**(a) Emission limitations**
(1) After January 1, 1995, each source that includes one or more affected units listed in table A is an affected source under this section. After January 1, 1995, it shall be unlawful for any affected unit (other than an eligible phase I unit under subsection (d)(2)) to emit sulfur dioxide in excess of the tonnage limitation stated as a total number of allowances in table A for phase I, unless (A) the emissions reduction requirements applicable to such unit have been achieved pursuant to subsection (b) or (d), or (B) the owner or operator of such unit holds allowances to emit not less than the unit’s total annual emissions, except that, after January 1, 2000, the emissions limitations established in this section shall be superseded by those established in [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim). The owner or operator of any unit in violation of this section shall be fully liable for such violation including, but not limited to, liability for fulfilling the obligations specified in [section 7651j of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651j&num=0&edition=prelim).
(2) Not later than December 31, 1991, the Administrator shall determine the total tonnage of reductions in the emissions of sulfur dioxide from all utility units in calendar year 1995 that will occur as a result of compliance with the emissions limitation requirements of this section, and shall establish a reserve of allowances equal in amount to the number of tons determined thereby not to exceed a total of 3.50 million tons. In making such a determination, the Administrator shall compute for each unit subject to the emissions limitation
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651c
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: 413d05f858c6a03476641365947f072d227dadd63c17c727b7115c1a178a078b. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_e1fea71a7b17e698edc8d718
Source file: Laws/federal/codes/united-states-code/title-42/section-7651c-phase-i-sulfur-dioxide-requirements--61b306a13b.md
Pages: Not recorded – Not recorded
Passage SHA-256: 763ba0d4283afd36a6ffcf0f24730ffbb0105860c0830ccd55b1ad1ee878bbd5
Source location: Title 42, Chapter 85, § 7651c; chapter-085-air-pollution-prevention-and-control.md
Stored source content
**(a) Emission limitations**
(1) After January 1, 1995, each source that includes one or more affected units listed in table A is an affected source under this section. After January 1, 1995, it shall be unlawful for any affected unit (other than an eligible phase I unit under subsection (d)(2)) to emit sulfur dioxide in excess of the tonnage limitation stated as a total number of allowances in table A for phase I, unless (A) the emissions reduction requirements applicable to such unit have been achieved pursuant to subsection (b) or (d), or (B) the owner or operator of such unit holds allowances to emit not less than the unit’s total annual emissions, except that, after January 1, 2000, the emissions limitations established in this section shall be superseded by those established in [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim). The owner or operator of any unit in violation of this section shall be fully liable for such violation including, but not limited to, liability for fulfilling the obligations specified in [section 7651j of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651j&num=0&edition=prelim).
(2) Not later than December 31, 1991, the Administrator shall determine the total tonnage of reductions in the emissions of sulfur dioxide from all utility units in calendar year 1995 that will occur as a result of compliance with the emissions limitation requirements of this section, and shall establish a reserve of allowances equal in amount to the number of tons determined thereby not to exceed a total of 3.50 million tons. In making such a determination, the Administrator shall compute for each unit subject to the emissions limitation requirements of this section the difference between:
(A) the product of its baseline multiplied by the lesser of each unit’s allowable 1985 emissions rate and its actual 1985 emissions rate, divided by 2,000, and
(B) the product of each unit’s baseline multiplied by 2.50 lbs/mmBtu divided by 2,000,
and sum the computations. The Administrator shall adjust the foregoing calculation to reflect projected calendar year 1995 utilization of the units subject to the emissions limitations of this subchapter that the Administrator finds would have occurred in the absence of the imposition of such requirements. Pursuant to subsection (d), the Administrator shall allocate allowances from the reserve established hereinunder until the earlier of such time as all such allowances in the reserve are allocated or December 31, 1999.
(3) In addition to allowances allocated pursuant to paragraph (1), in each calendar year beginning in 1995 and ending in 1999, inclusive, the Administrator shall allocate for each unit on Table A that is located in the States of Illinois, Indiana, or Ohio (other than units at Kyger Creek, Clifty Creek and Joppa Steam), allowances in an amount equal to 200,000 multiplied by the unit’s pro rata share of the total number of allowances allocated for all units on Table A in the 3 States (other than units at Kyger Creek, Clifty Creek, and Joppa Steam) pursuant to paragraph (1). Such allowances shall be excluded from the calculation of the reserve under paragraph (2).
**(b) Substitutions** The owner or operator of an affected unit under subsection (a) may include in its [section 7651g of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651g&num=0&edition=prelim) permit application and proposed compliance plan a proposal to reassign, in whole or in part, the affected unit’s sulfur dioxide reduction requirements to any other unit(s) under the control of such owner or operator. Such proposal shall specify—
(1) the designation of the substitute unit or units to which any part of the reduction obligations of subsection (a) shall be required, in addition to, or in lieu of, any original affected units designated under such subsection;
(2) the original affected unit’s baseline, the actual and allowable 1985 emissions rate for sulfur dioxide, and the authorized annual allowance allocation stated in table A;
(3) calculation of the annual average tonnage for calendar years 1985, 1986, and 1987, emitted by the substitute unit or units, based on the baseline for each unit, as defined in section 7651a(d) 11 So in original. Probably should be section “7651a(4)”. of this title, multiplied by the lesser of the unit’s actual or allowable 1985 emissions rate;
(4) the emissions rates and tonnage limitations that would be applicable to the original and substitute affected units under the substitution proposal;
(5) documentation, to the satisfaction of the Administrator, that the reassigned tonnage limits will, in total, achieve the same or greater emissions reduction than would have been achieved by the original affected unit and the substitute unit or units without such substitution; and
(6) such other information as the Administrator may require.
