16 U.S.C. § 824o — Electric reliability
Federal law — U.S. Code and appendices · legal_authorities
Page 1423
TITLE 16—CONSERVATION
§ 824o
1 See References in Text note below.
Subsec. (b). Pub. L. 102–486, § 722(1), struck out subsec.
(b) which required applicants for orders to be ready,
willing, and able to reimburse parties subject to such
orders.
Subsec. (e). Pub. L. 102–486, § 722(2), amended subsec.
(e) generally. Prior to amendment, subsec. (e) related
to utilization of interconnection or wheeling authority
in lieu of other authority and limitation of Commission
authority.
Subsecs. (g) to (k). Pub. L. 102–486, § 722(3), added sub-
secs. (g) to (k).
Statutory Notes and Related Subsidiaries
STATE AUTHORITIES; CONSTRUCTION
Nothing in amendment by Pub. L. 102–486 to be con-
strued as affecting or intending to affect, or in any way
to interfere with, authority of any State or local gov-
ernment relating to environmental protection or siting
of facilities, see section 731 of Pub. L. 102–486, set out
as a note under section 796 of this title.
§ 824l. Information requirements
(a) Requests for wholesale transmission services
Whenever any electric utility, Federal power
marketing agency, or any other person gener-
ating electric energy for sale for resale makes a
good faith request to a transmitting utility to
provide wholesale transmission services and re-
quests specific rates and charges, and other
terms and conditions, unless the transmitting
utility agrees to provide such services at rates,
charges, terms and conditions acceptable to
such person, the transmitting utility shall,
within 60 days of its receipt of the request, or
other mutually agreed upon period, provide such
person with a detailed written explanation, with
specific reference to the facts and circumstances
of the request, stating (1) the transmitting util-
ity’s basis for
Source: Supplied 2024 U.S. Code historical extraction · 16 U.S.C. § 824o
Stored review status: historical_2024_not_currentness_verified. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: 888e2d68308c98e90787958f4866cdc9034e9ea606f65377660e901bfaaac683. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:usc2024-157b92bddae6d45015caedc3
Source file: Laws/federal/codes/united-states-code-2024/title-16/section-824o-electric-reliability--9c84a579db.md
Pages: Not recorded – Not recorded
Passage SHA-256: fe9c9da8614bbf76d2f778fc82c63bca3402546958164fd880e31998992fa0b7
Source location: USCODE-2024-title16-chap12-subchapII-sec824o.pdf
Stored source content
Page 1423
TITLE 16—CONSERVATION
§ 824o
1 See References in Text note below.
Subsec. (b). Pub. L. 102–486, § 722(1), struck out subsec.
(b) which required applicants for orders to be ready,
willing, and able to reimburse parties subject to such
orders.
Subsec. (e). Pub. L. 102–486, § 722(2), amended subsec.
(e) generally. Prior to amendment, subsec. (e) related
to utilization of interconnection or wheeling authority
in lieu of other authority and limitation of Commission
authority.
Subsecs. (g) to (k). Pub. L. 102–486, § 722(3), added sub-
secs. (g) to (k).
Statutory Notes and Related Subsidiaries
STATE AUTHORITIES; CONSTRUCTION
Nothing in amendment by Pub. L. 102–486 to be con-
strued as affecting or intending to affect, or in any way
to interfere with, authority of any State or local gov-
ernment relating to environmental protection or siting
of facilities, see section 731 of Pub. L. 102–486, set out
as a note under section 796 of this title.
§ 824l. Information requirements
(a) Requests for wholesale transmission services
Whenever any electric utility, Federal power
marketing agency, or any other person gener-
ating electric energy for sale for resale makes a
good faith request to a transmitting utility to
provide wholesale transmission services and re-
quests specific rates and charges, and other
terms and conditions, unless the transmitting
utility agrees to provide such services at rates,
charges, terms and conditions acceptable to
such person, the transmitting utility shall,
within 60 days of its receipt of the request, or
other mutually agreed upon period, provide such
person with a detailed written explanation, with
specific reference to the facts and circumstances
of the request, stating (1) the transmitting util-
ity’s basis for the proposed rates, charges,
terms, and conditions for such services, and (2)
its analysis of any physical or other constraints
affecting the provision of such services.
