**(a) Reporting Requirements.—** (1) Upon receiving a concept definition study under phase 1 of the joint nuclear weapons life cycle for the W93 nuclear weapon, the Nuclear Weapons Council shall submit to the congressional defense committees a report that includes the following: (A) A description of the potential military characteristics of the weapon. (B) A description of the stockpile-to-target sequence requirements of the weapon. (C) An initial assessment of the requirements a W93 nuclear weapon program is likely to generate for the nuclear security enterprise, including— (i) adjustments to the size and composition of the workforce; (ii) additions to existing weapon design and production capabilities; or (iii) additional facility recapitalization or new construction. (D) A preliminary description of other significant requirements for a W93 nuclear weapon program, including— (i) first production unit date; (ii) initial operational capability date; (iii) full operational capability date; and (iv) any unique safety and surety requirements that could increase design complexity or cost estimate uncertainty. (2) (A) Not later than 15 days after the date on which the Nuclear Weapons Council approves phase 2 of the joint nuclear weapons life cycle for the W93 nuclear weapon, the Administrator shall provide to the congressional defense committees a briefing on a plan to implement a process of independent peer review or review by a board of experts, or both, with respect to— (i) the nonnuclear components of the weapon; (ii) subsystem design; and (iii) engineering aspects of the weapon. (B) The Administrator shall ensure that the process required by subparagraph (A)— (i) uses— (I) all relevant cap

Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 6135

Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.

Original supplied file — preserved unchanged

Download original Markdown file

File SHA-256: 5e0246fb84a313a9e88fea17b798104efb3960aab67416c0d1a6de82dc6c2d83. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.

Authority boundary: historical or unconfirmed source not current law verified.

Open the recorded source website ↗

Record provenance

Stable record: federal_law:legal_authorities:record_usc_db38b2d34a3af0573daa6c45
Source file: Laws/federal/codes/united-states-code/title-10/section-6135-w93-nuclear-warhead-acquisition-process--77f7c81d03.md
Pages: Not recorded – Not recorded
Passage SHA-256: 4c25e0738f7625311358a2f18c5205c4672adbfbd5eeb4bc378ba2de32843928

Source location: Title 10, Chapter 602, § 6135; chapter-602-nuclear-weapons-stockpile-matters.md

Stored source content

**(a) Reporting Requirements.—** (1) Upon receiving a concept definition study under phase 1 of the joint nuclear weapons life cycle for the W93 nuclear weapon, the Nuclear Weapons Council shall submit to the congressional defense committees a report that includes the following: (A) A description of the potential military characteristics of the weapon. (B) A description of the stockpile-to-target sequence requirements of the weapon. (C) An initial assessment of the requirements a W93 nuclear weapon program is likely to generate for the nuclear security enterprise, including— (i) adjustments to the size and composition of the workforce; (ii) additions to existing weapon design and production capabilities; or (iii) additional facility recapitalization or new construction. (D) A preliminary description of other significant requirements for a W93 nuclear weapon program, including— (i) first production unit date; (ii) initial operational capability date; (iii) full operational capability date; and (iv) any unique safety and surety requirements that could increase design complexity or cost estimate uncertainty. (2) (A) Not later than 15 days after the date on which the Nuclear Weapons Council approves phase 2 of the joint nuclear weapons life cycle for the W93 nuclear weapon, the Administrator shall provide to the congressional defense committees a briefing on a plan to implement a process of independent peer review or review by a board of experts, or both, with respect to— (i) the nonnuclear components of the weapon; (ii) subsystem design; and (iii) engineering aspects of the weapon. (B) The Administrator shall ensure that the process required by subparagraph (A)— (i) uses— (I) all relevant capabilities of the Federal Government, the defense industrial base, and institutions of higher education; and (II) other capabilities that the Administrator determines necessary; and (ii) informs the entire development life cycle of the W93 nuclear weapon. **(b) Certifications and Reports at Phase 3.—** Not later than 15 days after the date on which the Nuclear Weapons Council approves phase 3 of the joint nuclear weapons life cycle for the W93 nuclear weapon— (1) the administrator shall provide to the congressional defense committees a briefing that includes certifications that— (A) phases 1 through 5 of the joint nuclear weapons life cycle for the weapon will employ, at a minimum, the same best practices and will provide Congress with the same level of programmatic insight as exists under the phase 6.X process for life extension programs; and (B) the proposed design for the weapon can be carried out within estimated schedule and cost objectives; and (2) the Commander of the United States Strategic Command shall submit to the congressional defense committees a report containing, or provide to such committees a briefing on, the requirements for weapon quantity and composition by type for the sub-surface ballistic nuclear (SSBN) force, including such requirements planned for the 15-year period following the date of the report or briefing, as the case may be, including any planned life extensions, retirements, or alterations. **(c) Waivers.—** Subsections (a) and (b) may be waived during a period of war declared by Congress after January 1, 2021. **(d) Joint Nuclear Weapons Life Cycle Defined.—** In this section, the term “joint nuclear weapons life cycle” has the meaning given that term in section 6131.

