16 U.S.C. § 824i — Interconnection authority
Federal law — U.S. Code and appendices · legal_authorities
**(a) Powers of Commission; application by State regulatory authority**
(1) Upon application of any electric utility, Federal power marketing agency, geothermal power producer (including a producer which is not an electric utility), qualifying cogenerator, or qualifying small power producer, the Commission may issue an order requiring—
(A) the physical connection of any cogeneration facility, any small power production facility, or the transmission facilities of any electric utility, with the facilities of such applicant,
(B) such action as may be necessary to make effective any physical connection described in subparagraph (A), which physical connection is ineffective for any reason, such as inadequate size, poor maintenance, or physical unreliability,
(C) such sale or exchange of electric energy or other coordination, as may be necessary to carry out the purposes of any order under subparagraph (A) or (B), or
(D) such increase in transmission capacity as may be necessary to carry out the purposes of any order under subparagraph (A) or (B).
(2) Any State regulatory authority may apply to the Commission for an order for any action referred to in subparagraph (A), (B), (C), or (D) of paragraph (1). No such order may be issued by the Commission with respect to a Federal power marketing agency upon application of a State regulatory authority.
**(b) Notice, hearing and determination by Commission** Upon receipt of an application under subsection (a), the Commission shall—
(1) issue notice to each affected State regulatory authority, each affected electric utility, each affected Federal power marketing agency, each affected owner or operator of a cogeneration facility or of a small power production facility, and to the public.11 So in original. The period pro
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 824i
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: 9c58816bcbe6fcdf90f500a15921e3fd2f562db9299596b26686f139f1b1c309. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_0e6eb62097a693d96d52c94e
Source file: Laws/federal/codes/united-states-code/title-16/section-824i-interconnection-authority--f7e816dba1.md
Pages: Not recorded – Not recorded
Passage SHA-256: 5e362a9332f8db02ae8279e895be1d464b227ba8926b965b913e82372cd19847
Source location: Title 16, Chapter 12, § 824i; chapter-012-federal-regulation-and-development-of-power.md
Stored source content
**(a) Powers of Commission; application by State regulatory authority**
(1) Upon application of any electric utility, Federal power marketing agency, geothermal power producer (including a producer which is not an electric utility), qualifying cogenerator, or qualifying small power producer, the Commission may issue an order requiring—
(A) the physical connection of any cogeneration facility, any small power production facility, or the transmission facilities of any electric utility, with the facilities of such applicant,
(B) such action as may be necessary to make effective any physical connection described in subparagraph (A), which physical connection is ineffective for any reason, such as inadequate size, poor maintenance, or physical unreliability,
(C) such sale or exchange of electric energy or other coordination, as may be necessary to carry out the purposes of any order under subparagraph (A) or (B), or
(D) such increase in transmission capacity as may be necessary to carry out the purposes of any order under subparagraph (A) or (B).
(2) Any State regulatory authority may apply to the Commission for an order for any action referred to in subparagraph (A), (B), (C), or (D) of paragraph (1). No such order may be issued by the Commission with respect to a Federal power marketing agency upon application of a State regulatory authority.
**(b) Notice, hearing and determination by Commission** Upon receipt of an application under subsection (a), the Commission shall—
(1) issue notice to each affected State regulatory authority, each affected electric utility, each affected Federal power marketing agency, each affected owner or operator of a cogeneration facility or of a small power production facility, and to the public.11 So in original. The period probably should be a comma.
(2) afford an opportunity for an evidentiary hearing, and
(3) make a determination with respect to the matters referred to in subsection (c).
**(c) Necessary findings** No order may be issued by the Commission under subsection (a) unless the Commission determines that such order—
(1) is in the public interest,
(2) would—
(A) encourage overall conservation of energy or capital,
(B) optimize the efficiency of use of facilities and resources, or
(C) improve the reliability of any electric utility system or Federal power marketing agency to which the order applies, and
(3) meets the requirements of [section 824k of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section824k&num=0&edition=prelim).
**(d) Motion of Commission** The Commission may, on its own motion, after compliance with the requirements of paragraphs (1) and (2) of subsection (b), issue an order requiring any action described in subsection (a)(1) if the Commission determines that such order meets the requirements of subsection (c). No such order may be issued upon the Commission’s own motion with respect to a Federal power marketing agency.
**(e) Definitions**
(1) As used in this section, the term “facilities” means only facilities used for the generation or transmission of electric energy.
