19-4-1413. Projects constructed with private funds.
Arkansas Code — all titles (historical 2020) · legal_authorities
19-4-1413. Projects constructed with private funds.
(a) In the event funds from private sources are provided to a public institution of higher education for projects which exceed five million dollars ($5,000,000) regulated in this subchapter sufficient to finance at least eighty percent (80%) of the estimated cost of the proposed project, excluding the cost of land, the provisions of this subchapter and of all other provisions of the Arkansas Code governing construction of public facilities, including, but not limited to, the provisions of §§ 22-9-101 and 22-9-103 and §§ 22-9-201 — 22-9-212, shall not be applicable to such projects, subject to the following:
(1)(A)(i) The governing board of the public institution of higher education shall have adopted a resolution and procedure setting forth the method by which the architect, engineer, construction manager, contractor, and major subcontractors are to be selected for the project.
(ii) The procedure shall include by appropriate public notice and solicitation the opportunity for qualified, licensed professionals to submit proposals and shall assure the design and completion of the project in an expeditious manner while adhering to high standards of design and construction quality.
(iii) Such procedures shall require a payment and performance bond in an amount determined by the governing board and shall provide for the manner in which the construction shall be managed and supervised.
(B) In selecting a contractor and other professionals for the projects, the governing board shall consider the experience of the person or firm in constructing similar projects, the record of the person or firm in timely completion of such projects, and other similar matters to assure that the person or firm will complete the project
Source: Arkansas Code — historical release 78 (November 6, 2020) · 19-4-1413
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. A text match is a research starting point; applicability is not established.
Issuing source page ↗
Authority boundary: historical statutory source snapshot not current law.
Open the recorded source website ↗
Record provenance
Stable record: arkansas_code:legal_authorities:19-4-1413
Source file: gov.ar.code.title.19.odt
Pages: Not recorded – Not recorded
Passage SHA-256: 1278cde7c56b8d708a26ef628321a8f67710acdb35895a505384527a913a765f
Source location: content.xml paragraph 3713
Stored source content
19-4-1413. Projects constructed with private funds.
(a) In the event funds from private sources are provided to a public institution of higher education for projects which exceed five million dollars ($5,000,000) regulated in this subchapter sufficient to finance at least eighty percent (80%) of the estimated cost of the proposed project, excluding the cost of land, the provisions of this subchapter and of all other provisions of the Arkansas Code governing construction of public facilities, including, but not limited to, the provisions of §§ 22-9-101 and 22-9-103 and §§ 22-9-201 — 22-9-212, shall not be applicable to such projects, subject to the following:
(1)(A)(i) The governing board of the public institution of higher education shall have adopted a resolution and procedure setting forth the method by which the architect, engineer, construction manager, contractor, and major subcontractors are to be selected for the project.
(ii) The procedure shall include by appropriate public notice and solicitation the opportunity for qualified, licensed professionals to submit proposals and shall assure the design and completion of the project in an expeditious manner while adhering to high standards of design and construction quality.
(iii) Such procedures shall require a payment and performance bond in an amount determined by the governing board and shall provide for the manner in which the construction shall be managed and supervised.
(B) In selecting a contractor and other professionals for the projects, the governing board shall consider the experience of the person or firm in constructing similar projects, the record of the person or firm in timely completion of such projects, and other similar matters to assure that the person or firm will complete the project within the time and to the specifications set by the governing board;
(2)(A) Before the public institution of higher education shall enter into a contract with an architect, engineer, construction manager, or contractor for the design, construction, or financing of any project financed from private funds as provided in this section, it shall submit to the Chief Fiscal Officer of the State and the Legislative Council, in writing, a summary statement setting forth a general description of the proposed project, its estimated overall cost, and the method proposed to finance the cost, including a description of the sources and amount of private funds.
(B) The Chief Fiscal Officer of the State may forward a copy of this statement to the Building Authority Division, the Secretary of the Department of Transformation and Shared Services, and the Governor for information; and
(3) To enable a public institution of higher education to qualify under this subsection, the private funds shall be paid to the public institution of higher education or to a fund or foundation for the benefit of the public institution of higher education, and such funds may be represented in whole or in part by a written pledge or commitment from a donor, provided that the public institution of higher education shall assure itself of the financial stability of such donor to fulfill the pledge or commitment.
(b) Notwithstanding anything in this section to the contrary, the provisions of § 19-4-1405(f), § 22-9-301 et seq. [repealed], §§ 22-9-401 — 22-9-404, § 22-9-501 et seq., § 22-9-601 et seq., and § 22-9-701 et seq. shall remain in full force and effect and shall not be affected by this section.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Arkansas Code — all titles (historical 2020) · legal_authorities
22-9-101. Observation by registered professionals required.
(a) The state or a township, county, municipality, village, or other political subdivision of the state shall not engage in the capital improvement of public works involving engineering or architecture for which the plans, specifications, and estimates have not been made by and the capital improvement executed under the observation of a professional engineer as defined in § 17-30-101 or architect as defined in § 17-15-102, in their respective areas of expertise.
(b) Nothing in this section shall be held to apply to any public works wherein the contemplated capital improvement expenditure:
(1) For an engineering project does not exceed twenty-five thousand dollars ($25,000); or
(2) For an architectural project does not exceed one hundred thousand dollars ($100,000).
