42 U.S.C. § 7651d — Phase II sulfur dioxide requirements
Federal law — U.S. Code and appendices · legal_authorities
Page 7425
TITLE 42—THE PUBLIC HEALTH AND WELFARE
§ 7651d
at the election of the owner or operator of
such unit, the unit’s baseline may be cal-
culated (i) as provided under section 7651a(d) 1
of this title, or (ii) by utilizing the unit’s aver-
age annual fuel consumption at a 60 percent
capacity factor. Such election shall be made
no later than March 1, 1991.
(2) Allowance allocation
Whenever a unit referred to in paragraph (1)
elects to calculate its baseline as provided in
clause (ii) of paragraph (1), the Administrator
shall allocate allowances for the unit pursuant
to section 7651b(a)(1) of this title, this section,
and section 7651d of this title (as basic Phase
II allowance allocations) in an amount equal
to the baseline selected multiplied by the
lower of the average annual emission rate for
such unit in 1989, or 1.0 lbs./mmBtu. Such al-
lowance allocation shall be in lieu of any allo-
cation of allowances under this section and
section 7651d of this title.
(July 14, 1955, ch. 360, title IV, § 404, as added
Pub. L. 101–549, title IV, § 401, Nov. 15, 1990, 104
Stat. 2592.)
§ 7651d. Phase II sulfur dioxide requirements
(a) Applicability
(1) After January 1, 2000, each existing utility
unit as provided below is subject to the limita-
tions or requirements of this section. Each util-
ity unit subject to an annual sulfur dioxide ton-
nage emission limitation under this section is
an affected unit under this subchapter. Each
source that includes one or more affected units
is an affected source. In the case of an existing
unit that was not in operation during calendar
year 1985, the emission rate for a calendar year
after 1985, as determined by the Administrator,
shall be used in lieu of the 1985 rate. The owner
or operator of any unit
Source: Supplied 2024 U.S. Code historical extraction · 42 U.S.C. § 7651d
Stored review status: historical_2024_not_currentness_verified. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: a7d3a07f986df87044e8d77f220dffc3e903e1b45424f5fb9dec38b4c4882c0d. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:usc2024-62a6b0d9bccc38ef359c7f18
Source file: Laws/federal/codes/united-states-code-2024/title-42/section-7651d-phase-ii-sulfur-dioxide-requirements--5cee3f0498.md
Pages: Not recorded – Not recorded
Passage SHA-256: 61e8f9a208169e6254fa2edcbff5053d7824da74981264ac866401e5e0e81866
Source location: USCODE-2024-title42-chap85-subchapIV-A-sec7651d.pdf
Stored source content
Page 7425
TITLE 42—THE PUBLIC HEALTH AND WELFARE
§ 7651d
at the election of the owner or operator of
such unit, the unit’s baseline may be cal-
culated (i) as provided under section 7651a(d) 1
of this title, or (ii) by utilizing the unit’s aver-
age annual fuel consumption at a 60 percent
capacity factor. Such election shall be made
no later than March 1, 1991.
(2) Allowance allocation
Whenever a unit referred to in paragraph (1)
elects to calculate its baseline as provided in
clause (ii) of paragraph (1), the Administrator
shall allocate allowances for the unit pursuant
to section 7651b(a)(1) of this title, this section,
and section 7651d of this title (as basic Phase
II allowance allocations) in an amount equal
to the baseline selected multiplied by the
lower of the average annual emission rate for
such unit in 1989, or 1.0 lbs./mmBtu. Such al-
lowance allocation shall be in lieu of any allo-
cation of allowances under this section and
section 7651d of this title.
(July 14, 1955, ch. 360, title IV, § 404, as added
Pub. L. 101–549, title IV, § 401, Nov. 15, 1990, 104
Stat. 2592.)
§ 7651d. Phase II sulfur dioxide requirements
(a) Applicability
(1) After January 1, 2000, each existing utility
unit as provided below is subject to the limita-
tions or requirements of this section. Each util-
ity unit subject to an annual sulfur dioxide ton-
nage emission limitation under this section is
an affected unit under this subchapter. Each
source that includes one or more affected units
is an affected source. In the case of an existing
unit that was not in operation during calendar
year 1985, the emission rate for a calendar year
after 1985, as determined by the Administrator,
shall be used in lieu of the 1985 rate. The owner
or operator of any unit operated in violation of
this section shall be fully liable under this chap-
ter for fulfilling the obligations specified in sec-
tion 7651j of this title.