**(c) Administrator’s action on substitution proposals**
(1) The Administrator shall take final action on such substitution proposal in accordance with [section 7651g(c) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651g/c&num=0&edition=prelim) if the substitution proposal fulfills the requirements of this subsection. The Administrator may approve a substitution proposal in whole or in part and with such modifications or conditions as may be consistent with the orderly functioning of the allowance system and which will ensure the emissions reductions contemplated by this subchapter. If a proposal does not meet the requirements of subsection (b), the Administrator shall disapprove it. The owner or operator of a unit listed in table A shall not substitute another unit or units without the prior approval of the Administrator.
(2) Upon approval of a substitution proposal, each substitute unit, and each source with such unit, shall be deemed affected under this subchapter, and the Administrator shall issue a permit to the original and substitute affected source and unit in accordance with the approved substitution plan and [section 7651g of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651g&num=0&edition=prelim). The Administrator shall allocate allowances for the original and substitute affected units in accordance with the approved substitution proposal pursuant to [section 7651b of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651b&num=0&edition=prelim). It shall be unlawful for any source or unit that is allocated allowances pursuant to this section to emit sulfur dioxide in excess of the emissions limitation provided for in the approved substitution permit and plan unless the owner or operator of each unit governed by the permit and approved substitution plan holds allowances to emit not less than the units 22 So in original. Probably should be “unit’s”. total annual emissions. The owner or operator of any original or substitute affected unit operated in violation of this subsection shall be fully liable for such violation, including liability for fulfilling the obligations specified in [section 7651j of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651j&num=0&edition=prelim). If a substitution proposal is disapproved, the Administrator shall allocate allowances to the original affected unit or units in accordance with subsection (a).
**(d) Eligible phase I extension units**
(1) The owner or operator of any affected unit subject to an emissions limitation requirement under this section may petition the Administrator in its permit application under [section 7651g of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651g&num=0&edition=prelim) for an extension of 2 years of the deadline for meeting such requirement, provided that the owner or operator of any such unit holds allowances to emit not less than the unit’s total annual emissions for each of the 2 years of the period of extension. To qualify for such an extension, the affected unit must either employ a qualifying phase I technology, or transfer its phase I emissions reduction obligation to a unit employing a qualifying phase I technology. Such transfer shall be accomplished in accordance with a compliance plan, submitted and approved under [section 7651g of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651g&num=0&edition=prelim), that shall govern operations at all units included in the transfer, and that specifies the emissions reduction requirements imposed pursuant to this subchapter.
(2) Such extension proposal shall—
(A) specify the unit or units proposed for designation as an eligible phase I extension unit;
(B) provide a copy of an executed contract, which may be contingent upon the Administrator approving the proposal, for the design engineering, and construction of the qualifying phase I technology for the extension unit, or for the unit or units to which the extension unit’s emission reduction obligation is to be transferred;
(C) specify the unit’s or units’ baseline, actual 1985 emissions rate, allowable 1985 emissions rate, and projected utilization for calendar years 1995 through 1999;
(D) require CEMS on both the eligible phase I extension unit or units and the transfer unit or units beginning no later than January 1, 1995; and
(E) specify the emission limitation and number of allowances expected to be necessary for annual operation after the qualifying phase I technology has been installed.
(3) The Administrator shall review and take final action on each extension proposal in order of receipt, consistent with [section 7651g of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651g&num=0&edition=prelim), and for an approved proposal shall designate the unit or units as an eligible phase I extension unit. The Administrator may approve an extension proposal in whole or in part, and with such modifications or conditions as may be necessary, consistent with the orderly functioning of the allowance system, and to ensure the emissions reductions contemplated by the 33 So in original. Probably should be “this”. subchapter.
(4) In order to determine the number of proposals eligible for allocations from the reserve under subsection (a)(2) and the number of allowances remaining available after each proposal is acted upon, the Administrator shall reduce the total number of allowances remaining available in the reserve by the number of allowances calculated according to subparagraphs (A), (B) and (C) until either no allowances remain available in the reserve for further allocation or all approved proposals have been acted upon. If no allowances remain available in the reserve for further allocation before all proposals have been acted upon by the Administrator, any pending proposals shall be disapproved. The Administrator shall calculate allowances equal to—
(A) the difference between the lesser of the average annual emissions in calendar years 1988 and 1989 or the projected emissions tonnage for calendar year 1995 of each eligible phase I extension unit, as designated under paragraph (3), and the product of the unit’s baseline multiplied by an emission rate of 2.50 lbs/mmBtu, divided by 2,000;
(B) the difference between the lesser of the average annual emissions in calendar years 1988 and 1989 or the projected emissions tonnage for calendar year 1996 of each eligible phase I extension unit, as designated under paragraph (3), and the product of the unit’s baseline multiplied by an emission rate of 2.50 lbs/mmBtu, divided by 2,000; and
(C) the amount by which (i) the product of each unit’s baseline multiplied by an emission rate of 1.20 lbs/mmBtu, divided by 2,000, exceeds (ii) the tonnage level specified under subparagraph (E) of paragraph (2) of this subsection multiplied by a factor of 3.