(b) Transmission capacity and constraints
Not later than 1 year after October 24, 1992,
the Commission shall promulgate a rule requir-
ing that information be submitted annually to
the Commission by transmitting utilities which
is adequate to inform potential transmission
customers, State regulatory authorities, and the
public of potentially available transmission ca-
pacity and known constraints.
(June 10, 1920, ch. 285, pt. II, § 213, as added Pub.
L. 102–486, title VII, § 723, Oct. 24, 1992, 106 Stat.
2919.)
Statutory Notes and Related Subsidiaries
STATE AUTHORITIES; CONSTRUCTION
Nothing in this section to be construed as affecting
or intending to affect, or in any way to interfere with,
authority of any State or local government relating to
environmental protection or siting of facilities, see sec-
tion 731 of Pub. L. 102–486, set out as a note under sec-
tion 796 of this title.
§ 824m. Sales by exempt wholesale generators
No rate or charge received by an exempt
wholesale generator for the sale of electric en-
ergy shall be lawful under section 824d of this
title if, after notice and opportunity for hearing,
the Commission finds that such rate or charge
results from the receipt of any undue preference
or advantage from an electric utility which is an
associate company or an affiliate of the exempt
wholesale generator. For purposes of this sec-
tion, the terms ‘‘associate company’’ and ‘‘affil-
iate’’ shall have the same meaning as provided
in section 16451 of title 42.1
(June 10, 1920, ch. 285, pt. II, § 214, as added Pub.
L. 102–486, title VII, § 724, Oct. 24, 1992, 106 Stat.
2920;
amended
Pub.
L.
109–58,
title
XII,
§ 1277(b)(2), Aug. 8, 2005, 119 Stat. 978.)
Editorial Notes
REFERENCES IN TEXT
Section 16451 of title 42, referred to in text, was in the
original ‘‘section 2(a) of the Public Utility Holding
Company Act of 2005’’ and was translated as reading
‘‘section 1262’’ of that Act, meaning section 1262 of sub-
title F of title XII of Pub. L. 109–58, to reflect the prob-
able intent of Congress, because subtitle F of title XII
of Pub. L. 109–58 does not contain a section 2 and sec-
tion 1262 of subtitle F of title XII of Pub. L. 109–58 de-
fines terms.
AMENDMENTS
2005—Pub. L. 109–58 substituted ‘‘section 16451 of title
42’’ for ‘‘section 79b(a) of title 15’’.
Statutory Notes and Related Subsidiaries
EFFECTIVE DATE OF 2005 AMENDMENT
Amendment by Pub. L. 109–58 effective 6 months after
Aug. 8, 2005, with provisions relating to effect of com-
pliance with certain regulations approved and made ef-
fective prior to such date, see section 1274 of Pub. L.
109–58, set out as an Effective Date note under section
16451 of Title 42, The Public Health and Welfare.
STATE AUTHORITIES; CONSTRUCTION
Nothing in this section to be construed as affecting
or intending to affect, or in any way to interfere with,
authority of any State or local government relating to
environmental protection or siting of facilities, see sec-
tion 731 of Pub. L. 102–486, set out as a note under sec-
tion 796 of this title.
§ 824n. Repealed. Pub. L. 109–58, title XII,
§ 1232(e)(3), Aug. 8, 2005, 119 Stat. 957
Section, Pub. L. 106–377, § 1(a)(2) [title III, § 311], Oct.
27, 2000, 114 Stat. 1441, 1441A–80, related to authority re-
garding formation and operation of regional trans-
mission organizations.
§ 824o. Electric reliability
(a) Definitions
For purposes of this section:
(1) The term ‘‘bulk-power system’’ means—
(A) facilities and control systems nec-
essary for operating an interconnected elec-
tric energy transmission network (or any
portion thereof); and
(B) electric energy from generation facili-
ties needed to maintain transmission system
reliability.
The term does not include facilities used in
the local distribution of electric energy.
(2) The terms ‘‘Electric Reliability Organiza-
tion’’ and ‘‘ERO’’ mean the organization cer-
Page 1424
TITLE 16—CONSERVATION
§ 824o
tified by the Commission under subsection (c)
the purpose of which is to establish and en-
force reliability standards for the bulk-power
system, subject to Commission review.