(2) In addition to basic Phase II allowance al-
locations, in each year beginning in calendar
year 2000 and ending in calendar year 2009, inclu-
sive, the Administrator shall allocate up to
530,000 Phase II bonus allowances pursuant to
subsections (b)(2), (c)(4), (d)(3)(A) and (B), and
(h)(2) of this section and section 7651e of this
title. Not later than June 1, 1998, the Adminis-
trator shall calculate, for each unit granted an
extension pursuant to section 7651h of this title
the difference between (A) the number of allow-
ances allocated for the unit in calendar year
2000, and (B) the product of the unit’s baseline
multiplied by 1.20 lbs/mmBtu, divided by 2000,
and sum the computations. In each year, begin-
ning in calendar year 2000 and ending in cal-
endar year 2009, inclusive, the Administrator
shall deduct from each unit’s basic Phase II al-
lowance allocation its pro rata share of 10 per-
cent of the sum calculated pursuant to the pre-
ceding sentence.
(3) In addition to basic Phase II allowance al-
locations and Phase II bonus allowance alloca-
tions, beginning January 1, 2000, the Adminis-
trator shall allocate for each unit listed on
Table A in section 7651c of this title (other than
units at Kyger Creek, Clifty Creek, and Joppa
Steam) and located in the States of Illinois, In-
diana, Ohio, Georgia, Alabama, Missouri, Penn-
sylvania, West Virginia, Kentucky, or Tennessee
allowances in an amount equal to 50,000 multi-
plied by the unit’s pro rata share of the total
number of basic allowances allocated for all
units listed on Table A (other than units at
Kyger Creek, Clifty Creek, and Joppa Steam).
Allowances allocated pursuant to this paragraph
shall not be subject to the 8,900,000 ton limita-
tion in section 7651b(a) of this title.
(b) Units equal to, or above, 75 MWe and 1.20 lbs/
mmBtu
(1) Except as otherwise provided in paragraph
(3), after January 1, 2000, it shall be unlawful for
any existing utility unit that serves a generator
with nameplate capacity equal to, or greater,
than 75 MWe and an actual 1985 emission rate
equal to or greater than 1.20 lbs/mmBtu to ex-
ceed an annual sulfur dioxide tonnage emission
limitation equal to the product of the unit’s
baseline multiplied by an emission rate equal to
1.20 lbs/mmBtu, divided by 2,000, unless the
owner or operator of such unit holds allowances
to emit not less than the unit’s total annual
emissions.
(2) In addition to allowances allocated pursu-
ant to paragraph (1) and section 7651b(a)(1) of
this title as basic Phase II allowance alloca-
tions, beginning January 1, 2000, and for each
calendar year thereafter until and including
2009, the Administrator shall allocate annually
for each unit subject to the emissions limitation
requirements of paragraph (1) with an actual
1985 emissions rate greater than 1.20 lbs/mmBtu
and less than 2.50 lbs/mmBtu and a baseline ca-
pacity factor of less than 60 percent, allowances
from the reserve created pursuant to subsection
(a)(2) in an amount equal to 1.20 lbs/mmBtu mul-
tiplied by 50 percent of the difference, on a Btu
basis, between the unit’s baseline and the unit’s
fuel consumption at a 60 percent capacity fac-
tor.
(3) After January 1, 2000, it shall be unlawful
for any existing utility unit with an actual 1985
emissions rate equal to or greater than 1.20 lbs/
mmBtu whose annual average fuel consumption
during 1985, 1986, and 1987 on a Btu basis exceed-
ed 90 percent in the form of lignite coal which is
located in a State in which, as of July 1, 1989, no
county or portion of a county was designated
nonattainment under section 7407 of this title
for any pollutant subject to the requirements of
section 7409 of this title to exceed an annual sul-
fur dioxide tonnage limitation equal to the prod-
uct of the unit’s baseline multiplied by the less-
er of the unit’s actual 1985 emissions rate or its
allowable 1985 emissions rate, divided by 2,000,
unless the owner or operator of such unit holds
allowances to emit not less than the unit’s total
annual emissions.
(4) After January 1, 2000, the Administrator
shall allocate annually for each unit, subject to
the emissions limitation requirements of para-
graph (1), which is located in a State with an in-
stalled electrical generating capacity of more
than 30,000,000 kw in 1988 and for which was
issued a prohibition order or a proposed prohibi-
tion order (from burning oil), which unit subse-
Page 7426
TITLE 42—THE PUBLIC HEALTH AND WELFARE
§ 7651d
1 So in original. Probably should be ‘‘unit’s’’.
quently converted to coal between January 1,
1980 and December 31, 1985, allowances equal to
the difference between (A) the product of the
unit’s annual fuel consumption, on a Btu basis,
at a 65 percent capacity factor multiplied by the
lesser of its actual or allowable emissions rate
during the first full calendar year after conver-
sion, divided by 2,000, and (B) the number of al-
lowances allocated for the unit pursuant to
paragraph (1): Provided, That the number of al-
lowances allocated pursuant to this paragraph
shall not exceed an annual total of five thou-
sand. If necessary to meeting the restriction im-
posed in the preceding sentence the Adminis-
trator shall reduce, pro rata, the annual allow-
ances allocated for each unit under this para-
graph.
