31 U.S.C. § 3905 — Payment provisions relating to construction contracts
Federal law — U.S. Code and appendices · legal_authorities
**(a)** In the event that a contractor, after making a certified payment request to an agency pursuant to [section 3903(b) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903/b&num=0&edition=prelim), discovers that a portion or all of such payment request constitutes a payment for performance by such contractor that fails to conform to the specifications, terms, and conditions of its contract (hereafter in this subsection referred to as the “unearned amount”), then the contractor shall—
(1) notify the agency of such performance deficiency; and
(2) be obligated to pay the Government an amount equal to interest on the unearned amount (computed in the manner provided in [section 3903(c) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903/c&num=0&edition=prelim)), from the date of the contractor’s receipt of such unearned amount until—
(A) the date the contractor notifies the agency that the performance deficiency has been corrected; or
(B) the date the contractor reduces the amount of any subsequent certified application for payment to such agency by an amount equal to the unearned amount.
**(b)** Each construction contract awarded by an agency shall include a clause that requires the prime contractor to include in each subcontract for property or services entered into by the prime contractor and a subcontractor (including a material supplier) for the purpose of performing such construction contract—
(1) a payment clause which obligates the prime contractor to pay the subcontractor for satisfactory performance under its subcontract within 7 days out of such amounts as are paid to the prime contractor by the agency under such contract; and
(2) an interest penalty clause which
Source: Supplied U.S. Code snapshot — release unconfirmed · 31 U.S.C. § 3905
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: b8f823b1e7bc2b23eecc238baf66432adb237d900177f2df792a0ced8a464c97. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_0581c78b562d73cb6a38c3e2
Source file: Laws/federal/codes/united-states-code/title-31/section-3905-payment-provisions-relating-to-construction-contracts--b50ca0e322.md
Pages: Not recorded – Not recorded
Passage SHA-256: bc106a04c8e1b2e43d11d4da9a9b68a9ef512f20d1c49c428161ead33ad6f117
Source location: Title 31, Chapter 39, § 3905; chapter-039-prompt-payment.md
Stored source content
**(a)** In the event that a contractor, after making a certified payment request to an agency pursuant to [section 3903(b) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903/b&num=0&edition=prelim), discovers that a portion or all of such payment request constitutes a payment for performance by such contractor that fails to conform to the specifications, terms, and conditions of its contract (hereafter in this subsection referred to as the “unearned amount”), then the contractor shall—
(1) notify the agency of such performance deficiency; and
(2) be obligated to pay the Government an amount equal to interest on the unearned amount (computed in the manner provided in [section 3903(c) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903/c&num=0&edition=prelim)), from the date of the contractor’s receipt of such unearned amount until—
(A) the date the contractor notifies the agency that the performance deficiency has been corrected; or
(B) the date the contractor reduces the amount of any subsequent certified application for payment to such agency by an amount equal to the unearned amount.
**(b)** Each construction contract awarded by an agency shall include a clause that requires the prime contractor to include in each subcontract for property or services entered into by the prime contractor and a subcontractor (including a material supplier) for the purpose of performing such construction contract—
(1) a payment clause which obligates the prime contractor to pay the subcontractor for satisfactory performance under its subcontract within 7 days out of such amounts as are paid to the prime contractor by the agency under such contract; and
(2) an interest penalty clause which obligates the prime contractor to pay to the subcontractor an interest penalty on amounts due in the case of each payment not made in accordance with the payment clause included in the subcontract pursuant to paragraph (1) of this subsection—
(A) for the period beginning on the day after the required payment date and ending on the date on which payment of the amount due is made; and
(B) computed at the rate specified by [section 3902(a) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3902/a&num=0&edition=prelim).
**(c)** The construction contract awarded by the agency shall further require the prime contractor to include in each of its subcontracts (for the purpose of performance of such construction contract) a provision requiring the subcontractor to include a payment clause and an interest penalty clause conforming to the standards of subsection (b) of this section in each of its subcontracts and to require each of its subcontractors to include such clauses in their subcontracts with each lower-tier subcontractor or supplier.
