**(a) In general** Not later than February 1 of each year, the Secretary shall develop and submit to Congress an annual report, to be entitled “Report to Congress on Authorized Water Resources Development Projects and Studies”, that identifies—
(1) ongoing or new feasibility studies, authorized within the previous 20 years, for which a Report of the Chief of Engineers has not been issued;
(2) authorized feasibility studies for projects in the preconstruction, engineering and design phase;
(3) ongoing or new water resources development projects authorized for construction within the previous 20 years; and
(4) authorized and constructed water resources development projects the Secretary has the responsibility to operate or maintain.
**(b) Contents**
(1) **Inclusions**
(A) *Criteria* — The Secretary shall include in each report submitted under this section only a feasibility study or water resources development project—
(i) that has been authorized by Congress to be carried out by the Secretary and does not require any additional congressional authorization to be carried out;
(ii) that the Secretary has the capability to carry out if funds are appropriated for such study or project under any of the “Investigations”, “Construction”, “Operation and Maintenance”, or “Mississippi River and Tributaries” appropriations accounts for the Corps of Engineers; and
(iii) for which a non-Federal interest—
(I) in the case of a study or a project other than a project for which funds may be appropriated for operation and maintenance, has entered into a feasibility cost-sharing agreement, design agreement, or project partnership agreement with the Corps of Engineers, or has informed the Secretary that the non-Federal interest has the financial capability to e
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2282g
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: 27bebb3327ba5cff3ba681e6692d9619e376eacb8911abea138f27ea7c30194f. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_4a6c6c11d30667fb13091d48
Source file: Laws/federal/codes/united-states-code/title-33/section-2282g-report-to-congress-on-authorized-studies-and-projects--585cece953.md
Pages: Not recorded – Not recorded
Passage SHA-256: a42177c186ac0455786d3d62e3a029e1a011aba80ce6c1422e299c507b8fa5ee
Source location: Title 33, Chapter 36, § 2282g; chapter-036-water-resources-development.md
Stored source content
**(a) In general** Not later than February 1 of each year, the Secretary shall develop and submit to Congress an annual report, to be entitled “Report to Congress on Authorized Water Resources Development Projects and Studies”, that identifies—
(1) ongoing or new feasibility studies, authorized within the previous 20 years, for which a Report of the Chief of Engineers has not been issued;
(2) authorized feasibility studies for projects in the preconstruction, engineering and design phase;
(3) ongoing or new water resources development projects authorized for construction within the previous 20 years; and
(4) authorized and constructed water resources development projects the Secretary has the responsibility to operate or maintain.
**(b) Contents**
(1) **Inclusions**
(A) *Criteria* — The Secretary shall include in each report submitted under this section only a feasibility study or water resources development project—
(i) that has been authorized by Congress to be carried out by the Secretary and does not require any additional congressional authorization to be carried out;
(ii) that the Secretary has the capability to carry out if funds are appropriated for such study or project under any of the “Investigations”, “Construction”, “Operation and Maintenance”, or “Mississippi River and Tributaries” appropriations accounts for the Corps of Engineers; and
(iii) for which a non-Federal interest—
(I) in the case of a study or a project other than a project for which funds may be appropriated for operation and maintenance, has entered into a feasibility cost-sharing agreement, design agreement, or project partnership agreement with the Corps of Engineers, or has informed the Secretary that the non-Federal interest has the financial capability to enter into such an agreement within 1 year; and
(II) demonstrates the legal and financial capability to satisfy the requirements for local cooperation with respect to the study or project.
(B) *Description of benefits*
(i) *Description* — The Secretary shall, to the maximum extent practicable, describe in each report submitted under this section the benefits, as described in clause (ii), of each feasibility study and water resources development project included in the report.
(ii) *Benefits* — The benefits referred to in clause (i) are benefits to—
(I) the protection of human life and property;
(II) improvement to transportation;
(III) the national, regional, or local economy;
(IV) the environment; or
(V) the national security interests of the United States.
(2) **Transparency** — The Secretary shall include in each report submitted under this section, for each feasibility study and water resources development project included in the report—
(A) the name of the associated non-Federal interest, including the name of any non-Federal interest that has contributed, or is expected to contribute, a non-Federal share of the cost of the study or project;
(B) the purpose of the study or project;
(C) an estimate, to the extent practicable, of the Federal, non-Federal, and total costs of the study or project, including, to the extent practicable, the fully funded capability of the Corps of Engineers for—
(i) the 3 fiscal years following the fiscal year in which the report is submitted, in the case of a feasibility study; and
(ii) the 5 fiscal years following the fiscal year in which the report is submitted, in the case of a water resources development project; and
(D) an estimate, to the extent practicable, of the monetary and nonmonetary benefits of the study or project.