Cross-references

Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.

Federal law — U.S. Code and appendices · legal_authorities

50 U.S.C. § 2541, 2542 — Repealed. Pub. L. 119–60, div. C, title XXXI, § 3111(b)(1), Dec. 18, 2025, 139 Stat. 1458

### Statutory Notes Section 2537, Pub. L. 107–314, div. D, title XLII, § 4217, as added Pub. L. 112–239, div. C, title XXXI, § 3162(a), Jan. 2, 2013, 126 Stat. 2204; amended Pub. L. 113–66, div. C, title XXXI, §§ 3112(b), 3146(a)(2)(C), Dec. 26, 2013, 127 Stat. 1053, 1072; Pub. L. 113–291, div. C, title XXXI, § 3114(a), (b), Dec. 19, 2014, 128 Stat. 3887, 3888; Pub. L. 114–92, div. C, title XXXI, § 3113(b)(1), (2)(A), Nov. 25, 2015, 129 Stat. 1192; Pub. L. 115–91, div. C, title XXXI, §§ 3113, 3133(d), Dec. 12, 2017, 131 Stat. 1884, 1896; Pub. L. 116–283, div. C, title XXXI, § 3111(b), Jan. 1, 2021, 134 Stat. 4377; Pub. L. 117–81, div. A, title XVII, § 1702(k)(3)(A), Dec. 27, 2021, 135 Stat. 2160; Pub. L. 117–263, div. A, title VIII, § 809(c)(1), Dec. 23, 2022, 136 Stat. 2706, required submission of Selected Acquisition Reports and independent cost estimates and reviews of certain programs and facilities. See [section 6125 of Title 10](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section6125&num=0&edition=prelim), Armed Forces. Section 2538, Pub. L. 107–314, div. D, title XLII, § 4218, formerly Pub. L. 105–85, div. A, title XIII, § 1305, Nov. 18, 1997, 111 Stat. 1952, renumbered Pub. L. 107–314, div. D, title XLII, § 4218, and amended Pub. L. 112–239, div. C, title XXXI, § 3164(a), (b), Jan. 2, 2013, 126 Stat. 2206; Pub. L. 113–66, div. C, title XXXI, § 3146(a)(2)(D), (c)(10), Dec. 26, 2013, 127 Stat. 1072, 1075; Pub. L. 113–291, div. C, title XXXI, § 3142(e), Dec. 19, 2014, 128 Stat. 3900; Pub. L. 116–92, div. C, title XXXI, § 3139(b)(5), Dec. 20, 2019, 133 Stat. 1963, related to advice to the President and Congress regarding safety, security, and reliability of United States nuclear weapons stockpile. See [section 6126 of Title 10](https://usc