**(d)** The clauses required by subsections (b) and (c) of this section shall not be construed to impair the right of a prime contractor or a subcontractor at any tier to negotiate, and to include in their subcontract, provisions which—
(1) permit the prime contractor or a subcontractor to retain (without cause) a specified percentage of each progress payment otherwise due to a subcontractor for satisfactory performance under the subcontract, without incurring any obligation to pay a late payment interest penalty, in accordance with terms and conditions agreed to by the parties to the subcontract, giving such recognition as the parties deem appropriate to the ability of a subcontractor to furnish a performance bond and a payment bond;
(2) permit the contractor or subcontractor to make a determination that part or all of the subcontractor’s request for payment may be withheld in accordance with the subcontract agreement; and
(3) permit such withholding without incurring any obligation to pay a late payment penalty if—
(A) a notice conforming to the standards of subsection (g) of this section has been previously furnished to the subcontractor; and
(B) a copy of any notice issued by a prime contractor pursuant to subparagraph (A) of this paragraph has been furnished to the Government.
**(e)** If a prime contractor, after making application to an agency for payment under a contract but before making a payment to a subcontractor for the subcontractor’s performance covered by such application, discovers that all or a portion of the payment otherwise due such subcontractor is subject to withholding from the subcontractor in accordance with the subcontract agreement, then the prime contractor shall—
(1) furnish to the subcontractor a notice conforming to the standards of subsection (g) of this section as soon as practicable upon ascertaining the cause giving rise to a withholding, but prior to the due date for subcontractor payment;
(2) furnish to the Government, as soon as practicable, a copy of the notice furnished to the subcontractor pursuant to paragraph (1) of this subsection;
(3) reduce the subcontractor’s progress payment by an amount not to exceed the amount specified in the notice of withholding furnished under paragraph (1) of this subsection;
(4) pay the subcontractor as soon as practicable after the correction of the identified subcontract performance deficiency, and—
(A) make such payment within—
(i) 7 days after correction of the identified subcontract performance deficiency (unless the funds therefor must be recovered from the Government because of a reduction under paragraph (5)(A)); or
(ii) 7 days after the contractor recovers such funds from the Government; or
(B) incur an obligation to pay a late payment interest penalty computed at the rate specified by [section 3902(a) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3902/a&num=0&edition=prelim);
(5) notify the Government, upon—
(A) reduction of the amount of any subsequent certified application for payment; or
(B) payment to the subcontractor of any withheld amounts of a progress payment, specifying—
(i) the amounts of the progress payments withheld under paragraph (1) of this subsection; and
(ii) the dates that such withholding began and ended; and
(6) be obligated to pay to the Government an amount equal to interest on the withheld payments (computed in the manner provided in [section 3903(c) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903/c&num=0&edition=prelim)), from the 8th day after receipt of the withheld amounts from the Government until—
(A) the day the identified subcontractor performance deficiency is corrected; or
(B) the date that any subsequent payment is reduced under paragraph (5)(A).
**(f)**
(1) If a prime contractor, after making payment to a first-tier subcontractor, receives from a supplier or subcontractor of the first-tier subcontractor (hereafter referred to as a “second-tier subcontractor”) a written notice in accordance with [section 3133(b) of title 40](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section3133/b&num=0&edition=prelim), asserting a deficiency in such first-tier subcontractor’s performance under the contract for which the prime contractor may be ultimately liable, and the prime contractor determines that all or a portion of future payments otherwise due such first-tier subcontractor is subject to withholding in accordance with the subcontract agreement, then the prime contractor may, without incurring an obligation to pay an interest penalty under subsection (e)(6) of this section—
(A) furnish to the first-tier subcontractor a notice conforming to the standards of subsection (g) of this section as soon as practicable upon making such determination; and
(B) withhold from the first-tier subcontractor’s next available progress payment or payments an amount not to exceed the amount specified in the notice of withholding furnished under subparagraph (A) of this paragraph.
(2) As soon as practicable, but not later than 7 days after receipt of satisfactory written notification that the identified subcontract performance deficiency has been corrected, the prime contractor shall pay the amount withheld under paragraph (1)(B) of this subsection to such first-tier subcontractor, or shall incur an obligation to pay a late payment interest penalty to such first-tier subcontractor computed at the rate specified by [section 3902(a) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3902/a&num=0&edition=prelim).
