10 U.S.C. § 8751 — Notification of Navy procurement production disruptions
Federal law — U.S. Code and appendices · legal_authorities
**(a) Requirement for Contractor To Provide Notice of Delays.—** The Secretary of the Navy shall require prime contractors of any Navy procurement program funded under either the Shipbuilding and Conversion, Navy account or the Other Procurement, Navy account to report within 15 calendar days any stop work order or other manufacturing disruption of 15 calendar days or more, by the prime contractor or any subcontractor, to the respective program manager and Navy technical authority.
**(b) Quarterly Reports.—** The Secretary of the Navy shall submit to the congressional defense committees not later than 15 calendar days after the end of each quarter of a fiscal year a report listing all notifications made pursuant to subsection (a) during the preceding quarter.
Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 8751
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: ac2e22dc4e7b2a8df8585d2c7b860d5433a88bcb9a46dfc07636a74612d4648f. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_da6487264f0b7229d8aba356
Source file: Laws/federal/codes/united-states-code/title-10/section-8751-notification-of-navy-procurement-production-disruptions--4361e5f210.md
Pages: Not recorded – Not recorded
Passage SHA-256: 889867c52a5d5e26b5264a331a6d2d94cdc9cd6d6bec14a949f504c4ba686263
Source location: Title 10, Chapter 873, § 8751; chapter-873-procurement-of-supplies-and-services.md
Stored source content
**(a) Requirement for Contractor To Provide Notice of Delays.—** The Secretary of the Navy shall require prime contractors of any Navy procurement program funded under either the Shipbuilding and Conversion, Navy account or the Other Procurement, Navy account to report within 15 calendar days any stop work order or other manufacturing disruption of 15 calendar days or more, by the prime contractor or any subcontractor, to the respective program manager and Navy technical authority.
**(b) Quarterly Reports.—** The Secretary of the Navy shall submit to the congressional defense committees not later than 15 calendar days after the end of each quarter of a fiscal year a report listing all notifications made pursuant to subsection (a) during the preceding quarter.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
<a id="section-2339c"></a>
Source: U.S. Code supplied Markdown snapshot · 10 U.S.C. § 2339b
Stored review status: release_metadata_unconfirmed; partially_verified. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a)** The Secretary of the Air Force shall procure, and issue without charge to any person entitled thereto, any service medal authorized for members of the Air Force or the Space Force after September 26, 1947, and any ribbon, clasp, star, or similar device prescribed as a part of that medal.
**(b)** Under such regulations as the Secretary may prescribe, any medal or other device issued under subsection (a) that is lost, destroyed, or becomes unfit for use without fault or neglect of the owner, may be replaced at cost. However, if the owner is a member of the Air Force or the Space Force, the medal or device may be replaced without charge.
**(c)** The Secretary may spend, from any appropriation for the support of the Air Force or the Space Force, amounts necessary to provide medals and devices under this section.
Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 9281
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Defense Acquisition System.—** In this part, the term “defense acquisition system” means—
(1) the workforce engaged in carrying out the acquisition of property and services for the Department of Defense;
(2) the management structure responsible for directing and overseeing the acquisition of property and services for the Department of Defense; and
(3) the statutory, regulatory, and policy framework that guides the acquisition of property and services for the Department of Defense.
**(b) Element of the Defense Acquisition System.—** In this part, the term “element of the defense acquisition system” means an organization that—
(1) employs members of the acquisition workforce;
(2) carries out acquisition functions; and
(3) focuses primarily on acquisition.
**(c) Acquisition.—** In this part, the term “acquisition” has the meaning provided in [section 131 of title 41](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section131&num=0&edition=prelim).
Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 3001
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Page 3377
TITLE 10—ARMED FORCES
§ 8752
Sec.
8753.
Tolls and fares: payment or reimbursement.
8754.
Marine mammals: use for national defense
purposes.
8755.
Disclosures for offerors for certain ship-
building major defense acquisition program
contracts.
Editorial Notes
PRIOR PROVISIONS
A prior chapter 873, consisting of sections 9021 to 9027,
related to civilian employees in the Air Force, prior to
renumbering as chapter 947 of this title.
AMENDMENTS
2021—Pub. L. 117–81, div. A, title XVII, § 1701(e)(1)(B),
Dec. 27, 2021, 135 Stat. 2138, added item 8755.
Pub. L. 116–283, div. A, title XVIII, § 1878(b), Jan. 1,
2021, 134 Stat. 4292, added item 8751.
2018—Pub. L. 115–232, div. A, title VIII, § 807(e)(4),
(f)(1), Aug. 13, 2018, 132 Stat. 1838, redesignated chapter
645 of this title as this chapter and items 7522 to 7524 as
8752 to 8754, respectively.
1994—Pub. L. 103–355, title II, § 2001(j)(3)(C), Oct. 13,
1994, 108 Stat. 3303, struck out item 7521 ‘‘Progress pay-
ment for work done; lien based on payment’’.
1986—Pub. L. 99–661, div. A, title XIII, § 1354(b), Nov.
14, 1986, 100 Stat. 3996, added item 7524.
§ 8751. Notification of Navy procurement produc-
tion disruptions
(a) REQUIREMENT FOR CONTRACTOR TO PROVIDE
NOTICE OF DELAYS.—The Secretary of the Navy
shall require prime contractors of any Navy pro-
curement program funded under either the Ship-
building and Conversion, Navy account or the
Other Procurement, Navy account to report
within 15 calendar days any stop work order or
other manufacturing disruption of 15 calendar
days or more, by the prime contractor or any
subcontractor, to the respective program man-
ager and Navy technical authority.
(b) QUARTERLY
REPORTS.—The Secretary of
the Navy shall submit to the congressional de-
fe
Source: Supplied 2024 U.S. Code historical extraction · 10 U.S.C. § 8751
Stored review status: historical_2024_not_currentness_verified. Same stored citation; legal effect and authority still require review.