(c) Coal or oil-fired units below 75 MWe and
above 1.20 lbs/mmBtu
(1) Except as otherwise provided in paragraph
(3), after January 1, 2000, it shall be unlawful for
a coal or oil-fired existing utility unit that
serves a generator with nameplate capacity of
less than 75 MWe and an actual 1985 emission
rate equal to, or greater than, 1.20 lbs/mmBtu
and which is a unit owned by a utility operating
company whose aggregate nameplate fossil fuel
steam-electric capacity is, as of December 31,
1989, equal to, or greater than, 250 MWe to ex-
ceed an annual sulfur dioxide emissions limita-
tion equal to the product of the unit’s baseline
multiplied by an emission rate equal to 1.20 lbs/
mmBtu, divided by 2,000, unless the owner or op-
erator of such unit holds allowances to emit not
less than the unit’s total annual emissions.
(2) After January 1, 2000, it shall be unlawful
for a coal or oil-fired existing utility unit that
serves a generator with nameplate capacity of
less than 75 MWe and an actual 1985 emission
rate equal to, or greater than, 1.20 lbs/mmBtu
(excluding units subject to section 7411 of this
title or to a federally enforceable emissions lim-
itation for sulfur dioxide equivalent to an an-
nual rate of less than 1.20 lbs/mmBtu) and which
is a unit owned by a utility operating company
whose aggregate nameplate fossil fuel steam-
electric capacity is, as of December 31, 1989, less
than 250 MWe, to exceed an annual sulfur diox-
ide tonnage emissions limitation equal to the
product of the unit’s baseline multiplied by the
lesser of its actual 1985 emissions rate or its al-
lowable 1985 emissions rate, divided by 2,000, un-
less the owner or operator of such unit holds al-
lowances to emit not less than the unit’s total
annual emissions.
(3) After January 1, 2000, it shall be unlawful
for any existing utility unit with a nameplate
capacity below 75 MWe and an actual 1985 emis-
sions rate equal to, or greater than, 1.20 lbs/
mmBtu which became operational on or before
December 31, 1965, which is owned by a utility
operating company with, as of December 31, 1989,
a total fossil fuel steam-electric generating ca-
pacity greater than 250 MWe, and less than 450
MWe which serves fewer than 78,000 electrical
customers as of November 15, 1990, to exceed an
annual sulfur dioxide emissions tonnage limita-
tion equal to the product of its baseline multi-
plied by the lesser of its actual or allowable 1985
emission rate, divided by 2,000, unless the owner
or operator holds allowances to emit not less
than the units 1 total annual emissions. After
January 1, 2010, it shall be unlawful for each
unit subject to the emissions limitation require-
ments of this paragraph to exceed an annual
emissions tonnage limitation equal to the prod-
uct of its baseline multiplied by an emissions
rate of 1.20 lbs/mmBtu, divided by 2,000, unless
the owner or operator holds allowances to emit
not less than the unit’s total annual emissions.
(4) In addition to allowances allocated pursu-
ant to paragraph (1) and section 7651b(a)(1) of
this title as basic Phase II allowance alloca-
tions, beginning January 1, 2000, and for each
calendar year thereafter until and including
2009, inclusive, the Administrator shall allocate
annually for each unit subject to the emissions
limitation requirements of paragraph (1) with an
actual 1985 emissions rate equal to, or greater
than, 1.20 lbs/mmBtu and less than 2.50 lbs/
mmBtu and a baseline capacity factor of less
than 60 percent, allowances from the reserve
created pursuant to subsection (a)(2) in an
amount equal to 1.20 lbs/mmBtu multiplied by 50
percent of the difference, on a Btu basis, be-
tween the unit’s baseline and the unit’s fuel con-
sumption at a 60 percent capacity factor.
(5) After January 1, 2000, it shall be unlawful
for any existing utility unit with a nameplate
capacity below 75 MWe and an actual 1985 emis-
sions rate equal to, or greater than, 1.20 lbs/
mmBtu which is part of an electric utility sys-
tem which, as of November 15, 1990, (A) has at
least 20 percent of its fossil-fuel capacity con-
trolled by flue gas desulfurization devices, (B)
has more than 10 percent of its fossil-fuel capac-
ity consisting of coal-fired units of less than 75
MWe, and (C) has large units (greater than 400
MWe) all of which have difficult or very difficult
FGD Retrofit Cost Factors (according to the
Emissions and the FGD Retrofit Feasibility at
the 200 Top Emitting Generating Stations, pre-
pared for the United States Environmental Pro-
tection Agency on January 10, 1986) to exceed an
annual sulfur dioxide emissions tonnage limita-
tion equal to the product of its baseline multi-
plied by an emissions rate of 2.5 lbs/mmBtu, di-
vided by 2,000, unless the owner or operator
holds allowances to emit not less than the unit’s
total annual emissions. After January 1, 2010, it
shall be unlawful for each unit subject to the
emissions limitation requirements of this para-
graph to exceed an annual emissions tonnage
limitation equal to the product of its baseline
multiplied by an emissions rate of 1.20 lbs/
mmBtu, divided by 2,000, unless the owner or op-
erator holds for use allowances to emit not less
than the unit’s total annual emissions.