(5) Each eligible Phase I extension unit shall receive allowances determined under subsection (a)(1) or (c) of this section. In addition, for calendar year 1995, the Administrator shall allocate to each eligible Phase I extension unit, from the allowance reserve created pursuant to subsection (a)(2), allowances equal to the difference between the lesser of the average annual emissions in calendar years 1988 and 1989 or its projected emissions tonnage for calendar year 1995 and the product of the unit’s baseline multiplied by an emission rate of 2.50 lbs/mmBtu, divided by 2,000. In calendar year 1996, the Administrator shall allocate for each eligible unit, from the allowance reserve created pursuant to subsection (a)(2) of this section, allowances equal to the difference between the lesser of the average annual emissions in calendar years 1988 and 1989 or its projected emissions tonnage for calendar year 1996 and the product of the unit’s baseline multiplied by an emission rate of 2.50 lbs/mmBtu, divided by 2,000. It shall be unlawful for any source or unit subject to an approved extension plan under this subsection to emit sulfur dioxide in excess of the emissions limitations provided for in the permit and approved extension plan, unless the owner or operator of each unit governed by the permit and approved plan holds allowances to emit not less than the unit’s total annual emissions.
(6) In addition to allowances specified in paragraph (5), the Administrator shall allocate for each eligible Phase I extension unit employing qualifying Phase I technology, for calendar years 1997, 1998, and 1999, additional allowances, from any remaining allowances in the reserve created pursuant to subsection (a)(2), following the reduction in the reserve provided for in paragraph (4), not to exceed the amount by which (A) the product of each eligible unit’s baseline times an emission rate of 1.20 lbs/mmBtu, divided by 2,000, exceeds (B) the tonnage level specified under subparagraph (E) of paragraph (2) of this subsection.
(7) After January 1, 1997, in addition to any liability under this chapter, including under [section 7651j of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651j&num=0&edition=prelim), if any eligible phase I extension unit employing qualifying phase I technology or any transfer unit under this subsection emits sulfur dioxide in excess of the annual tonnage limitation specified in the extension plan, as approved in paragraph (3) of this subsection, the Administrator shall, in the calendar year following such excess, deduct allowances equal to the amount of such excess from such unit’s annual allowance allocation.
**(e) Allocation of allowances**
(1) In the case of a unit that receives authorization from the Governor of the State in which such unit is located to make reductions in the emissions of sulfur dioxide prior to calendar year 1995 and that is part of a utility system that meets the following requirements: (A) the total coal-fired generation within the utility system as a percentage of total system generation decreased by more than 20 percent between January 1, 1980, and December 31, 1985; and (B) the weighted capacity factor of all coal-fired units within the utility system averaged over the period from January 1, 1985, through December 31, 1987, was below 50 percent, the Administrator shall allocate allowances under this paragraph for the unit pursuant to this subsection. The Administrator shall allocate allowances for a unit that is an affected unit pursuant to [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim) (but is not also an affected unit under this section) and part of a utility system that includes 1 or more affected units under [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim) for reductions in the emissions of sulfur dioxide made during the period 1995–1999 if the unit meets the requirements of this subsection and the requirements of the preceding sentence, except that for the purposes of applying this subsection to any such unit, the prior year concerned as specified below, shall be any year after January 1, 1995 but prior to January 1, 2000.
(2) In the case of an affected unit under this section described in subparagraph (A),44 So in original. Probably should be “paragraph (1)”. the allowances allocated under this subsection for early reductions in any prior year may not exceed the amount which (A) the product of the unit’s baseline multiplied by the unit’s 1985 actual sulfur dioxide emission rate (in lbs. per mmBtu), divided by 2,000, exceeds (B) the allowances specified for such unit in Table A. In the case of an affected unit under [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim) described in subparagraph (A),4 the allowances awarded under this subsection for early reductions in any prior year may not exceed the amount by which (i) the product of the quantity of fossil fuel consumed by the unit (in mmBtu) in the prior year multiplied by the lesser of 2.50 or the most stringent emission rate (in lbs. per mmBtu) applicable to the unit under the applicable implementation plan, divided by 2,000, exceeds (ii) the unit’s actual tonnage of sulfur dioxide emission for the prior year concerned. Allowances allocated under this subsection for units referred to in subparagraph (A) 4 may be allocated only for emission reductions achieved as a result of physical changes or changes in the method of operation made after November 15, 1990, including changes in the type or quality of fossil fuel consumed.