(3) **Certification** — The Secretary shall include in each report submitted under this section a certification stating that each feasibility study or water resources development project included in the report meets the criteria described in paragraph (1)(A).
(4) **Omissions**
(A) *Limitation* — The Secretary shall not omit from a report submitted under this section a study or project that otherwise meets the criteria for inclusion in the report solely on the basis of a policy of the Secretary.
(B) *Appendix* — If the Secretary omits from a report submitted under this section a study or project that otherwise meets the criteria for inclusion in the report, the Secretary shall include with the report an appendix that lists the name of the study or project and reason for its omission.
**(c) Submission to Congress; publication**
(1) **Submission to Congress** — The Secretary may submit a report under this section in conjunction with the submission of the annual report under [section 2282d of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2282d&num=0&edition=prelim).
(2) **Publication** — On submission of each report under this section, the Secretary shall make the report publicly available, including through publication on the internet.
**(d) Definitions** In this section:
(1) **Non-Federal interest** — The term “non-Federal interest” has the meaning given that term in [section 1962d–5b of title 42](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section1962d–5b&num=0&edition=prelim).
(2) **Water resources development project** — The term “water resources development project” includes a separable element of a project, a project under an environmental infrastructure assistance program, and a project the authorized purposes of which include water supply.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
In any case in which a project under the jurisdiction of the Secretary is budgeted under a different business line than the business line under which the project was originally authorized, the Secretary shall ensure that the project is carried out in accordance with any requirements that apply to the business line under which the project was originally authorized.
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2201
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Omitted**
**(b) Planning process improvements** The Chief of Engineers—
(1) shall adopt a risk analysis approach to project cost estimates for water resources projects; and
(2) not later than one year after November 8, 2007, shall—
(A) issue procedures for risk analysis for cost estimation for water resources projects; and
(B) submit to Congress a report that includes any recommended amendments to [section 2280 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2280&num=0&edition=prelim).
**(c) Benchmarks**
(1) **In general** — Not later than 12 months after November 8, 2007, the Chief of Engineers shall establish benchmarks for determining the length of time it should take to conduct a feasibility study for a water resources project and its associated review process under the National Environmental Policy Act of 1969 ([42 U.S.C. 4321](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section4321&num=0&edition=prelim) et seq.). The Chief of Engineers shall use such benchmarks as a management tool to make the feasibility study process more efficient in all districts of the Corps of Engineers.
(2) **Benchmark goals** — The Chief of Engineers shall establish, to the extent practicable, under paragraph (1) benchmark goals for completion of feasibility studies for water resources projects generally within 2 years. In the case of feasibility studies that the Chief of Engineers determines may require additional time based on the project type, size, cost, or complexity, the benchmark goal for completion shall be generally within 4 years.
**(d) Calculation of benefits and costs for flood damage reduction projects** A feasibility study for a project for flood damage reduction shall include, as part of t
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2282d
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
The Council is authorized to delegate to any member or employee of the Council its administrative functions under [section 1962a–4 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section1962a-4&num=0&edition=prelim) and the detailed administration of the grant program under subchapter III.
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 1962d–5b
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Page 775
TITLE 33—NAVIGATION AND NAVIGABLE WATERS
§ 2282g
§ 2282e. Post-authorization change reports
(a) In general
The completion of a post-authorization change
report prepared by the Corps of Engineers for a
water resources development project—
(1) may not be delayed as a result of consid-
eration being given to changes in policy or pri-
ority with respect to project consideration;
and
(2) shall be submitted, upon completion, to—
(A) the Committee on Environment and
Public Works of the Senate; and
(B) the Committee on Transportation and
Infrastructure of the House of Representa-
tives.
(b) Completion review
With respect to a post-authorization change
report subject to review by the Secretary, the
Secretary shall, not later than 120 days after the
date of completion of such report—
(1) review the report; and
(2) provide to Congress any recommenda-
tions of the Secretary regarding modification
of the applicable water resources development
project.
(c) Prior reports
Not later than 120 days after December 16,
2016, with respect to any post-authorization
change report that was completed prior to De-
cember 16, 2016, and is subject to a review by the
Secretary that has yet to be completed, the Sec-
retary shall complete review of, and provide rec-
ommendations to Congress with respect to, the
report.
(d) Post-authorization change report inclusions
In this section, the term ‘‘post-authorization
change report’’ includes—
(1) a general reevaluation report;
(2) a limited reevaluation report; and
(3) any other report that recommends the
modification of an authorized water resources
development project.
(Pub. L. 114–322, title I, § 1132, Dec. 16, 2016, 130
Stat. 1653.)
Editorial Notes
CODIFICATION
Section was enacted as part of the Water Resourc
Source: Supplied 2024 U.S. Code historical extraction · 33 U.S.C. § 2282g
Stored review status: historical_2024_not_currentness_verified. Same stored citation; legal effect and authority still require review.