(d) Coal-fired units below 1.20 lbs/mmBtu
(1) After January 1, 2000, it shall be unlawful
for any existing coal-fired utility unit the lesser
of whose actual or allowable 1985 sulfur dioxide
emissions rate is less than 0.60 lbs/mmBtu to ex-
ceed an annual sulfur dioxide tonnage emission
limitation equal to the product of the unit’s
baseline multiplied by (A) the lesser of 0.60 lbs/
mmBtu or the unit’s allowable 1985 emissions
rate, and (B) a numerical factor of 120 percent,
Page 7427
TITLE 42—THE PUBLIC HEALTH AND WELFARE
§ 7651d
2 So in original. This subsection does not contain a paragraph
(6).
3 So in original. The words ‘‘the Administrator shall,’’ probably
should not appear.
divided by 2,000, unless the owner or operator of
such unit holds allowances to emit not less than
the unit’s total annual emissions.
(2) After January 1, 2000, it shall be unlawful
for any existing coal-fired utility unit the lesser
of whose actual or allowable 1985 sulfur dioxide
emissions rate is equal to, or greater than, 0.60
lbs/mmBtu and less than 1.20 lbs/mmBtu to ex-
ceed an annual sulfur dioxide tonnage emissions
limitation equal to the product of the unit’s
baseline multiplied by (A) the lesser of its ac-
tual 1985 emissions rate or its allowable 1985
emissions rate, and (B) a numerical factor of 120
percent, divided by 2,000, unless the owner or op-
erator of such unit holds allowances to emit not
less than the unit’s total annual emissions.
(3)(A) In addition to allowances allocated pur-
suant to paragraph (1) and section 7651b(a)(1) of
this title as basic Phase II allowance alloca-
tions, at the election of the designated rep-
resentative of the operating company, beginning
January 1, 2000, and for each calendar year
thereafter until and including 2009, the Adminis-
trator shall allocate annually for each unit sub-
ject to the emissions limitation requirements of
paragraph (1) allowances from the reserve cre-
ated pursuant to subsection (a)(2) in an amount
equal to the amount by which (i) the product of
the lesser of 0.60 lbs/mmBtu or the unit’s allow-
able 1985 emissions rate multiplied by the unit’s
baseline adjusted to reflect operation at a 60
percent capacity factor, divided by 2,000, exceeds
(ii) the number of allowances allocated for the
unit pursuant to paragraph (1) and section
7651b(a)(1) of this title as basic Phase II allow-
ance allocations.
(B) In addition to allowances allocated pursu-
ant to paragraph (2) and section 7651b(a)(1) of
this title as basic Phase II allowance alloca-
tions, at the election of the designated rep-
resentative of the operating company, beginning
January 1, 2000, and for each calendar year
thereafter until and including 2009, the Adminis-
trator shall allocate annually for each unit sub-
ject to the emissions limitation requirements of
paragraph (2) allowances from the reserve cre-
ated pursuant to subsection (a)(2) in an amount
equal to the amount by which (i) the product of
the lesser of the unit’s actual 1985 emissions rate
or its allowable 1985 emissions rate multiplied
by the unit’s baseline adjusted to reflect oper-
ation at a 60 percent capacity factor, divided by
2,000, exceeds (ii) the number of allowances allo-
cated for the unit pursuant to paragraph (2) and
section 7651b(a)(1) of this title as basic Phase II
allowance allocations.
(C) An operating company with units subject
to the emissions limitation requirements of this
subsection may elect the allocation of allow-
ances as provided under subparagraphs (A) and
(B). Such election shall apply to the annual al-
lowance allocation for each and every unit in
the operating company subject to the emissions
limitation requirements of this subsection. The
Administrator shall allocate allowances pursu-
ant to subparagraphs (A) and (B) only in accord-
ance with this subparagraph.
(4) Notwithstanding any other provision of
this section, at the election of the owner or op-
erator, after January 1, 2000, the Administrator
shall allocate in lieu of allocation, pursuant to
paragraph (1), (2), (3), (5), or (6),2 allowances for
a unit subject to the emissions limitation re-
quirements of this subsection which commenced
commercial operation on or after January 1, 1981
and before December 31, 1985, which was subject
to, and in compliance with, section 7411 of this
title in an amount equal to the unit’s annual
fuel consumption, on a Btu basis, at a 65 percent
capacity factor multiplied by the unit’s allow-
able 1985 emissions rate, divided by 2,000.
(5) For the purposes of this section, in the case
of an oil- and gas-fired unit which has been
awarded a clean coal technology demonstration
grant as of January 1, 1991, by the United States
Department of Energy, beginning January 1,
2000, the Administrator shall allocate for the
unit allowances in an amount equal to the unit’s
baseline multiplied by 1.20 lbs/mmBtu, divided
by 2,000.