(3) In no event shall the provisions of this paragraph 55 So in original. Probably should be “subsection”. be interpreted as an event of force majeur 66 So in original. Probably should be “majeure”. or a commercial impractibility 77 So in original. Probably should be “impracticability”. or in any other way as a basis for excused nonperformance by a utility system under a coal sales contract in effect before November 15, 1990. Table A.—Affected Sources and Units in Phase I and Their Sulfur Dioxide Allowances (tons) StatePlant NameGeneratorPhase I Allowances AlabamaColbert1234513,57015,31015,40015,41037,180 E.C. Gaston1234518,10018,54018,31019,28059,840 FloridaBig Bend12328,41027,10026,740 Crist6719,20031,680 GeorgiaBowen123456,32054,77071,75071,740 Hammond12348,7809,2208,91037,640 J. McDonough1219,91020,600 Wansley1270,77065,430 Yates12345677,2107,0406,9508,9109,41024,76021,480 IllinoisBaldwin12342,01044,42042,550 Coffeen1211,79035,670 Grand Tower45,910 Hennepin218,410 Joppa Steam12345612,59010,77012,27011,36011,42010,620 Kincaid1231,53033,810 Meredosia313,890 Vermilion28,880 IndianaBailly7811,18015,630 Breed118,500 Cayuga1233,37034,130 Clifty Creek12345620,15019,81020,41020,08019,36020,380 E. W. Stout5673,8804,77023,610 F. B. Culley234,29016,970 F. E. Ratts128,3308,480 Gibson123440,40041,01041,08040,320 H. T. Pritchard65,770 Michigan City1223,310 Petersburg1216,43032,380 R. Gallagher12346,4907,2806,5307,650 Tanners Creek424,820 Wabash River123564,0002,8603,7503,67012,280 Warrick426,980 IowaBurlington110,710 Des Moines72,320 George Neal11,290 M.L. Kapp213,800 Prairie Creek48,180 Riverside53,990 KansasQuindaro24,220 KentuckyColeman12311,25012,84012,340 Cooper127,45015,320 E.W. Brown1237,11010,91026,100 Elmer Smith126,52014,410 Ghent128,410 Green River47,820 H.L. Spurlock122,780 Henderson II1213,34012,310 Paradise359,170 Shawnee1010,170 MarylandChalk Point1221,91024,330 C. P. Crane1210,3309,230 Morgantown1235,26038,480 MichiganJ. H. Campbell1219,28023,060 MinnesotaHigh Bridge64,270 MississippiJack Watson4517,91036,700 MissouriAsbury116,190 James River54,850 Labadie123440,11037,71040,31035,940 Montrose1237,3908,20010,090 New Madrid1228,24032,480 Sibley315,580 Sioux1222,57023,690 Thomas Hill1210,25019,390 New HampshireMerrimack1210,19022,000 New JerseyB.L. England129,06011,720 New YorkDunkirk3412,60014,060 Greenidge47,540 Milliken1211,17012,410 Northport12319,81024,11026,480 Port Jefferson3410,47012,330 OhioAshtabula516,740 Avon Lake8911,65030,480 Cardinal1234,27038,320 Conesville12344,2104,8905,50048,770 Eastlake123457,8008,64010,02014,51034,070 Edgewater45,050 Gen. J.M. Gavin1279,08080,560 Kyger Creek1234519,28018,56017,91018,71018,740 Miami Fort56776011,38038,510 Muskingum River1234514,88014,17013,95011,78040,470 Niles126,9409,100 Picway54,930 R.E. Burger3456,15010,78012,430 W.H. Sammis56724,17039,93043,220 W.C. Beckjord568,95023,020 PennsylvaniaArmstrong1214,41015,430 Brunner Island12327,76031,10053,820 Cheswick139,170 Conemaugh1259,79066,450 Hatfield’s Ferry12337,83037,32040,270 Martins Creek1212,66012,820 Portland125,94010,230 Shawville123410,32010,32014,22014,070 Sunbury348,76011,450 TennesseeAllen12315,32016,77015,670 Cumberland1286,70094,840 Gallatin123417,87017,31020,02021,260 Johnsonville123456789107,7908,0408,4107,9908,2407,8908,9808,7007,0807,550 West VirginiaAlbright312,000 Fort Martin1241,59041,200 Harrison12348,62046,15041,500 Kammer12318,74019,46017,390 Mitchell1243,98045,510 Mount Storm12343,72035,58042,430 WisconsinEdgewater424,750 La Crosse/Genoa322,700 Nelson Dewey126,0106,680 N. Oak Creek12345,2205,1405,3706,320 Pulliam87,510 S. Oak Creek56789,67012,04016,18015,790
**(f) Energy conservation and renewable energy**
(1) **Definitions** — As used in this subsection:
(A) *Qualified energy conservation measure* — The term “qualified energy conservation measure” means a cost effective measure, as identified by the Administrator in consultation with the Secretary of Energy, that increases the efficiency of the use of electricity provided by an electric utility to its customers.
(B) *Qualified renewable energy* — The term “qualified renewable energy” means energy derived from biomass, solar, geothermal, or wind as identified by the Administrator in consultation with the Secretary of Energy.
(C) *Electric utility* — The term “electric utility” means any person, State agency, or Federal agency, which sells electric energy.