**(g)** A written notice of any withholding shall be issued to a subcontractor (with a copy to the Government of any such notice issued by a prime contractor), specifying—
(1) the amount to be withheld;
(2) the specific causes for the withholding under the terms of the subcontract; and
(3) the remedial actions to be taken by the subcontractor in order to receive payment of the amounts withheld.
**(h)** A prime contractor may not request payment from the agency of any amount withheld or retained in accordance with subsection (d) of this section until such time as the prime contractor has determined and certified to the agency that the subcontractor is entitled to the payment of such amount.
**(i)** A dispute between a contractor and subcontractor relating to the amount or entitlement of a subcontractor to a payment or a late payment interest penalty under a clause included in the subcontract pursuant to subsection (b) or (c) of this section does not constitute a dispute to which the United States is a party. The United States may not be interpleaded in any judicial or administrative proceeding involving such a dispute.
**(j)** Except as provided in subsection (i) of this section, this section shall not limit or impair any contractual, administrative, or judicial remedies otherwise available to a contractor or a subcontractor in the event of a dispute involving late payment or nonpayment by a prime contractor or deficient subcontract performance or nonperformance by a subcontractor.
**(k)** A contractor’s obligation to pay an interest penalty to a subcontractor pursuant to the clauses included in a subcontract under subsection (b) or (c) of this section may not be construed to be an obligation of the United States for such interest penalty. A contract modification may not be made for the purpose of providing reimbursement of such interest penalty. A cost reimbursement claim may not include any amount for reimbursement of such interest penalty.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a)** Under regulations prescribed under [section 3903 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903&num=0&edition=prelim), the head of an agency acquiring property or service from a business concern, who does not pay the concern for each complete delivered item of property or service by the required payment date, shall pay an interest penalty to the concern on the amount of the payment due. The interest shall be computed at the rate of interest established by the Secretary of the Treasury, and published in the Federal Register, for interest payments under section 7109(a)(1) and (b) of title 41, which is in effect at the time the agency accrues the obligation to pay a late payment interest penalty.
**(b)** The interest penalty shall be paid for the period beginning on the day after the required payment date and ending on the date on which payment is made.
**(c)**
(1) A business concern shall be entitled to an interest penalty of $1.00 or more which is owed such business concern under this section, and such penalty shall be paid without regard to whether the business concern has requested payment of such penalty.
(2) Each payment subject to this chapter for which a late payment interest penalty is required to be paid shall be accompanied by a notice stating the amount of the interest penalty included in such payment and the rate by which, and period for which, such penalty was computed.
(3) If a business concern—
(A) is owed an interest penalty by an agency;
(B) is not paid the interest penalty in a payment made to the business concern by the agency on or after the date on which the interest penalty becomes due;
(C) is not paid the interest penalty by the agency within 10 days after the date on which such
Source: Supplied U.S. Code snapshot — release unconfirmed · 31 U.S.C. § 3902
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
### Statutory Notes
Section, added Pub. L. 97–452, § 1(18)(A), Jan. 12, 1983, 96 Stat. 2476, § 3905; renumbered § 3906 and amended Pub. L. 100–496, §§ 9(a)(1), 10, Oct. 17, 1988, 102 Stat. 2460, 2463, required submission of reports to Director of the Office of Management and Budget by 60th day after end of fiscal year by head of each agency concerning agency’s payment practices during that fiscal year.
A prior section 3906 was renumbered [section 3907 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3907&num=0&edition=prelim).
Source: Supplied U.S. Code snapshot — release unconfirmed · 31 U.S.C. § 3906
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a)** In this chapter—
(1) “agency” has the same meaning given that term in [section 551(1) of title 5](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section551/1&num=0&edition=prelim) and includes an entity being operated, and the head of the agency identifies the entity as being operated, only as an instrumentality of the agency to carry out a program of the agency.
(2) “business concern” means—
(A) a person carrying on a trade or business; and
(B) a nonprofit entity operating as a contractor.
(3) “proper invoice” is an invoice containing or accompanied by substantiating documentation the Director of the Office of Management and Budget may require by regulation and the head of the appropriate agency may require by regulation or contract.