(3) The term ‘‘reliability standard’’ means a
requirement, approved by the Commission
under this section, to provide for reliable oper-
ation of the bulk-power system. The term in-
cludes requirements for the operation of exist-
ing bulk-power system facilities, including
cybersecurity protection, and the design of
planned additions or modifications to such fa-
cilities to the extent necessary to provide for
reliable operation of the bulk-power system,
but the term does not include any requirement
to enlarge such facilities or to construct new
transmission capacity or generation capacity.
(4) The term ‘‘reliable operation’’ means op-
erating the elements of the bulk-power system
within equipment and electric system ther-
mal, voltage, and stability limits so that in-
stability, uncontrolled separation, or cas-
cading failures of such system will not occur
as a result of a sudden disturbance, including
a cybersecurity incident, or unanticipated
failure of system elements.
(5) The term ‘‘Interconnection’’ means a geo-
graphic area in which the operation of bulk-
power system components is synchronized
such that the failure of one or more of such
components may adversely affect the ability
of the operators of other components within
the system to maintain reliable operation of
the facilities within their control.
(6) The term ‘‘transmission organization’’
means a Regional Transmission Organization,
Independent System Operator, independent
transmission provider, or other transmission
organization finally approved by the Commis-
sion for the operation of transmission facili-
ties.
(7) The term ‘‘regional entity’’ means an en-
tity having enforcement authority pursuant to
subsection (e)(4).
(8) The term ‘‘cybersecurity incident’’ means
a malicious act or suspicious event that dis-
rupts, or was an attempt to disrupt, the oper-
ation of those programmable electronic de-
vices and communication networks including
hardware, software and data that are essential
to the reliable operation of the bulk power
system.
(b) Jurisdiction and applicability
(1) The Commission shall have jurisdiction,
within the United States, over the ERO certified
by the Commission under subsection (c), any re-
gional entities, and all users, owners and opera-
tors of the bulk-power system, including but not
limited to the entities described in section 824(f)
of this title, for purposes of approving reliability
standards established under this section and en-
forcing compliance with this section. All users,
owners and operators of the bulk-power system
shall comply with reliability standards that
take effect under this section.
(2) The Commission shall issue a final rule to
implement the requirements of this section not
later than 180 days after August 8, 2005.
(c) Certification
Following the issuance of a Commission rule
under subsection (b)(2), any person may submit
an application to the Commission for certifi-
cation as the Electric Reliability Organization.
The Commission may certify one such ERO if
the Commission determines that such ERO—
(1) has the ability to develop and enforce,
subject to subsection (e)(2), reliability stand-
ards that provide for an adequate level of reli-
ability of the bulk-power system; and
(2) has established rules that—
(A) assure its independence of the users
and owners and operators of the bulk-power
system, while assuring fair stakeholder rep-
resentation in the selection of its directors
and balanced decisionmaking in any ERO
committee or subordinate organizational
structure;
(B) allocate equitably reasonable dues,
fees, and other charges among end users for
all activities under this section;
(C) provide fair and impartial procedures
for enforcement of reliability standards
through the imposition of penalties in ac-
cordance with subsection (e) (including limi-
tations on activities, functions, or oper-
ations, or other appropriate sanctions);
(D) provide for reasonable notice and op-
portunity for public comment, due process,
openness, and balance of interests in devel-
oping reliability standards and otherwise ex-
ercising its duties; and
(E) provide for taking, after certification,
appropriate steps to gain recognition in Can-
ada and Mexico.
(d) Reliability standards
(1) The Electric Reliability Organization shall
file each reliability standard or modification to
a reliability standard that it proposes to be
made effective under this section with the Com-
mission.
(2) The Commission may approve, by rule or
order, a proposed reliability standard or modi-
fication to a reliability standard if it determines
that the standard is just, reasonable, not unduly
discriminatory or preferential, and in the public
interest. The Commission shall give due weight
to the technical expertise of the Electric Reli-
ability Organization with respect to the content
of a proposed standard or modification to a reli-
ability standard and to the technical expertise
of a regional entity organized on an Inter-
connection-wide basis with respect to a reli-
ability standard to be applicable within that
Interconnection, but shall not defer with respect
to the effect of a standard on competition. A
proposed standard or modification shall take ef-
fect upon approval by the Commission.