(2) **Allowances for emissions avoided through energy conservation and renewable energy**
(A) *In general* — The regulations under paragraph (4) of this subsection shall provide that for each ton of sulfur dioxide emissions avoided by an electric utility, during the applicable period, through the use of qualified energy conservation measures or qualified renewable energy, the Administrator shall allocate a single allowance to such electric utility, on a first-come-first-served basis from the Conservation and Renewable Energy Reserve established under subsection (g), up to a total of 300,000 allowances for allocation from such Reserve.
(B) *Requirements for issuance* — The Administrator shall allocate allowances to an electric utility under this subsection only if all of the following requirements are met:
(i) Such electric utility is paying for the qualified energy conservation measures or qualified renewable energy directly or through purchase from another person.
(ii) The emissions of sulfur dioxide avoided through the use of qualified energy conservation measures or qualified renewable energy are quantified in accordance with regulations promulgated by the Administrator under this subsection.
(iii)
(I) Such electric utility has adopted and is implementing a least cost energy conservation and electric power plan which evaluates a range of resources, including new power supplies, energy conservation, and renewable energy resources, in order to meet expected future demand at the lowest system cost.
(II) The qualified energy conservation measures or qualified renewable energy, or both, are consistent with that plan.
(III) Electric utilities subject to the jurisdiction of a State regulatory authority must have such plan approved by such authority. For electric utilities not subject to the jurisdiction of a State regulatory authority such plan shall be approved by the entity with rate-making authority for such utility.
(iv) In the case of qualified energy conservation measures undertaken by a State regulated electric utility, the Secretary of Energy certifies that the State regulatory authority with jurisdiction over the electric rates of such electric utility has established rates and charges which ensure that the net income of such electric utility after implementation of specific cost effective energy conservation measures is at least as high as such net income would have been if the energy conservation measures had not been implemented. Upon the date of any such certification by the Secretary of Energy, all allowances which, but for this paragraph, would have been allocated under subparagraph (A) before such date, shall be allocated to the electric utility. This clause is not a requirement for qualified renewable energy.
(v) Such utility or any subsidiary of the utility’s holding company owns or operates at least one affected unit.
(C) *Period of applicability* — Allowances under this subsection shall be allocated only with respect to kilowatt hours of electric energy saved by qualified energy conservation measures or generated by qualified renewable energy after January 1, 1992 and before the earlier of (i) December 31, 2000, or (ii) the date on which any electric utility steam generating unit owned or operated by the electric utility to which the allowances are allocated becomes subject to this subchapter (including those sources that elect to become affected by this subchapter, pursuant to [section 7651i of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651i&num=0&edition=prelim)).
(D) *Determination of avoided emissions*
(i) *88 So in original. There is no cl. (ii). Application* — In order to receive allowances under this subsection, an electric utility shall make an application which—
(I) designates the qualified energy conservation measures implemented and the qualified renewable energy sources used for purposes of avoiding emissions,99 So in original. The comma probably should be a semicolon.
(II) calculates, in accordance with subparagraphs (F) and (G), the number of tons of emissions avoided by reason of the implementation of such measures or the use of such renewable energy sources; and
(III) demonstrates that the requirements of subparagraph (B) have been met.
Such application for allowances by a State-regulated electric utility shall require approval by the State regulatory authority with jurisdiction over such electric utility. The authority shall review the application for accuracy and compliance with this subsection and the rules under this subsection. Electric utilities whose retail rates are not subject to the jurisdiction of a State regulatory authority shall apply directly to the Administrator for such approval.
(E) *Avoided emissions from qualified energy conservation measures* — For the purposes of this subsection, the emission tonnage deemed avoided by reason of the implementation of qualified energy conservation measures for any calendar year shall be a tonnage equal to the product of multiplying—
(i) the kilowatt hours that would otherwise have been supplied by the utility during such year in the absence of such qualified energy conservation measures, by
(ii) 0.004,
(F) *Avoided emissions from the use of qualified renewable energy* — The emissions tonnage deemed avoided by reason of the use of qualified renewable energy by an electric utility for any calendar year shall be a tonnage equal to the product of multiplying—
(i) the actual kilowatt hours generated by, or purchased from, qualified renewable energy, by
(ii) 0.004,
and dividing by 2,000.
(G) *Prohibitions*
(i) No allowances shall be allocated under this subsection for the implementation of programs that are exclusively informational or educational in nature.
(ii) No allowances shall be allocated for energy conservation measures or renewable energy that were operational before January 1, 1992.
(3) **Savings provision** — Nothing in this subsection precludes a State or State regulatory authority from providing additional incentives to utilities to encourage investment in demand-side resources.
(4) **Regulations** — Not later than 18 months after November 15, 1990, and in conjunction with the regulations required to be promulgated under subsections (b) and (c), the Administrator shall, in consultation with the Secretary of Energy, promulgate regulations under this subsection. Such regulations shall list energy conservation measures and renewable energy sources which may be treated as qualified energy conservation measures and qualified renewable energy for purposes of this subsection. Allowances shall only be allocated if all requirements of this subsection and the rules promulgated to implement this subsection are complied with. The Administrator shall review the determinations of each State regulatory authority under this subsection to encourage consistency from electric utility to electric utility and from State to State in accordance with the Administrator’s rules. The Administrator shall publish the findings of this review no less than annually.
