Pacific Northwest, (ii) shall carry out its functions and responsibilities in accordance with the provisions of this chapter, (iii) shall continue in force and effect in accordance with the provisions of this chapter, and (iv) except as otherwise provided in this chapter, shall not be considered an agency or instrumentality of the United States for the purpose of any Federal law; and
(B) two persons from each State may be appointed, subject to the applicable laws of each such State, to undertake the functions and duties of members of the Council.
The State may fill any vacancy occurring prior to the expiration of the term of any member. The appointment of six initial members, subje
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 839b
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Conservation measures; resources**
(1) The Administrator shall acquire such resources through conservation, implement all such conservation measures, and acquire such renewable resources which are installed by a residential or small commercial consumer to reduce load, as the Administrator determines are consistent with the plan, or if no plan is in effect with the criteria of [section 839b(e)(1) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839b/e/1&num=0&edition=prelim) and the considerations of [section 839b(e)(2) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839b/e/2&num=0&edition=prelim) and, in the case of major resources, in accordance with subsection (c) of this section. Such conservation measures and such resources may include, but are not limited to—
(A) loans and grants to consumers for insulation or weatherization, increased system efficiency, and waste energy recovery by direct application,
(B) technical and financial assistance to, and other cooperation with, the Administrator’s customers and governmental authorities to encourage maximum cost-effective voluntary conservation and the attainment of any cost-effective conservation objectives adopted by individual States or subdivisions thereof,
(C) aiding the Administrator’s customers and governmental authorities in implementing model conservation standards adopted pursuant to [section 839b(f) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section839b/f&num=0&edition=prelim), and
(D) conducting demonstration projects to determine the cost effectiveness of conservation measures and direct application of renewable energy resources.
(2) In addition to acquiring electri
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 839d
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
For the purpose of improving navigation on the Columbia River, and for other purposes incidental thereto, the dam, locks, power plant, and appurtenant works under construction on August 20, 1937, at Bonneville, Oregon and North Bonneville, Washington (called Bonneville project in this chapter), shall be completed, maintained, and operated under the direction of the Secretary of the Army and the supervision of the Chief of Engineers, subject to the provisions of this chapter relating to the powers and duties of the Bonneville power administrator provided for in [section 832a(a) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section832a/a&num=0&edition=prelim) (called the administrator in this chapter) respecting the transmission and sale of electric energy generated at said project. The Secretary of the Army shall provide, construct, operate, maintain, and improve at Bonneville project such machinery, equipment, and facilities for the generation of electric energy as the administrator may deem necessary to develop such electric energy as rapidly as markets may be found therefor. The electric energy thus generated and not required for the operation of the dam and locks at such project and the navigation facilities employed in connection therewith shall be delivered to the administrator, for disposition as provided in this chapter.
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 832
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Establishment; periodic review and revision; confirmation and approval by Federal Energy Regulatory Commission**
(1) The Administrator shall establish, and periodically review and revise, rates for the sale and disposition of electric energy and capacity and for the transmission of non-Federal power. Such rates shall be established and, as appropriate, revised to recover, in accordance with sound business principles, the costs associated with the acquisition, conservation, and transmission of electric power, including the amortization of the Federal investment in the Federal Columbia River Power System (including irrigation costs required to be repaid out of power revenues) over a reasonable period of years and the other costs and expenses incurred by the Administrator pursuant to this chapter and other provisions of law. Such rates shall be established in accordance with sections 9 and 10 of the Federal Columbia River Transmission System Act ([16 U.S.C. 838](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section838&num=0&edition=prelim)) [[16 U.S.C. 838g](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section838g&num=0&edition=prelim) and 838h], section 5 of the Flood Control Act of 1944 [[16 U.S.C. 825s](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section825s&num=0&edition=prelim)], and the provisions of this chapter.
(2) Rates established under this section shall become effective only, except in the case of interim rules as provided in subsection (i)(6), upon confirmation and approval by the Federal Energy Regulatory Commission upon a finding by the Commission, that such rates—
(A) are sufficient to assure repayment of the Federal investment in the Federal Columbia River Power System over
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 839e
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Any capacity in Federal transmission lines connecting, either by themselves or with non-Federal lines, a generating plant in the Pacific Northwest or Canada with the other area or with any other area outside the Pacific Northwest, which is not required for the transmission of Federal energy or the energy described in [section 837h of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section837h&num=0&edition=prelim), shall be made available as a carrier for transmission of other electric energy between such areas. The transmission of other electric energy shall be at equitable rates determined by the Secretary, but such rates shall be subject to equitable adjustment at appropriate intervals not less frequently than once in every five years as agreed to by the parties. No contract for the transmission of non-Federal energy on a firm basis shall be affected by any increase, subsequent to the execution of such contract, in the requirements for transmission of Federal energy, the energy described in [section 837h of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section837h&num=0&edition=prelim), or other electric energy.
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 837e
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Exclusion** Except as provided in subsection (b), gross income does not include interest on any State or local bond.
**(b) Exceptions** Subsection (a) shall not apply to—
(1) **Private activity bond which is not a qualified bond** — Any private activity bond which is not a qualified bond (within the meaning of section 141).
(2) **Arbitrage bond** — Any arbitrage bond (within the meaning of section 148).
(3) **Bond not in registered form, etc.** — Any bond unless such bond meets the applicable requirements of section 149.
**(c) Definitions** For purposes of this section and part IV—
(1) **State or local bond** — The term “State or local bond” means an obligation of a State or political subdivision thereof.
(2) **State** — The term “State” includes the District of Columbia and any possession of the United States.
Source: Supplied U.S. Code snapshot — release unconfirmed · 26 U.S.C. § 103
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
To the extent necessary to decision and when presented, the reviewing court shall decide all relevant questions of law, interpret constitutional and statutory provisions, and determine the meaning or applicability of the terms of an agency action. The reviewing court shall—
(1) compel agency action unlawfully withheld or unreasonably delayed; and
(2) hold unlawful and set aside agency action, findings, and conclusions found to be—
(A) arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law;
(B) contrary to constitutional right, power, privilege, or immunity;
(C) in excess of statutory jurisdiction, authority, or limitations, or short of statutory right;
(D) without observance of procedure required by law;
(E) unsupported by substantial evidence in a case subject to sections 556 and 557 of this title or otherwise reviewed on the record of an agency hearing provided by statute; or
(F) unwarranted by the facts to the extent that the facts are subject to trial de novo by the reviewing court.
In making the foregoing determinations, the court shall review the whole record or those parts of it cited by a party, and due account shall be taken of the rule of prejudicial error.
Source: Supplied U.S. Code snapshot — release unconfirmed · 5 U.S.C. § 706