30 U.S.C. § 1260 — Permit approval or denial
Federal law — U.S. Code and appendices · legal_authorities
**(a) Basis for decision; notification of applicant and local government officials; burden of proof** Upon the basis of a complete mining application and reclamation plan or a revision or renewal thereof, as required by this chapter and pursuant to an approved State program or Federal program under the provisions of this chapter, including public notification and an opportunity for a public hearing as required by [section 1263 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title30-section1263&num=0&edition=prelim), the regulatory authority shall grant, require modification of, or deny the application for a permit in a reasonable time set by the regulatory authority and notify the applicant in writing. The applicant for a permit, or revision of a permit, shall have the burden of establishing that his application is in compliance with all the requirements of the applicable State or Federal program. Within ten days after the granting of a permit, the regulatory authority shall notify the local governmental officials in the local political subdivision in which the area of land to be affected is located that a permit has been issued and shall describe the location of the land.
**(b) Requirements for approval** No permit or revision application shall be approved unless the application affirmatively demonstrates and the regulatory authority finds in writing on the basis of the information set forth in the application or from information otherwise available which will be documented in the approval, and made available to the applicant, that—
(1) the permit application is accurate and complete and that all the requirements of this chapter and the State or Federal program have been complied with;
(2) the applicant has demonstrated that reclamation a
Source: Supplied U.S. Code snapshot — release unconfirmed · 30 U.S.C. § 1260
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: a7b3e6c798c601664379f1dfa94747937832f038cc9eb0c0b17d7bea7ca29164. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_76c9a0aa91bd48031ac501da
Source file: Laws/federal/codes/united-states-code/title-30/section-1260-permit-approval-or-denial--7422d65cbe.md
Pages: Not recorded – Not recorded
Passage SHA-256: 41eb56fbe4919f1c8b8db692c13253d0f722b92e293e60e35f44a2bc196aad03
Source location: Title 30, Chapter 25, § 1260; chapter-025-surface-mining-control-and-reclamation.md
Stored source content
**(a) Basis for decision; notification of applicant and local government officials; burden of proof** Upon the basis of a complete mining application and reclamation plan or a revision or renewal thereof, as required by this chapter and pursuant to an approved State program or Federal program under the provisions of this chapter, including public notification and an opportunity for a public hearing as required by [section 1263 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title30-section1263&num=0&edition=prelim), the regulatory authority shall grant, require modification of, or deny the application for a permit in a reasonable time set by the regulatory authority and notify the applicant in writing. The applicant for a permit, or revision of a permit, shall have the burden of establishing that his application is in compliance with all the requirements of the applicable State or Federal program. Within ten days after the granting of a permit, the regulatory authority shall notify the local governmental officials in the local political subdivision in which the area of land to be affected is located that a permit has been issued and shall describe the location of the land.
**(b) Requirements for approval** No permit or revision application shall be approved unless the application affirmatively demonstrates and the regulatory authority finds in writing on the basis of the information set forth in the application or from information otherwise available which will be documented in the approval, and made available to the applicant, that—
(1) the permit application is accurate and complete and that all the requirements of this chapter and the State or Federal program have been complied with;
(2) the applicant has demonstrated that reclamation as required by this chapter and the State or Federal program can be accomplished under the reclamation plan contained in the permit application;
(3) the assessment of the probable cumulative impact of all anticipated mining in the area on the hydrologic balance specified in [section 1257(b) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title30-section1257/b&num=0&edition=prelim) has been made by the regulatory authority and the proposed operation thereof has been designed to prevent material damage to hydrologic balance outside permit area;
(4) the area proposed to be mined is not included within an area designated unsuitable for surface coal mining pursuant to [section 1272 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title30-section1272&num=0&edition=prelim) or is not within an area under study for such designation in an administrative proceeding commenced pursuant to section 1272(a)(4)(D) or [section 1272(c) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title30-section1272/c&num=0&edition=prelim) (unless in such an area as to which an administrative proceeding has commenced pursuant to [section 1272(a)(4)(D) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title30-section1272/a/4/D&num=0&edition=prelim), the operator making the permit application demonstrates that, prior to January 1, 1977, he has made substantial legal and financial commitments in relation to the operation for which he is applying for a permit);
(5) the proposed surface coal mining operation, if located west of the one hundredth meridian west longitude, would— Provided, That this paragraph (5) shall not affect those surface coal mining operations which in the year preceding August 3, 1977, (I) produced coal in commercial quantities, and were located within or adjacent to alluvial valley floors or (II) had obtained specific permit approval by the State regulatory authority to conduct surface coal mining operations within said alluvial valley floors.