**(g) Conservation and Renewable Energy Reserve** The Administrator shall establish a Conservation and Renewable Energy Reserve under this subsection. Beginning on January 1, 1995, the Administrator may allocate from the Conservation and Renewable Energy Reserve an amount equal to a total of 300,000 allowances for emissions of sulfur dioxide pursuant to [section 7651b of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651b&num=0&edition=prelim). In order to provide 300,000 allowances for such reserve, in each year beginning in calendar year 2000 and until calendar year 2009, inclusive, the Administrator shall reduce each unit’s basic Phase II allowance allocation on the basis of its pro rata share of 30,000 allowances. If allowances remain in the reserve after January 2, 2010, the Administrator shall allocate such allowances for affected units under [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim) on a pro rata basis. For purposes of this subsection, for any unit subject to the emissions limitation requirements of [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim), the term “pro rata basis” refers to the ratio which the reductions made in such unit’s allowances in order to establish the reserve under this subsection bears to the total of such reductions for all such units.
**(h) Alternative allowance allocation for units in certain utility systems with optional baseline**
(1) **Optional baseline for units in certain systems** — In the case of a unit subject to the emissions limitation requirements of this section which (as of November 15, 1990)—
(A) has an emission rate below 1.0 lbs/mmBtu,
(B) has decreased its sulfur dioxide emissions rate by 60 percent or greater since 1980, and
(C) is part of a utility system which has a weighted average sulfur dioxide emissions rate for all fossil fueled-fired units below 1.0 lbs/mmBtu,
at the election of the owner or operator of such unit, the unit’s baseline may be calculated (i) as provided under section 7651a(d) 1 of this title, or (ii) by utilizing the unit’s average annual fuel consumption at a 60 percent capacity factor. Such election shall be made no later than March 1, 1991.
(2) **Allowance allocation** — Whenever a unit referred to in paragraph (1) elects to calculate its baseline as provided in clause (ii) of paragraph (1), the Administrator shall allocate allowances for the unit pursuant to [section 7651b(a)(1) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651b/a/1&num=0&edition=prelim), this section, and [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim) (as basic Phase II allowance allocations) in an amount equal to the baseline selected multiplied by the lower of the average annual emission rate for such unit in 1989, or 1.0 lbs./mmBtu. Such allowance allocation shall be in lieu of any allocation of allowances under this section and [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim).
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Permit program** The provisions of this subchapter shall be implemented, subject to [section 7651b of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651b&num=0&edition=prelim), by permits issued to units subject to this subchapter (and enforced) in accordance with the provisions of subchapter V, as modified by this subchapter. Any such permit issued by the Administrator, or by a State with an approved permit program, shall prohibit—
(1) annual emissions of sulfur dioxide in excess of the number of allowances to emit sulfur dioxide the owner or operator, or the designated representative of the owners or operators, of the unit hold for the unit,
(2) exceedances of applicable emissions rates,
(3) the use of any allowance prior to the year for which it was allocated, and
(4) contravention of any other provision of the permit.
Permits issued to implement this subchapter shall be issued for a period of 5 years, notwithstanding subchapter V. No permit shall be issued that is inconsistent with the requirements of this subchapter, and subchapter V as applicable.
**(b) Compliance plan** Each initial permit application shall be accompanied by a compliance plan for the source to comply with its requirements under this subchapter. Where an affected source consists of more than one affected unit, such plan shall cover all such units, and for purposes of [section 7661a(c) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7661a/c&num=0&edition=prelim), such source shall be considered a “facility”. Nothing in this section regarding compliance plans or in subchapter V shall be construed as affecting allowances. Except as provided under subsection (c)(1)(B), submission of a statement by the owner
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651g
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Excess emissions penalty** The owner or operator of any unit or process source subject to the requirements of sections 11 So in original. Probably should be “section”. 7651b, 7651c, 7651d, 7651e, 7651f or 7651h of this title, or designated under [section 7651i of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651i&num=0&edition=prelim), that emits sulfur dioxide or nitrogen oxides for any calendar year in excess of the unit’s emissions limitation requirement or, in the case of sulfur dioxide, of the allowances the owner or operator holds for use for the unit for that calendar year shall be liable for the payment of an excess emissions penalty, except where such emissions were authorized pursuant to [section 7410(f) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7410/f&num=0&edition=prelim). That penalty shall be calculated on the basis of the number of tons emitted in excess of the unit’s emissions limitation requirement or, in the case of sulfur dioxide, of the allowances the operator holds for use for the unit for that year, multiplied by $2,000. Any such penalty shall be due and payable without demand to the Administrator as provided in regulations to be issued by the Administrator by no later than eighteen months after November 15, 1990. Any such payment shall be deposited in the United States Treasury pursuant to the Miscellaneous Receipts Act.22 See References in Text note below. Any penalty due and payable under this section shall not diminish the liability of the unit’s owner or operator for any fine, penalty or assessment against the unit for the same violation under any other section of this chapter.