(e) Oil and gas-fired units equal to or greater
than 0.60 lbs/mmBtu and less than 1.20 lbs/
mmBtu
After January 1, 2000, it shall be unlawful for
any existing oil and gas-fired utility unit the
lesser of whose actual or allowable 1985 sulfur
dioxide emission rate is equal to, or greater
than, 0.60 lbs/mmBtu, but less than 1.20 lbs/
mmBtu to exceed an annual sulfur dioxide ton-
nage limitation equal to the product of the
unit’s baseline multiplied by (A) the lesser of
the unit’s allowable 1985 emissions rate or its
actual 1985 emissions rate and (B) a numerical
factor of 120 percent divided by 2,000, unless the
owner or operator of such unit holds allowances
to emit not less than the unit’s total annual
emissions.
(f) Oil and gas-fired units less than 0.60 lbs/
mmBtu
(1) After January 1, 2000, it shall be unlawful
for any oil and gas-fired existing utility unit the
lesser of whose actual or allowable 1985 emission
rate is less than 0.60 lbs/mmBtu and whose aver-
age annual fuel consumption during the period
1980 through 1989 on a Btu basis was 90 percent
or less in the form of natural gas to exceed an
annual sulfur dioxide tonnage emissions limita-
tion equal to the product of the unit’s baseline
multiplied by (A) the lesser of 0.60 lbs/mmBtu or
the unit’s allowable 1985 emissions, and (B) a nu-
merical factor of 120 percent, divided by 2,000,
unless the owner or operator of such unit holds
allowances to emit not less than the unit’s total
annual emissions.
(2) In addition to allowances allocated pursu-
ant to paragraph (1) as basic Phase II allowance
allocations and section 7651b(a)(1) of this title,
beginning January 1, 2000, the Administrator
shall,3 in the case of any unit operated by a util-
ity that furnishes electricity, electric energy,
steam, and natural gas within an area consisting
of a city and 1 contiguous county, and in the
case of any unit owned by a State authority, the
output of which unit is furnished within that
same area consisting of a city and 1 contiguous
county, the Administrator shall allocate for
Page 7428
TITLE 42—THE PUBLIC HEALTH AND WELFARE
§ 7651d
4 So in original. Probably should not be capitalized.
5 See References in Text note below.
6 So in original. Probably should be ‘‘seq.,’’.
7 So in original. No subpar. (B) has been enacted.
8 So in original. Probably should be preceded by a comma.
9 So in original. Probably means clause ‘‘(C)’’.
each unit in the utility its pro rata share of 7,000
allowances and for each unit in the State au-
thority its pro rata share of 2,000 allowances.
(g) Units that commence operation between 1986
and December 31, 1995
(1) After January 1, 2000, it shall be unlawful
for any utility unit that has commenced com-
mercial operation on or after January 1, 1986,
but not later than September 30, 1990 to exceed
an annual tonnage emission limitation equal to
the product of the unit’s annual fuel consump-
tion, on a Btu basis, at a 65 percent capacity fac-
tor multiplied by the unit’s allowable 1985 sulfur
dioxide emission rate (converted, if necessary,
to pounds per mmBtu), divided by 2,000 unless
the owner or operator of such unit holds allow-
ances to emit not less than the unit’s total an-
nual emissions.
(2) After January 1, 2000, the Administrator
shall allocate allowances pursuant to section
7651b of this title to each unit which is listed in
table B of this paragraph in an annual amount
equal to the amount specified in table B.
TABLE B
Unit
Allowances
Brandon Shores ...................................
8,907
Miller 4 ................................................
9,197
TNP One 2 ...........................................
4,000
Zimmer 1 .............................................
18,458
Spruce 1 ..............................................
7,647
Clover 1 ...............................................
2,796
Clover 2 ...............................................
2,796
Twin Oak 2 ..........................................
1,760
Twin Oak 1 ..........................................
9,158
Cross 1 .................................................
6,401
Malakoff 1 ...........................................
1,759
Notwithstanding any other paragraph of this
subsection, for units subject to this paragraph,
the Administrator shall not allocate allowances
pursuant to any other paragraph of this sub-
section, Provided 4 that the owner or operator of
a unit listed on Table B may elect an allocation
of allowances under another paragraph of this
subsection in lieu of an allocation under this
paragraph.
(3) Beginning January 1, 2000, the Adminis-
trator shall allocate to the owner or operator of
any utility unit that commences commercial op-
eration, or has commenced commercial oper-
ation, on or after October 1, 1990, but not later
than December 31, 1992 allowances in an amount
equal to the product of the unit’s annual fuel
consumption, on a Btu basis, at a 65 percent ca-
pacity factor multiplied by the lesser of 0.30 lbs/
mmBtu or the unit’s allowable sulfur dioxide
emission rate (converted, if necessary, to pounds
per mmBtu), divided by 2,000.