(3) The Electric Reliability Organization shall
rebuttably presume that a proposal from a re-
gional entity organized on an Interconnection-
wide basis for a reliability standard or modifica-
tion to a reliability standard to be applicable on
an Interconnection-wide basis is just, reason-
able, and not unduly discriminatory or pref-
erential, and in the public interest.
(4) The Commission shall remand to the Elec-
tric Reliability Organization for further consid-
eration a proposed reliability standard or a
modification to a reliability standard that the
Commission disapproves in whole or in part.
(5) The Commission, upon its own motion or
upon complaint, may order the Electric Reli-
Page 1425
TITLE 16—CONSERVATION
§ 824o
ability Organization to submit to the Commis-
sion a proposed reliability standard or a modi-
fication to a reliability standard that addresses
a specific matter if the Commission considers
such a new or modified reliability standard ap-
propriate to carry out this section.
(6) The final rule adopted under subsection
(b)(2) shall include fair processes for the identi-
fication and timely resolution of any conflict
between a reliability standard and any function,
rule, order, tariff, rate schedule, or agreement
accepted, approved, or ordered by the Commis-
sion applicable to a transmission organization.
Such transmission organization shall continue
to comply with such function, rule, order, tariff,
rate schedule or agreement accepted, approved,
or ordered by the Commission until—
(A) the Commission finds a conflict exists
between a reliability standard and any such
provision;
(B) the Commission orders a change to such
provision pursuant to section 824e of this title;
and
(C) the ordered change becomes effective
under this subchapter.
If the Commission determines that a reliability
standard needs to be changed as a result of such
a conflict, it shall order the ERO to develop and
file with the Commission a modified reliability
standard under paragraph (4) or (5) of this sub-
section.
(e) Enforcement
(1) The ERO may impose, subject to paragraph
(2), a penalty on a user or owner or operator of
the bulk-power system for a violation of a reli-
ability standard approved by the Commission
under subsection (d) if the ERO, after notice and
an opportunity for a hearing—
(A) finds that the user or owner or operator
has violated a reliability standard approved by
the Commission under subsection (d); and
(B) files notice and the record of the pro-
ceeding with the Commission.
(2) A penalty imposed under paragraph (1) may
take effect not earlier than the 31st day after
the ERO files with the Commission notice of the
penalty and the record of proceedings. Such pen-
alty shall be subject to review by the Commis-
sion, on its own motion or upon application by
the user, owner or operator that is the subject of
the penalty filed within 30 days after the date
such notice is filed with the Commission. Appli-
cation to the Commission for review, or the ini-
tiation of review by the Commission on its own
motion, shall not operate as a stay of such pen-
alty unless the Commission otherwise orders
upon its own motion or upon application by the
user, owner or operator that is the subject of
such penalty. In any proceeding to review a pen-
alty imposed under paragraph (1), the Commis-
sion, after notice and opportunity for hearing
(which hearing may consist solely of the record
before the ERO and opportunity for the presen-
tation of supporting reasons to affirm, modify,
or set aside the penalty), shall by order affirm,
set aside, reinstate, or modify the penalty, and,
if appropriate, remand to the ERO for further
proceedings. The Commission shall implement
expedited procedures for such hearings.
(3) On its own motion or upon complaint, the
Commission may order compliance with a reli-
ability standard and may impose a penalty
against a user or owner or operator of the bulk-
power system if the Commission finds, after no-
tice and opportunity for a hearing, that the user
or owner or operator of the bulk-power system
has engaged or is about to engage in any acts or
practices that constitute or will constitute a
violation of a reliability standard.
(4) The Commission shall issue regulations au-
thorizing the ERO to enter into an agreement to
delegate authority to a regional entity for the
purpose of proposing reliability standards to the
ERO and enforcing reliability standards under
paragraph (1) if—
(A) the regional entity is governed by—
(i) an independent board;
(ii) a balanced stakeholder board; or
(iii) a combination independent and bal-
anced stakeholder board.