**(b) Excess emissions offset** The owner or operator of any affected
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651j
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Applicability** The owner or operator of any unit that is not, nor will become, an affected unit under section 7651b(e), 7651c, or 7651d of this title, or that is a process source under subsection (d), that emits sulfur dioxide, may elect to designate that unit or source to become an affected unit and to receive allowances under this subchapter. An election shall be submitted to the Administrator for approval, along with a permit application and proposed compliance plan in accordance with [section 7651g of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651g&num=0&edition=prelim). The Administrator shall approve a designation that meets the requirements of this section, and such designated unit, or source, shall be allocated allowances, and be an affected unit for purposes of this subchapter.
**(b) Establishment of baseline** The baseline for a unit designated under this section shall be established by the Administrator by regulation, based on fuel consumption and operating data for the unit for calendar years 1985, 1986, and 1987, or if such data is not available, the Administrator may prescribe a baseline based on alternative representative data.
**(c) Emission limitations** Annual emissions limitations for sulfur dioxide shall be equal to the product of the baseline multiplied by the lesser of the unit’s 1985 actual or allowable emission rate in lbs/mmBtu, or, if the unit did not operate in 1985, by the lesser of the unit’s actual or allowable emission rate for a calendar year after 1985 (as determined by the Administrator), divided by 2,000.
**(d) Process sources** Not later than 18 months after November 15, 1990, the Administrator shall establish a program under which the owner or operator of a process source that e
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651i
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Allocations of annual allowances for existing and new units**
(1) 11 So in original. No pars. (2) and (3) have been enacted. For the emission limitation programs under this subchapter, the Administrator shall allocate annual allowances for the unit, to be held or distributed by the designated representative of the owner or operator of each affected unit at an affected source in accordance with this subchapter, in an amount equal to the annual tonnage emission limitation calculated under section 7651c, 7651d, 7651e, 7651h, or 7651i of this title except as otherwise specifically provided elsewhere in this subchapter. Except as provided in sections 7651d(a)(2), 7651d(a)(3), 7651h and 7651i of this title, beginning January 1, 2000, the Administrator shall not allocate annual allowances to emit sulfur dioxide pursuant to [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim) in such an amount as would result in total annual emissions of sulfur dioxide from utility units in excess of 8.90 million tons except that the Administrator shall not take into account unused allowances carried forward by owners and operators of affected units or by other persons holding such allowances, following the year for which they were allocated. If necessary to meeting the restrictions imposed in the preceding sentence, the Administrator shall reduce, pro rata, the basic Phase II allowance allocations for each unit subject to the requirements of [section 7651d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651d&num=0&edition=prelim). Subject to the provisions of section 7651o of this title, the Administrator shall allocate allowances for each affected unit at an affe
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651b
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Applicability**
(1) After January 1, 2000, each existing utility unit as provided below is subject to the limitations or requirements of this section. Each utility unit subject to an annual sulfur dioxide tonnage emission limitation under this section is an affected unit under this subchapter. Each source that includes one or more affected units is an affected source. In the case of an existing unit that was not in operation during calendar year 1985, the emission rate for a calendar year after 1985, as determined by the Administrator, shall be used in lieu of the 1985 rate. The owner or operator of any unit operated in violation of this section shall be fully liable under this chapter for fulfilling the obligations specified in [section 7651j of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651j&num=0&edition=prelim).
(2) In addition to basic Phase II allowance allocations, in each year beginning in calendar year 2000 and ending in calendar year 2009, inclusive, the Administrator shall allocate up to 530,000 Phase II bonus allowances pursuant to subsections (b)(2), (c)(4), (d)(3)(A) and (B), and (h)(2) of this section and [section 7651e of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651e&num=0&edition=prelim). Not later than June 1, 1998, the Administrator shall calculate, for each unit granted an extension pursuant to [section 7651h of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651h&num=0&edition=prelim) the difference between (A) the number of allowances allocated for the unit in calendar year 2000, and (B) the product of the unit’s baseline multiplied by 1.20 lbs/mmBtu, divided by 2000, and sum the computations. In each year,
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651d
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Applicability** On the date that a coal-fired utility unit becomes an affected unit pursuant to sections 7651c, 7651d,11 So in original. Probably should be followed by “or”. 7651h of this title, or on the date a unit subject to the provisions of section 7651c(d) or 7651h(b) of this title, must meet the SO2 reduction requirements, each such unit shall become an affected unit for purposes of this section and shall be subject to the emission limitations for nitrogen oxides set forth herein.
**(b) Emission limitations**
(1) Not later than eighteen months after November 15, 1990, the Administrator shall by regulation establish annual allowable emission limitations for nitrogen oxides for the types of utility boilers listed below, which limitations shall not exceed the rates listed below: Provided, That the Administrator may set a rate higher than that listed for any type of utility boiler if the Administrator finds that the maximum listed rate for that boiler type cannot be achieved using low NOx burner technology. The maximum allowable emission rates are as follows:
(A) for tangentially fired boilers, 0.45 lb/mmBtu;
(B) for dry bottom wall-fired boilers (other than units applying cell burner technology), 0.50 lb/mmBtu.