(2) With respect to an order issued pursuant to an application of a qualifying cogenerator or qualifying small power producer under subsection (a)(1), the term “facilities of such applicant” means the qualifying cogeneration facilities or qualifying small power production facilities of the applicant, as specified in the application. With respect to an order issued pursuant to an application under subsection (a)(2), the term “facilities of such applicant” means the qualifying cogeneration facilities, qualifying small power production facilities, or the transmission facilities of an electric utility, as specified in the application. With respect to an order issued by the Commission on its own motion under subsection (d), such term means the qualifying cogeneration facilities, qualifying small power production facilities, or the transmission facilities of an electric utility, as specified in the proposed order.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Rates, charges, terms, and conditions for wholesale transmission services** An order under [section 824j of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section824j&num=0&edition=prelim) shall require the transmitting utility subject to the order to provide wholesale transmission services at rates, charges, terms, and conditions which permit the recovery by such utility of all the costs incurred in connection with the transmission services and necessary associated services, including, but not limited to, an appropriate share, if any, of legitimate, verifiable and economic costs, including taking into account any benefits to the transmission system of providing the transmission service, and the costs of any enlargement of transmission facilities. Such rates, charges, terms, and conditions shall promote the economically efficient transmission and generation of electricity and shall be just and reasonable, and not unduly discriminatory or preferential. Rates, charges, terms, and conditions for transmission services provided pursuant to an order under [section 824j of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section824j&num=0&edition=prelim) shall ensure that, to the extent practicable, costs incurred in providing the wholesale transmission services, and properly allocable to the provision of such services, are recovered from the applicant for such order and not from a transmitting utility’s existing wholesale, retail, and transmission customers.
**(b) Repealed. Pub. L. 102–486, title VII, § 722(1), Oct. 24, 1992, 106 Stat. 2916**
**(c) Issuance of proposed order; agreement by parties to terms and conditions of order; approval by Commission; inclusion in final order; failure to agree**
(1)
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 824k
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Cogeneration and small power production rules** Not later than 1 year after November 9, 1978, the Commission shall prescribe, and from time to time thereafter revise, such rules as it determines necessary to encourage cogeneration and small power production, and to encourage geothermal small power production facilities of not more than 80 megawatts capacity, which rules require electric utilities to offer to—
(1) sell electric energy to qualifying cogeneration facilities and qualifying small power production facilities 11 So in original. Probably should be followed by a comma. and
(2) purchase electric energy from such facilities.
Such rules shall be prescribed, after consultation with representatives of Federal and State regulatory agencies having ratemaking authority for electric utilities, and after public notice and a reasonable opportunity for interested persons (including State and Federal agencies) to submit oral as well as written data, views, and arguments. Such rules shall include provisions respecting minimum reliability of qualifying cogeneration facilities and qualifying small power production facilities (including reliability of such facilities during emergencies) and rules respecting reliability of electric energy service to be available to such facilities from electric utilities during emergencies. Such rules may not authorize a qualifying cogeneration facility or qualifying small power production facility to make any sale for purposes other than resale.
**(b) Rates for purchases by electric utilities** The rules prescribed under subsection (a) shall insure that, in requiring any electric utility to offer to purchase electric energy from any qualifying cogeneration facility or qualifying small power production facility, the rates for such purcha
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 824a–3
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Transmission service by any electric utility; notice, hearing and findings by Commission** Any electric utility, Federal power marketing agency, or any other person generating electric energy for sale for resale, may apply to the Commission for an order under this subsection requiring a transmitting utility to provide transmission services (including any enlargement of transmission capacity necessary to provide such services) to the applicant. Upon receipt of such application, after public notice and notice to each affected State regulatory authority, each affected electric utility, and each affected Federal power marketing agency, and after affording an opportunity for an evidentiary hearing, the Commission may issue such order if it finds that such order meets the requirements of [section 824k of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section824k&num=0&edition=prelim), and would otherwise be in the public interest. No order may be issued under this subsection unless the applicant has made a request for transmission services to the transmitting utility that would be the subject of such order at least 60 days prior to its filing of an application for such order.
**(b) Reliability of electric service** No order may be issued under this section or [section 824i of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section824i&num=0&edition=prelim) if, after giving consideration to consistently applied regional or national reliability standards, guidelines, or criteria, the Commission finds that such order would unreasonably impair the continued reliability of electric systems affected by the order.
**(c) Replacement of electric energy** No order may be issued under subsection (a) or (b) which
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 824j
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Page 1416
TITLE 16—CONSERVATION
§ 824f
costs to be paid by other electric utility companies of
such registered holding company. For purposes of this
section, the terms ‘electric utility companies’ and ‘reg-
istered holding company’ shall have the same meanings
as provided in the Public Utility Holding Company Act
of 1935, as amended [15 U.S.C. 79 et seq.].’’
STUDY
Pub. L. 100–473, § 5, Oct. 6, 1988, 102 Stat. 2301, directed
that, no earlier than three years and no later than four
years after Oct. 6, 1988, Federal Energy Regulatory
Commission perform a study of effect of amendments
to this section, analyzing (1) impact, if any, of such
amendments on cost of capital paid by public utilities,
(2) any change in average time taken to resolve pro-
ceedings under this section, and (3) such other matters
as Commission may deem appropriate in public inter-
est, with study to be sent to Committee on Energy and
Natural Resources of Senate and Committee on Energy
and Commerce of House of Representatives.
§ 824f. Ordering furnishing of adequate service
Whenever the Commission, upon complaint of
a State commission, after notice to each State
commission and public utility affected and after
opportunity for hearing, shall find that any
interstate service of any public utility is inad-
equate or insufficient, the Commission shall de-
termine the proper, adequate, or sufficient serv-
ice to be furnished, and shall fix the same by its
order, rule, or regulation: Provided, That the
Commission shall have no authority to compel
the enlargement of generating facilities for such
purposes, nor to compel the public utility to sell
or exchange energy when to do so would impair
its ability to render adequate service to its cus-
tomers.
(June 10, 1920, ch. 285, pt. II, §