(A) not interrupt, discontinue, or preclude farming on alluvial valley floors that are irrigated or naturally subirrigated, but, excluding undeveloped range lands which are not significant to farming on said alluvial valley floors and those lands as to which the regulatory authority finds that if the farming that will be interrupted, discontinued, or precluded is of such small acreage as to be of negligible impact on the farm’s agricultural production, or
(B) not materially damage the quantity or quality of water in surface or underground water systems that supply these valley floors in (A) of subsection (b)(5):
With respect to such surface mining operations which would have been within the purview of the foregoing proviso but for the fact that no coal was so produced in commercial quantities and no such specific permit approval was so received, the Secretary, if he determines that substantial financial and legal commitments were made by an operator prior to January 1, 1977, in connection with any such operation, is authorized, in accordance with such regulations as the Secretary may prescribe, to enter into an agreement with that operator pursuant to which the Secretary may, notwithstanding any other provision of law, lease other Federal coal deposits to such operator in exchange for the relinquishment by such operator of his Federal lease covering coal deposits involving such mining operations, or pursuant to [section 1716 of title 43](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title43-section1716&num=0&edition=prelim), convey to the fee holder of any such coal deposits involving such mining operations the fee title to other available Federal coal deposits in exchange for the fee title to such deposits so involving such mining operations. It is the policy of the Congress that the Secretary shall develop and carry out a coal exchange program to acquire private fee coal precluded from being mined by the restrictions of this paragraph (5) in exchange for Federal coal which is not so precluded. Such exchanges shall be made under [section 1716 of title 43](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title43-section1716&num=0&edition=prelim);
(6) in cases where the private mineral estate has been severed from the private surface estate, the applicant has submitted to the regulatory authority—
(A) the written consent of the surface owner to the extraction of coal by surface mining methods; or
(B) a conveyance that expressly grants or reserves the right to extract the coal by surface mining methods; or
(C) if the conveyance does not expressly grant the right to extract coal by surface mining methods, the surface-subsurface legal relationship shall be determined in accordance with State law: Provided, That nothing in this chapter shall be construed to authorize the regulatory authority to adjudicate property rights disputes.
**(c) Schedule of violations** The applicant shall file with his permit application a schedule listing any and all notices of violations of this chapter and any law, rule, or regulation of the United States, or of any department or agency in the United States pertaining to air or water environmental protection incurred by the applicant in connection with any surface coal mining operation during the three-year period prior to the date of application. The schedule shall also indicate the final resolution of any such notice of violation. Where the schedule or other information available to the regulatory authority indicates that any surface coal mining operation owned or controlled by the applicant is currently in violation of this chapter or such other laws referred to 11 So in original. Probably should be followed by “in”. this subsection, the permit shall not be issued until the applicant submits proof that such violation has been corrected or is in the process of being corrected to the satisfaction of the regulatory authority, department, or agency which has jurisdiction over such violation and no permit shall be issued to an applicant after a finding by the regulatory authority, after opportunity for hearing, that the applicant, or the operator specified in the application, controls or has controlled mining operations with a demonstrated pattern of willful violations of this chapter of such nature and duration with such resulting irreparable damage to the environment as to indicate an intent not to comply with the provisions of this chapter.
**(d) Prime farmland mining permit**
(1) In addition to finding the application in compliance with subsection (b) of this section, if the area proposed to be mined contains prime farmland pursuant to [section 1257(b)(16) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title30-section1257/b/16&num=0&edition=prelim), the regulatory authority shall, after consultation with the Secretary of Agriculture, and pursuant to regulations issued hereunder by the Secretary of 22 So in original. Probably should be “of the”. Interior with the concurrence of the Secretary of Agriculture, grant a permit to mine on prime farmland if the regulatory authority finds in writing that the operator has the technological capability to restore such mined area, within a reasonable time, to equivalent or higher levels of yield as non-mined prime farmland in the surrounding area under equivalent levels of management and can meet the soil reconstruction standards in [section 1265(b)(7) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title30-section1265/b/7&num=0&edition=prelim). Except for compliance with subsection (b), the requirements of this paragraph (1) shall apply to all permits issued after August 3, 1977.
(2) Nothing in this subsection shall apply to any permit issued prior to August 3, 1977, or to any revisions or renewals thereof, or to any existing surface mining operations for which a permit was issued prior to August 3, 1977.
**(e) Modification of prohibition** After October 24, 1992, the prohibition of subsection (c) shall not apply to a permit application due to any violation resulting from an unanticipated event or condition at a surface coal mining operation on lands eligible for remining under a permit held by the person making such application. As used in this subsection, the term “violation” has the same meaning as such term has under subsection (c).
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Authorization and limitations on authority of Secretary of the Interior and Secretary of Agriculture** A tract of public land or interests therein may be disposed of by exchange by the Secretary under this Act and a tract of land or interests therein within the National Forest System may be disposed of by exchange by the Secretary of Agriculture under applicable law where the Secretary concerned determines that the public interest will be well served by making that exchange: Provided, That when considering public interest the Secretary concerned shall give full consideration to better Federal land management and the needs of State and local people, including needs for lands for the economy, community expansion, recreation areas, food, fiber, minerals, and fish and wildlife and the Secretary concerned finds that the values and the objectives which Federal lands or interests to be conveyed may serve if retained in Federal ownership are not more than the values of the non-Federal lands or interests and the public objectives they could serve if acquired.