After January 1, 1995, it shall be unlawful for any unit that is an affected unit on that date and is of the type listed in this paragraph to emit nitrogen oxides in excess of the emission rates set by the Administrator pursuant to this paragraph.
(2) Not later than January 1, 1997, the Administrator shall, by regulation, establish allowable emission limitations on a lb/mmBtu, annual average basis, for nitrogen oxides for the following types of utility boilers:
(A) wet bottom wall-fired boilers;
(B) cyclones;
(C) units applying cell
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651f
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Applicability** The owner and operator of any source subject to this subchapter shall be required to install and operate CEMS on each affected unit at the source, and to quality assure the data for sulfur dioxide, nitrogen oxides, opacity and volumetric flow at each such unit. The Administrator shall, by regulations issued not later than eighteen months after November 15, 1990, specify the requirements for CEMS, for any alternative monitoring system that is demonstrated as providing information with the same precision, reliability, accessibility, and timeliness as that provided by CEMS, and for recordkeeping and reporting of information from such systems. Such regulations may include limitations or the use of alternative compliance methods by units equipped with an alternative monitoring system as may be necessary to preserve the orderly functioning of the allowance system, and which will ensure the emissions reductions contemplated by this subchapter. Where 2 or more units utilize a single stack, a separate CEMS shall not be required for each unit, and for such units the regulations shall require that the owner or operator collect sufficient information to permit reliable compliance determinations for each such unit.
**(b) First phase requirements** Not later than thirty-six months after November 15, 1990, the owner or operator of each affected unit under [section 7651c of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651c&num=0&edition=prelim), including, but not limited to, units that become affected units pursuant to subsections (b) and (c) and eligible units under subsection (d), shall install and operate CEMS, quality assure the data, and keep records and reports in accordance with the regulations issued under subs
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651k
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Definitions** For purposes of this section—
(1) The term “independent power producer” means any person who owns or operates, in whole or in part, one or more new independent power production facilities.
(2) The term “new independent power production facility” means a facility that—
(A) is used for the generation of electric energy, 80 percent or more of which is sold at wholesale;
(B) is nonrecourse project-financed (as such term is defined by the Secretary of Energy within 3 months of November 15, 1990);
(C) does not generate electric energy sold to any affiliate (as defined in section 79b(a)(11) 11 See References in Text note below. of title 15) of the facility’s owner or operator unless the owner or operator of the facility demonstrates that it cannot obtain allowances from the affiliate; and
(D) is a new unit required to hold allowances under this subchapter.
(3) The term “required allowances” means the allowances required to operate such unit for so much of the unit’s useful life as occurs after January 1, 2000.
**(b) Special reserve of allowances** Within 36 months after November 15, 1990, the Administrator shall promulgate regulations establishing a Special Allowance Reserve containing allowances to be sold under this section. For purposes of establishing the Special Allowance Reserve, the Administrator shall withhold—
(1) 2.8 percent of the allocation of allowances for each year from 1995 through 1999 inclusive; and
(2) 2.8 percent of the basic Phase II allowance allocation of allowances for each year beginning in the year 2000
which would (but for this subsection) be issued for each affected unit at an affected source. The Administrator shall record such withholding for purposes of transferring the proceeds of the allowance sales under t
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651o
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Page 7418
TITLE 42—THE PUBLIC HEALTH AND WELFARE
§ 7651c
2 See References in Text note below.
(h) Competitive bidding for power supply
Nothing in this subchapter shall be construed
to interfere with or impair any program for
competitive bidding for power supply in a State
in which such program is established.
(i) Applicability of antitrust laws
(1) Nothing in this section affects—
(A) the applicability of the antitrust laws to
the transfer, use, or sale of allowances, or
(B) the authority of the Federal Energy Reg-
ulatory Commission under any provision of
law respecting unfair methods of competition
or anticompetitive acts or practices.
(2) As used in this section, ‘‘antitrust laws’’
means those Acts set forth in section 12 of title
15.
(j) Public Utility Holding Company Act
The acquisition or disposition of allowances
pursuant to this subchapter including the
issuance of securities or the undertaking of any
other financing transaction in connection with
such allowances shall not be subject to the pro-
visions of the Public Utility Holding Company
Act of 1935.2
(July 14, 1955, ch. 360, title IV, § 403, as added
Pub. L. 101–549, title IV, § 401, Nov. 15, 1990, 104
Stat. 2589.)
Editorial Notes
REFERENCES IN TEXT
The Federal Power Act, referred to in subsec. (f), is
act June 10, 1920, ch. 285, 41 Stat. 1063, which is classi-
fied generally to chapter 12 (§ 791a et seq.) of Title 16,
Conservation. For complete classification of this Act to
the Code, see section 791a of Title 16 and Tables.
The Public Utility Holding Company Act of 1935, re-
ferred to in subsec. (j), is title I of act Aug. 26, 1935, ch.
687, 49 Stat. 803, which was classified generally to chap-
ter 2C (§ 79 et seq.) of Title 15, Commerce and Trade,
prior to repeal by Pub. L.
Source: Supplied 2024 U.S. Code historical extraction · 42 U.S.C. § 7651c
Stored review status: historical_2024_not_currentness_verified. Same stored citation; legal effect and authority still require review.