(B) the regional entity otherwise satisfies
the provisions of subsection (c)(1) and (2); and
(C) the agreement promotes effective and ef-
ficient administration of bulk-power system
reliability.
The Commission may modify such delegation.
The ERO and the Commission shall rebuttably
presume that a proposal for delegation to a re-
gional entity organized on an Interconnection-
wide basis promotes effective and efficient ad-
ministration of bulk-power system reliability
and should be approved. Such regulation may
provide that the Commission may assign the
ERO’s authority to enforce reliability standards
under paragraph (1) directly to a regional entity
consistent with the requirements of this para-
graph.
(5) The Commission may take such action as is
necessary or appropriate against the ERO or a
regional entity to ensure compliance with a reli-
ability standard or any Commission order af-
fecting the ERO or a regional entity.
(6) Any penalty imposed under this section
shall bear a reasonable relation to the serious-
ness of the violation and shall take into consid-
eration the efforts of such user, owner, or oper-
ator to remedy the violation in a timely man-
ner.
(f) Changes in Electric Reliability Organization
rules
The Electric Reliability Organization shall
file with the Commission for approval any pro-
posed rule or proposed rule change, accompanied
by an explanation of its basis and purpose. The
Commission, upon its own motion or complaint,
may propose a change to the rules of the ERO.
A proposed rule or proposed rule change shall
take effect upon a finding by the Commission,
after notice and opportunity for comment, that
the change is just, reasonable, not unduly dis-
criminatory or preferential, is in the public in-
terest, and satisfies the requirements of sub-
section (c).
(g) Reliability reports
The ERO shall conduct periodic assessments of
the reliability and adequacy of the bulk-power
system in North America.
Page 1426
TITLE 16—CONSERVATION
§ 824o–1
(h) Coordination with Canada and Mexico
The President is urged to negotiate inter-
national agreements with the governments of
Canada and Mexico to provide for effective com-
pliance with reliability standards and the effec-
tiveness of the ERO in the United States and
Canada or Mexico.
(i) Savings provisions
(1) The ERO shall have authority to develop
and enforce compliance with reliability stand-
ards for only the bulk-power system.
(2) This section does not authorize the ERO or
the Commission to order the construction of ad-
ditional generation or transmission capacity or
to set and enforce compliance with standards for
adequacy or safety of electric facilities or serv-
ices.
(3) Nothing in this section shall be construed
to preempt any authority of any State to take
action to ensure the safety, adequacy, and reli-
ability of electric service within that State, as
long as such action is not inconsistent with any
reliability standard, except that the State of
New York may establish rules that result in
greater reliability within that State, as long as
such action does not result in lesser reliability
outside the State than that provided by the reli-
ability standards.
(4) Within 90 days of the application of the
Electric Reliability Organization or other af-
fected party, and after notice and opportunity
for comment, the Commission shall issue a final
order determining whether a State action is in-
consistent with a reliability standard, taking
into consideration any recommendation of the
ERO.
(5) The Commission, after consultation with
the ERO and the State taking action, may stay
the effectiveness of any State action, pending
the Commission’s issuance of a final order.
(j) Regional advisory bodies
The Commission shall establish a regional ad-
visory body on the petition of at least two-
thirds of the States within a region that have
more than one-half of their electric load served
within the region. A regional advisory body
shall be composed of one member from each par-
ticipating State in the region, appointed by the
Governor of each State, and may include rep-
resentatives of agencies, States, and provinces
outside the United States. A regional advisory
body may provide advice to the Electric Reli-
ability Organization, a regional entity, or the
Commission regarding the governance of an ex-
isting or proposed regional entity within the
same region, whether a standard proposed to
apply within the region is just, reasonable, not
unduly discriminatory or preferential, and in
the public interest, whether fees proposed to be
assessed within the region are just, reasonable,
not unduly discriminatory or preferential, and
in the public interest and any other responsibil-
ities requested by the Commission. The Commis-
sion may give deference to the advice of any
such regional advisory body if that body is orga-
nized on an Interconnection-wide basis.
(k) Alaska and Hawaii
The provisions of this section do not apply to
Alaska or Hawaii.
(June 10, 1920, ch. 285, pt. II, § 215, as added Pub.
L. 109–58, title XII, § 1211(a), Aug. 8, 2005, 119
Stat. 941.)