(4) Beginning January 1, 2000, the Adminis-
trator shall allocate to the owner or operator of
any utility unit that has commenced construc-
tion before December 31, 1990 and that com-
mences commercial operation between January
1, 1993 and December 31, 1995, allowances in an
amount equal to the product of the unit’s an-
nual fuel consumption, on a Btu basis, at a 65
percent capacity factor multiplied by the lesser
of 0.30 lbs/mmBtu or the unit’s allowable sulfur
dioxide emission rate (converted, if necessary,
to pounds per mmBtu), divided by 2,000.
(5) After January 1, 2000, it shall be unlawful
for any existing utility unit that has completed
conversion from predominantly gas fired exist-
ing operation to coal fired operation between
January 1, 1985 and December 31, 1987, for which
there has been allocated a proposed or final pro-
hibition order pursuant to section 301(b) 5 of the
Powerplant and Industrial Fuel Use Act of 1978
(42 U.S.C. 8301 et seq,6 repealed 1987) to exceed an
annual sulfur dioxide tonnage emissions limita-
tion equal to the product of the unit’s annual
fuel consumption, on a Btu basis, at a 65 percent
capacity factor multiplied by the lesser of 1.20
lbs/mmBtu or the unit’s allowable 1987 sulfur di-
oxide emissions rate, divided by 2,000, unless the
owner or operator of such unit has obtained al-
lowances equal to its actual emissions.
(6)(A) 7 Unless the Administrator has approved
a designation of such facility under section 7651i
of this title, the provisions of this subchapter
shall not apply to a ‘‘qualifying small power
production facility’’ or ‘‘qualifying cogeneration
facility’’
(within
the
meaning
of
section
796(17)(C) or 796(18)(B) of title 16) or to a ‘‘new
independent power production facility’’ as de-
fined in section 7651o of this title except 8 that
clause (iii) 9 of such definition in section 7651o of
this title shall not apply for purposes of this
paragraph if, as of November 15, 1990,
(i) an applicable power sales agreement has
been executed;
(ii) the facility is the subject of a State reg-
ulatory authority order requiring an electric
utility to enter into a power sales agreement
with, purchase capacity from, or (for purposes
of establishing terms and conditions of the
electric utility’s purchase of power) enter into
arbitration concerning, the facility;
(iii) an electric utility has issued a letter of
intent or similar instrument committing to
purchase power from the facility at a pre-
viously offered or lower price and a power
sales agreement is executed within a reason-
able period of time; or
(iv) the facility has been selected as a win-
ning bidder in a utility competitive bid solici-
tation.
(h) Oil and gas-fired units less than 10 percent
oil consumed
(1) After January 1, 2000, it shall be unlawful
for any oil- and gas-fired utility unit whose av-
erage annual fuel consumption during the period
1980 through 1989 on a Btu basis exceeded 90 per-
cent in the form of natural gas to exceed an an-
nual sulfur dioxide tonnage limitation equal to
the product of the unit’s baseline multiplied by
the unit’s actual 1985 emissions rate divided by
2,000 unless the owner or operator of such unit
holds allowances to emit not less than the unit’s
total annual emissions.
(2) In addition to allowances allocated pursu-
ant to paragraph (1) and section 7651b(a)(1) of
this title as basic Phase II allowance alloca-
tions, beginning January 1, 2000, and for each
calendar year thereafter until and including
Page 7429
TITLE 42—THE PUBLIC HEALTH AND WELFARE
§ 7651e
2009, the Administrator shall allocate annually
for each unit subject to the emissions limitation
requirements of paragraph (1) allowances from
the reserve created pursuant to subsection (a)(2)
of this section in an amount equal to the unit’s
baseline multiplied by 0.050 lbs/mmBtu, divided
by 2,000.
(3) In addition to allowances allocated pursu-
ant to paragraph (1) and section 7651b(a)(1) of
this title, beginning January 1, 2010, the Admin-
istrator shall allocate annually for each unit
subject to the emissions limitation require-
ments of paragraph (1) allowances in an amount
equal to the unit’s baseline multiplied by 0.050
lbs/mmBtu, divided by 2,000.
(i) Units in high growth States
(1) In addition to allowances allocated pursu-
ant to this section and section 7651b(a)(1) of this
title as basic Phase II allowance allocations, be-
ginning January 1, 2000, the Administrator shall
allocate annually allowances for each unit, sub-
ject to an emissions limitation requirement
under this section, and located in a State that—
(A) has experienced a growth in population
in excess of 25 percent between 1980 and 1988
according to State Population and Household
Estimates, With Age, Sex, and Components of
Change: 1981–1988 allocated by the United
States Department of Commerce, and
(B) had an installed electrical generating ca-
pacity of more than 30,000,000 kw in 1988,
in an amount equal to the difference between
(A) the number of allowances that would be allo-
cated for the unit pursuant to the emissions
limitation requirements of this section applica-
ble to the unit adjusted to reflect the unit’s an-
nual average fuel consumption on a Btu basis of
any three consecutive calendar years between
1980 and 1989 (inclusive) as elected by the owner
or operator and (B) the number of allowances al-
located for the unit pursuant to the emissions
limitation requirements of this section: Pro-
vided, That the number of allowances allocated
pursuant to this subsection shall not exceed an
annual total of 40,000. If necessary to meeting
the 40,000 allowance restriction imposed under
this subsection the Administrator shall reduce,
pro rata, the additional annual allowances allo-
cated to each unit under this subsection.