**(b) Implementation requirements; cash equalization waiver** In exercising the exchange authority granted by subsection (a) or by [section 1715(a) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title43-section1715/a&num=0&edition=prelim), the Secretary concerned may accept title to any non-Federal land or interests therein in exchange for such land, or interests therein which he finds proper for transfer out of Federal ownership and which are located in the same State as the non-Federal land or interest to be acquired. For the purposes of this subsection, unsurveyed school sections which, upon survey by the Secretary, would become State lands, shall be considered as “non-Federal lands”.
Source: Supplied U.S. Code snapshot — release unconfirmed · 43 U.S.C. § 1716
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Submittal of advertisement to regulatory authority; notification of local governmental bodies** At the time of submission of an application for a surface coal mining and reclamation permit, or revision of an existing permit, pursuant to the provisions of this chapter or an approved State program, the applicant shall submit to the regulatory authority a copy of his advertisement of the ownership, precise location, and boundaries of the land to be affected. At the time of submission such advertisement shall be placed by the applicant in a local newspaper of general circulation in the locality of the proposed surface mine at least once a week for four consecutive weeks. The regulatory authority shall notify various local governmental bodies, planning agencies, and sewage and water treatment authorities, of 11 So in original. Probably should be “or”. water companies in the locality in which the proposed surface mining will take place, notifying them of the operator’s intention to surface mine a particularly described tract of land and indicating the application’s permit number and where a copy of the proposed mining and reclamation plan may be inspected. These local bodies, agencies, authorities, or companies may submit written comments within a reasonable period established by the regulatory authority on the mining applications with respect to the effect of the proposed operation on the environment which are within their area of responsibility. Such comments shall immediately be transmitted to the applicant by the regulatory authority and shall be made available to the public at the same locations as are the mining applications.
**(b) Objections to permit applications; informal conference; record** Any person having an interest which is or may be adversely affected
Source: Supplied U.S. Code snapshot — release unconfirmed · 30 U.S.C. § 1263
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Establishment of State planning process; standards; State process requirements; integration with present and future land use planning and regulation processes; savings provisions**
(1) To be eligible to assume primary regulatory authority pursuant to [section 1253 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title30-section1253&num=0&edition=prelim), each State shall establish a planning process enabling objective decisions based upon competent and scientifically sound data and information as to which, if any, land areas of a State are unsuitable for all or certain types of surface coal mining operations pursuant to the standards set forth in paragraphs (2) and (3) of this subsection but such designation shall not prevent the mineral exploration pursuant to the chapter of any area so designated.
(2) Upon petition pursuant to subsection (c) of this section, the State regulatory authority shall designate an area as unsuitable for all or certain types of surface coal mining operations if the State regulatory authority determines that reclamation pursuant to the requirements of this chapter is not technologically and economically feasible.
(3) Upon petition pursuant to subsection (c) of this section, a surface area may be designated unsuitable for certain types of surface coal mining operations if such operations will—
(A) be incompatible with existing State or local land use plans or programs; or
(B) affect fragile or historic lands in which such operations could result in significant damage to important historic, cultural, scientific, and esthetic values and natural systems; or
(C) affect renewable resource lands in which such operations could result in a substantial loss or reduction of long-range productivity of water sup
Source: Supplied U.S. Code snapshot — release unconfirmed · 30 U.S.C. § 1272
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Page 282
TITLE 30—MINERAL LANDS AND MINING
§ 1260
(c) Bond of applicant without separate surety; al-
ternate system
The regulatory authority may accept the bond
of the applicant itself without separate surety
when the applicant demonstrates to the satis-
faction of the regulatory authority the exist-
ence of a suitable agent to receive service of
process and a history of financial solvency and
continuous operation sufficient for authoriza-
tion to self-insure or bond such amount or in
lieu of the establishment of a bonding program,
as set forth in this section, the Secretary may
approve as part of a State or Federal program
an alternative system that will achieve the ob-
jectives and purposes of the bonding program
pursuant to this section.
(d) Deposit of cash or securities
Cash or securities so deposited shall be depos-
ited upon the same terms as the terms upon
which surety bonds may be deposited. Such se-
curities shall be security for the repayment of
such negotiable certificate of deposit.
(e) Adjustments
The amount of the bond or deposit required
and the terms of each acceptance of the appli-
cant’s bond shall be adjusted by the regulatory
authority from time to time as affected land
acreages are increased or decreased or where the
cost of future reclamation changes.
(Pub. L. 95–87, title V, § 509, Aug. 3, 1977, 91 Stat.
479.)
§ 1260. Permit approval or denial
(a) Basis for decision; notification of applicant
and local government officials; burden of
proof
Upon the basis of a complete mining applica-
tion and reclamation plan or a revision or re-
newal thereof, as required by this chapter and
pursuant to an approved State program or Fed-
eral program under the provisions of this chap-
ter, including public notification and an oppor-
tun
Source: Supplied 2024 U.S. Code historical extraction · 30 U.S.C. § 1260