Statutory Notes and Related Subsidiaries
STATUS OF ERO
Pub. L. 109–58, title XII, § 1211(b), Aug. 8, 2005, 119
Stat. 946, provided that: ‘‘The Electric Reliability Orga-
nization certified by the Federal Energy Regulatory
Commission under section 215(c) of the Federal Power
Act [16 U.S.C. 824o(c)] and any regional entity delegated
enforcement authority pursuant to section 215(e)(4) of
that Act [16 U.S.C. 824o(e)(4)] are not departments,
agencies, or instrumentalities of the United States
Government.’’
ACCESS APPROVALS BY FEDERAL AGENCIES
Pub. L. 109–58, title XII, § 1211(c), Aug. 8, 2005, 119
Stat. 946, provided that: ‘‘Federal agencies responsible
for approving access to electric transmission or dis-
tribution facilities located on lands within the United
States shall, in accordance with applicable law, expe-
dite any Federal agency approvals that are necessary
to allow the owners or operators of such facilities to
comply with any reliability standard, approved by the
[Federal Energy Regulatory] Commission under section
215 of the Federal Power Act [16 U.S.C. 824o], that per-
tains to vegetation management, electric service res-
toration, or resolution of situations that imminently
endanger the reliability or safety of the facilities.’’
§ 824o–1. Critical electric infrastructure security
(a) Definitions
For purposes of this section:
(1) Bulk-power system; Electric Reliability Or-
ganization; regional entity
The terms ‘‘bulk-power system’’, ‘‘Electric
Reliability Organization’’, and ‘‘regional enti-
ty’’ have the meanings given such terms in
paragraphs (1), (2), and (7) of section 824o(a) of
this title, respectively.
(2) Critical electric infrastructure
The term ‘‘critical electric infrastructure’’
means a system or asset of the bulk-power sys-
tem, whether physical or virtual, the inca-
pacity or destruction of which would nega-
tively affect national security, economic secu-
rity, public health or safety, or any combina-
tion of such matters.
(3) Critical electric infrastructure information
The term ‘‘critical electric infrastructure in-
formation’’ means information related to crit-
ical electric infrastructure, or proposed crit-
ical electrical infrastructure, generated by or
provided to the Commission or other Federal
agency, other than classified national security
information, that is designated as critical
electric infrastructure information by the
Commission or the Secretary pursuant to sub-
section (d). Such term includes information
that qualifies as critical energy infrastructure
information under the Commission’s regula-
tions.
(4) Defense critical electric infrastructure
The term ‘‘defense critical electric infra-
structure’’ means any electric infrastructure
located in any of the 48 contiguous States or
the District of Columbia that serves a facility
designated by the Secretary pursuant to sub-
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Definitions** For purposes of this section:
(1) The term “bulk-power system” means—
(A) facilities and control systems necessary for operating an interconnected electric energy transmission network (or any portion thereof); and
(B) electric energy from generation facilities needed to maintain transmission system reliability.
The term does not include facilities used in the local distribution of electric energy.
(2) The terms “Electric Reliability Organization” and “ERO” mean the organization certified by the Commission under subsection (c) the purpose of which is to establish and enforce reliability standards for the bulk-power system, subject to Commission review.
(3) The term “reliability standard” means a requirement, approved by the Commission under this section, to provide for reliable operation of the bulk-power system. The term includes requirements for the operation of existing bulk-power system facilities, including cybersecurity protection, and the design of planned additions or modifications to such facilities to the extent necessary to provide for reliable operation of the bulk-power system, but the term does not include any requirement to enlarge such facilities or to construct new transmission capacity or generation capacity.
(4) The term “reliable operation” means operating the elements of the bulk-power system within equipment and electric system thermal, voltage, and stability limits so that instability, uncontrolled separation, or cascading failures of such system will not occur as a result of a sudden disturbance, including a cybersecurity incident, or unanticipated failure of system elements.
(5) The term “Interconnection” means a geographic area in which the operation of bulk-power system components is synchronized such that the f
Source: Supplied U.S. Code snapshot — release unconfirmed · 16 U.S.C. § 824o
Stored review status: release_metadata_unconfirmed. Same stored citation; legal effect and authority still require review.