(2) Beginning January 1, 2000, in addition to al-
lowances allocated pursuant to this section and
section 7651b(a)(1) of this title as basic Phase II
allowance allocations, the Administrator shall
allocate annually for each unit subject to the
emissions limitation requirements of subsection
(b)(1), (A) the lesser of whose actual or allowable
1980 emissions rate has declined by 50 percent or
more as of November 15, 1990, (B) whose actual
emissions rate is less than 1.2 lbs/mmBtu as of
January 1, 2000, (C) which commenced operation
after January 1, 1970, (D) which is owned by a
utility company whose combined commercial
and industrial kilowatt-hour sales have in-
creased by more than 20 percent between cal-
endar year 1980 and November 15, 1990, and (E)
whose company-wide fossil-fuel sulfur dioxide
emissions rate has declined 40 per centum or
more from 1980 to 1988, allowances in an amount
equal to the difference between (i) the number of
allowances that would be allocated for the unit
pursuant to the emissions limitation require-
ments of subsection (b)(1) adjusted to reflect the
unit’s annual average fuel consumption on a Btu
basis for any three consecutive years between
1980 and 1989 (inclusive) as elected by the owner
or operator and (ii) the number of allowances al-
located for the unit pursuant to the emissions
limitation requirements of subsection (b)(1) of
this section: Provided, That the number of allow-
ances allocated pursuant to this paragraph shall
not exceed an annual total of 5,000. If necessary
to meeting the 5,000-allowance restriction im-
posed in the last clause of the preceding sen-
tence the Administrator shall reduce, pro rata,
the additional allowances allocated to each unit
pursuant to this paragraph.
(j) Certain municipally owned power plants
Beginning January 1, 2000, in addition to al-
lowances allocated pursuant to this section and
section 7651b(a)(1) of this title as basic Phase II
allowance allocations, the Administrator shall
allocate annually for each existing municipally
owned oil and gas-fired utility unit with name-
plate capacity equal to, or less than, 40 MWe,
the lesser of whose actual or allowable 1985 sul-
fur dioxide emission rate is less than 1.20 lbs/
mmBtu, allowances in an amount equal to the
product of the unit’s annual fuel consumption
on a Btu basis at a 60 percent capacity factor
multiplied by the lesser of its allowable 1985
emission rate or its actual 1985 emission rate,
divided by 2,000.
(July 14, 1955, ch. 360, title IV, § 405, as added
Pub. L. 101–549, title IV, § 401, Nov. 15, 1990, 104
Stat. 2605.)
Editorial Notes
REFERENCES IN TEXT
Section 301(b) of the Powerplant and Industrial Fuel
Use Act of 1978, referred to in subsec. (g)(5), is section
301(b) of Pub. L. 95–620, which is classified to section
8341(b) of this title. A prior section 301(b) of Pub. L.
95–620, title III, Nov. 9, 1978, 92 Stat. 3305, which was for-
merly classified to section 8341(b) of this title, was re-
pealed by Pub. L. 97–35, title X, § 1021(a), Aug. 13, 1981,
95 Stat. 614.
§ 7651e. Allowances for States with emissions
rates at or below 0.80 lbs/mmBtu
(a) Election of Governor
In addition to basic Phase II allowance alloca-
tions, upon the election of the Governor of any
State, with a 1985 state-wide annual sulfur diox-
ide emissions rate equal to or less than, 0.80 lbs/
mmBtu, averaged over all fossil fuel-fired util-
ity steam generating units, beginning January
1, 2000, and for each calendar year thereafter
until and including 2009, the Administrator shall
allocate, in lieu of other Phase II bonus allow-
ance allocations, allowances from the reserve
created pursuant to section 7651d(a)(2) of this
title to all such units in the State in an amount
equal to 125,000 multiplied by the unit’s pro rata
share of electricity generated in calendar year
1985 at fossil fuel-fired utility steam units in all
States eligible for the election.
(b) Notification of Administrator
Pursuant to section 7651b(a)(1) of this title,
each Governor of a State eligible to make an
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Applicability**
(1) After January 1, 2000, each existing utility unit as provided below is subject to the limitations or requirements of this section. Each utility unit subject to an annual sulfur dioxide tonnage emission limitation under this section is an affected unit under this subchapter. Each source that includes one or more affected units is an affected source. In the case of an existing unit that was not in operation during calendar year 1985, the emission rate for a calendar year after 1985, as determined by the Administrator, shall be used in lieu of the 1985 rate. The owner or operator of any unit operated in violation of this section shall be fully liable under this chapter for fulfilling the obligations specified in [section 7651j of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651j&num=0&edition=prelim).