(c) This section does not apply to:
(1) A school district, county, municipality, or township project that is planned and executed according to plans and specifications furnished by authorized state agencies; or
(2)(A) The design or construction of an unpaved trail project as defined under § 22-2-102.
(B) The State Parks, Recreation, and Travel Commission shall ensure that an unpaved trail project created under this subdivision (c)(2) meets the standards for observation by registered professionals as established by the Building Authority Division.
Source: Arkansas Code — historical release 78 (November 6, 2020) · 22-9-101
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. The source passage cites 22-9-101. This identifies an authority to review, not proof of applicability.
Arkansas Code — all titles (historical 2020) · legal_authorities
22-9-103. Authorization for state agency to commit cash funds for construction — Penalty.
(a)(1) It shall be unlawful for any agency, department, or institution supported by state-appropriated funds or cash funds to expend any cash funds of the agency for the construction of a building or to incur any obligation committing or pledging the cash funds of the agency for the construction of a building unless the agency, department, or institution has previously obtained specific authorization by legislative enactment for the construction of the building to be paid, wholly or in part, from cash funds of the agency.
(2) If the agency does not have specific legislative authority to construct a building from cash funds, the agency, department, or institution shall first obtain specific legislative authorization for the construction of the building prior to the expending of any cash funds of the agency, or prior to entering into any contract or agreement with respect to constructing any building to be paid from cash funds of the agency.
(b) In the interim between legislative sessions, authorization for the construction of buildings and for the expending of cash funds of the agency therefor may be given by the Governor, in writing.
(c) Nothing in this section shall apply to public school districts.
(d) Any board, commission, or authorized head of any agency, department, or institution which shall expend any cash funds of the agency in violation of the provisions of this section shall be guilty of malfeasance in office and shall be removed therefrom.
Source: Arkansas Code — historical release 78 (November 6, 2020) · 22-9-103
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. The source passage cites 22-9-103. This identifies an authority to review, not proof of applicability.
Arkansas Code — all titles (historical 2020) · legal_authorities
22-9-201. Applicability of §§ 22-9-202 — 22-9-204.
(a) The provisions of §§ 22-9-202 — 22-9-204 shall not apply to contracts awarded by the State Highway Commission for construction or maintenance of public highways, roads, or streets under the provisions of §§ 27-67-206 and 27-67-207.
(b) The provisions of § 22-9-204 shall not apply to projects designed to provide utility needs of the state or any agency thereof, a municipality, or a county. Those projects shall include, but shall not be limited to, pipeline installation, sanitation projects, light earth work and foundation work, local flood control, sanitary landfills, drainage projects, site clearing, water lines, streets, roads, alleys, sidewalks, water channelization, light construction sewage, water works, and improvements to street and highway construction.
(c)(1)(A) The notice and bid security provisions of §§ 19-4-1401, 19-4-1405, and 22-9-203 pertaining to the project amount and the time frames of the advertisement shall not apply to contracts for the performance of any work or the making of any capital improvements due to emergency contracting procedures.
(B) Nothing shall prohibit the contracting authority from requiring a bid security if the contracting authority determines to require a bid security.
(2)(A) The percentage requirements of § 22-9-203(e) shall not apply to contracts for the performance of any work or the making of any capital improvements due to emergency contracting procedures.
(B) If negotiations are unsuccessful and the contracting authority determines further negotiations with the lowest responsible bidder are not in the contracting authority's best interests, nothing shall prohibit the contracting authority from terminating negotiations and negotiating the award of the contrac
Source: Arkansas Code — historical release 78 (November 6, 2020) · 22-9-201
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. The source passage cites 22-9-201. This identifies an authority to review, not proof of applicability.
Arkansas Code — all titles (historical 2020) · legal_authorities
22-9-212. Public improvements generally — Trench or excavation safety systems.
(a) Whenever any agency of this state or of any county, municipality, or school district, or other local taxing unit or improvement district, enters into a contract covered by the provisions of §§ 22-9-202 — 22-9-204 for the making of repairs or alterations or the erection of buildings or for the making of any other improvements, or for the construction or improvement of highways, roads, streets, sidewalks, curbs, gutters, drainage or sewer projects, or for any other construction project in which the public work or public improvement construction project involves any trench or excavation which equals or exceeds five feet (5') in depth, the agency, county, municipality, school district, local taxing unit, or improvement district shall require:
(1) That the current edition of Occupational Safety and Health Administration Standard for Excavation and Trenches Safety System, 29 C.F.R. Part 1926, Subpart P, be specifically incorporated into the specifications for the project; and
(2) That the contract bid form include a separate pay item for trench or excavation safety systems to be included in the base bid.
(b) In the event a contractor fails to complete a separate pay item in accordance with the applicable provisions of subsection (a) of this section, the agency, county, municipality, school district, local taxing unit, or improvement district shall declare that the bid fails to comply fully with the provisions of the specifications and bid documents and will be considered invalid as a nonresponsive bid. The owners of the above-stated project shall notify the Safety Division of the Division of Labor of the award of a contract covered by this section.
Source: Arkansas Code — historical release 78 (November 6, 2020) · 22-9-212
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. The source passage cites 22-9-212. This identifies an authority to review, not proof of applicability.