(4) for the purposes of determining a payment due date and the date upon which any late payment interest penalty shall begin to accrue, the head of the agency is deemed to receive an invoice—
(A) on the later of—
(i) the date on which the place or person designated by the agency to first receive such invoice actually receives a proper invoice; or
(ii) on the 7th day after the date on which, in accordance with the terms and conditions of the contract, the property is actually delivered or performance of the services is actually completed, as the case may be, unless—
(I) the agency has actually accepted such property or services before such 7th day; or
(II) the contract (except in the case of a contract for the procurement of a brand-name commercial product for authorized resale) specifies a longer acceptance period, as determined by the contracting officer to be required to afford the agency a practicable opportunity to inspect and test the property furnished or evaluate the
Source: Supplied U.S. Code snapshot — release unconfirmed · 31 U.S.C. § 3901
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a)** The Director of the Office of Management and Budget shall prescribe regulations to carry out [section 3902 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3902&num=0&edition=prelim). The regulations shall—
(1) provide that the required payment date is—
(A) the date payment is due under the contract for the item of property or service provided; or
(B) except as provided in paragraphs (10) and (11), 30 days after a proper invoice for the amount due is received if a specific payment date is not established by contract;
(2) for the acquisition of meat or a meat food product (as defined in section 2(a)(3) of the Packers and Stockyards Act, 1921 ([7 U.S.C. 182(3)](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title7-section182/3&num=0&edition=prelim))), including any edible fresh or frozen poultry meat, any perishable poultry meat food product, fresh eggs, and any perishable egg product, or of fresh or frozen fish (as defined in section 204(3) of the Fish and Seafood Promotion Act of 1986 ([16 U.S.C. 4003(3)](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section4003/3&num=0&edition=prelim)), provide a required payment date of not later than 7 days after the meat, meat food product, or fish is delivered; and
(3) for the acquisition of a perishable agricultural commodity (as defined in section 1(4) 11 See References in Text note below. of the Perishable Agricultural Commodities Act, 1930 ([7 U.S.C. 499a(4)](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title7-section499a/4&num=0&edition=prelim))), provide a required payment date consistent with that Act;
(4) for the acquisition of dairy products (as defined in section 111(e) of the Dairy Production Stabilization Act
Source: Supplied U.S. Code snapshot — release unconfirmed · 31 U.S.C. § 3903
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Page 365
TITLE 31—MONEY AND FINANCE
§ 3905
head of the agency shall pay an interest penalty
on an amount remaining unpaid in violation of
this section. The penalty accrues as provided
under sections 3902 and 3903 of this title, except
that the required payment date for the unpaid
amount is the last day specified in the contract
that the discounted amount may be paid.
(Added Pub. L. 97–452, § 1(18)(A), Jan. 12, 1983, 96
Stat. 2476; amended Pub. L. 100–496, § 8, Oct. 17,
1988, 102 Stat. 2460.)
HISTORICAL AND REVISION NOTES
Revised
Section
Source (U.S. Code)
Source (Statutes at Large)
3904 .........
31 App.:1802.
May 21, 1982, Pub. L. 97–177,
§ 3, 96 Stat. 86.
The word ‘‘otherwise’’ is omitted as surplus. The
words ‘‘may pay the discounted amount’’ are sub-
stituted for ‘‘may make payment in an amount equal
to the discounted price’’ to eliminate unnecessary
words. The words ‘‘on such unpaid amount’’ and ‘‘the
regulations prescribed pursuant to’’ are omitted as sur-
plus. The words ‘‘specified in the contract that the dis-
counted amount may be paid’’ are substituted for ‘‘of
the specified period of time described in subsection (a)’’
for clarity.
Editorial Notes
AMENDMENTS
1988—Pub. L. 100–496 inserted after first sentence
‘‘For the purpose of the preceding sentence, the speci-
fied time shall be determined from the date of the in-
voice.’’
Statutory Notes and Related Subsidiaries
EFFECTIVE DATE OF 1988 AMENDMENT
Amendment by Pub. L. 100–496 applicable to pay-
ments under contracts awarded, contracts renewed, and
contract options exercised during or after the first fis-
cal quarter which begins more than 90 days after Oct.
17, 1988, see section 14(a) of Pub. L. 100–496, set out as
a note under section 3902 of this title.
§ 3905. Payment provi
Source: Supplied 2024 U.S. Code historical extraction · 31 U.S.C. § 3905
Stored review status: historical_2024_not_currentness_verified. Same stored citation; legal effect and authority still require review.