(2) In addition to basic Phase II allowance allocations, in each year beginning in calendar year 2000 and ending in calendar year 2009, inclusive, the Administrator shall allocate up to 530,000 Phase II bonus allowances pursuant to subsections (b)(2), (c)(4), (d)(3)(A) and (B), and (h)(2) of this section and [section 7651e of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651e&num=0&edition=prelim). Not later than June 1, 1998, the Administrator shall calculate, for each unit granted an extension pursuant to [section 7651h of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7651h&num=0&edition=prelim) the difference between (A) the number of allowances allocated for the unit in calendar year 2000, and (B) the product of the unit’s baseline multiplied by 1.20 lbs/mmBtu, divided by 2000, and sum the computations. In each year,
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 7651d
Stored review status: release_metadata_unconfirmed. Same stored citation; legal effect and authority still require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Findings** The Congress finds that—
(1) the protection of public health and welfare, the preservation of national security, and the regulation of interstate commerce require the establishment of a program for the expended 11 So in original. Probably should be “expanded”. use, consistent with applicable environmental requirements, of coal and other alternate fuels as primary energy sources for existing and new electric powerplants; and
(2) the purposes of this chapter are furthered in cases in which coal or other alternate fuels are used by electric powerplants, consistent with applicable environmental requirements, as primary energy sources in lieu of natural gas or petroleum.
**(b) Statement of purposes** The purpose 22 So in original. Probably should be “purposes”. of this chapter, which shall be carried out in a manner consistent with applicable environmental requirements, are—
(1) to reduce the importation of petroleum and increase the Nation’s capability to use indigenous energy resources of the United States to the extent such reduction and use further the goal of national energy self-sufficiency and otherwise are in the best interests of the United States;
(2) to encourage and foster the greater use of coal and other alternate fuels, in lieu of natural gas and petroleum, as a primary energy source;
(3) to the extent permitted by this chapter, to encourage the use of synthetic gas derived from coal or other alternate fuels;
(4) to encourage the rehabilitation and upgrading of railroad service and equipment necessary to transport coal to regions or States which can use coal in greater quantities;
(5) to encourage the modernization or replacement of existing and new electric powerplants which utilize natural gas or petroleum as a primary energy source
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 8301
Stored review status: release_metadata_unconfirmed. The source passage cites 42 U.S.C. § 8301. This identifies an authority to review, not proof of applicability.
Federal law — U.S. Code and appendices · legal_authorities
Page 7583
TITLE 42—THE PUBLIC HEALTH AND WELFARE
§ 8301
1 So in original. Probably should be ‘‘expanded’’.
2 So in original. Probably should be ‘‘purposes’’.
Editorial Notes
REFERENCES IN TEXT
The Energy Policy Act of 1992, referred to in text, is
Pub. L. 102–486, Oct. 24, 1992, 106 Stat. 2776. For com-
plete classification of this Act to the Code, see Short
Title note set out under section 13201 of this title and
Tables.
CODIFICATION
Section was enacted as part of Department of the In-
terior and Related Agencies Appropriations Act, 1999,
and also as part of the Omnibus Consolidated and
Emergency Supplemental Appropriations Act, 1999, and
not as part of the National Energy Conservation Policy
Act which comprises this chapter.
Statutory Notes and Related Subsidiaries
SIMILAR PROVISIONS
Similar provisions were contained in the following
prior appropriation act:
Pub. L. 105–83, title II, Nov. 14, 1997, 111 Stat. 1582.
CHAPTER 92—POWERPLANT AND
INDUSTRIAL FUEL USE
SUBCHAPTER I—GENERAL PROVISIONS
Sec.
8301.
Findings; statement of purposes.
8302.
Definitions.
8303.
Territorial application.
SUBCHAPTER II—NEW FACILITIES
PART A—PROHIBITIONS
8311.
Coal capability of new electric powerplants;
certification of compliance.
8312.
Repealed.
PART B—EXEMPTIONS
8321.
Temporary exemptions.
8322.
Permanent exemptions.
8323.
General requirements for exemptions.
8324.
Terms and conditions; compliance plans.
SUBCHAPTER III—EXISTING FACILITIES
PART A—PROHIBITIONS
8341.
Existing electric powerplants.
8342.
Repealed.
8343.
Rules relating to case-by-case and category
prohibitions.
PART B—EXEMPTIONS
8351.
Temporary exemptions.
8352.
Permanent exemptions.
8353.
General requirements for exemptions.
8354.
Terms and conditions; compliance pl
Source: Supplied 2024 U.S. Code historical extraction · 42 U.S.C. § 8301
Stored review status: historical_2024_not_currentness_verified. The source passage cites 42 U.S.C. § 8301. This identifies an authority to review, not proof of applicability.