40 U.S.C. § 3703 — Report of violations and withholding of amounts for unpaid wages and liquidated damages
Federal law — U.S. Code and appendices · legal_authorities
**(a) Reports of Inspectors.—** An officer or individual designated as an inspector of the work to be performed under a contract described in [section 3701 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section3701&num=0&edition=prelim), or to aid in the enforcement or fulfillment of the contract, on observation or after investigation immediately shall report to the proper officer of the Federal Government, a territory of the United States, or the District of Columbia all violations of this chapter occurring in the performance of the work, together with the name of each laborer or mechanic who was required or permitted to work in violation of this chapter and the day the violation occurred.
**(b) Withholding Amounts.—**
(1) **Determining amount.—** — The amount of unpaid wages and liquidated damages owing under this chapter shall be determined administratively.
(2) **Amount directed to be withheld.—** — The officer or individual whose duty it is to approve the payment of money by the Government, territory, or District of Columbia in connection with the performance of the contract work shall direct the amount of—
(A) liquidated damages to be withheld for the use and benefit of the Government, territory, or District; and
(B) unpaid wages to be withheld for the use and benefit of the laborers and mechanics who were not compensated as required under this chapter.
(3) **Payment.—** — The Secretary of Labor shall pay the amount administratively determined to be due directly to the laborers and mechanics from amounts withheld on account of underpayments of wages if the amount withheld is adequate. If the amount withheld is not adequate, the Secretary of Labor shall pay an equitable proportion of the amount due.
**(c) Right of Act
Source: Supplied U.S. Code snapshot — release unconfirmed · 40 U.S.C. § 3703
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: 0c2969cda1602cf481aec134eaaa71d06c723cb417c24630a4d8724814b273fe. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_b58963dfc8bdb8909a1a7087
Source file: Laws/federal/codes/united-states-code/title-40/section-3703-report-of-violations-and-withholding-of-amounts-for-unpaid-wages-and-liq--8552ff9ebd.md
Pages: Not recorded – Not recorded
Passage SHA-256: b0151b9557ef8335a888d099c9a0fc942472b9536593fcd4c3fe8e57b1902238
Source location: Title 40, Chapter 37, § 3703; chapter-037-contract-work-hours-and-safety-standards.md
Stored source content
**(a) Reports of Inspectors.—** An officer or individual designated as an inspector of the work to be performed under a contract described in [section 3701 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section3701&num=0&edition=prelim), or to aid in the enforcement or fulfillment of the contract, on observation or after investigation immediately shall report to the proper officer of the Federal Government, a territory of the United States, or the District of Columbia all violations of this chapter occurring in the performance of the work, together with the name of each laborer or mechanic who was required or permitted to work in violation of this chapter and the day the violation occurred.
**(b) Withholding Amounts.—**
(1) **Determining amount.—** — The amount of unpaid wages and liquidated damages owing under this chapter shall be determined administratively.
(2) **Amount directed to be withheld.—** — The officer or individual whose duty it is to approve the payment of money by the Government, territory, or District of Columbia in connection with the performance of the contract work shall direct the amount of—
(A) liquidated damages to be withheld for the use and benefit of the Government, territory, or District; and
(B) unpaid wages to be withheld for the use and benefit of the laborers and mechanics who were not compensated as required under this chapter.
(3) **Payment.—** — The Secretary of Labor shall pay the amount administratively determined to be due directly to the laborers and mechanics from amounts withheld on account of underpayments of wages if the amount withheld is adequate. If the amount withheld is not adequate, the Secretary of Labor shall pay an equitable proportion of the amount due.
**(c) Right of Action and Intervention Against Contractors and Sureties.—** If the accrued payments withheld under the terms of the contract are insufficient to reimburse all the laborers and mechanics who have not been paid the wages required under this chapter, the laborers and mechanics, in the case of a department or agency of the Government, have the same right of action and intervention against the contractor and the contractor’s sureties as is conferred by law on persons furnishing labor or materials. In those proceedings it is not a defense that the laborers and mechanics accepted or agreed to accept less than the required rate of wages or voluntarily made refunds.
**(d) Review Process.—**
(1) **Time limit for appeal.—** — Within 60 days after an amount is withheld as liquidated damages, any contractor or subcontractor aggrieved by the withholding may appeal to the head of the agency of the Government or territory for which the contract work is done or which is providing financial assistance for the work, or to the Mayor of the District of Columbia in the case of liquidated damages withheld for the use and benefit of the District.
(2) **Review by agency head or mayor.—** — The agency head or Mayor may review the administrative determination of liquidated damages. The agency head or Mayor may issue a final order affirming the determination or may recommend to the Secretary of Labor that an appropriate adjustment in liquidated damages be made, or that the contractor or subcontractor be relieved of liability for the liquidated damages, if it is found that the amount is incorrect or that the contractor or subcontractor violated this chapter inadvertently, notwithstanding the exercise of due care by the contractor or subcontractor and the agents of the contractor or subcontractor.
(3) **Review by secretary.—** — The Secretary shall review all pertinent facts in the matter and may conduct any investigation the Secretary considers necessary in order to affirm or reject the recommendation. The decision of the Secretary is final.
(4) **Judicial action.—** — A contractor or subcontractor aggrieved by a final order for the withholding of liquidated damages may file a claim in the United States Court of Federal Claims within 60 days after the final order. A final order of the agency head, Mayor, or Secretary is conclusive with respect to findings of fact if supported by substantial evidence.
**(e) Applicability of Other Laws.—**
(1) **Reorganization plan.—** — Reorganization Plan Numbered 14 of 1950 (eff. May 24, 1950, 64 Stat. 1267) applies to this chapter.
(2) **Section 3145.—** — [Section 3145 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section3145&num=0&edition=prelim) applies to contractors and subcontractors referred to in section 3145 who are engaged in the performance of contracts subject to this chapter.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Definition.—** In this chapter, the term “Federal Government” has the same meaning that the term “United States” had in the Contract Work Hours and Safety Standards Act (Public Law 87–581, 76 Stat. 357).
**(b) Application.—**
(1) **Contracts.—** — This chapter applies to—
(A) any contract that may require or involve the employment of laborers or mechanics on a public work of the Federal Government, a territory of the United States, or the District of Columbia; and
(B) any other contract that may require or involve the employment of laborers or mechanics if the contract is one—
(i) to which the Government, an agency or instrumentality of the Government, a territory, or the District of Columbia is a party;
(ii) which is made for or on behalf of the Government, an agency or instrumentality, a territory, or the District of Columbia; or
(iii) which is a contract for work financed at least in part by loans or grants from, or loans insured or guaranteed by, the Government or an agency or instrumentality under any federal law providing wage standards for the work.
(2) **Laborers and mechanics.—** — This chapter applies to all laborers and mechanics employed by a contractor or subcontractor in the performance of any part of the work under the contract—
(A) including watchmen, guards, and workers performing services in connection with dredging or rock excavation in any river or harbor of the United States, a territory, or the District of Columbia; but
(B) not including an employee employed as a seaman.
(3) **Exceptions.—**
(A) *This chapter.—* — This chapter does not apply to—
(i) a contract for—
(I) transportation by land, air, or water;
(II) the transmission of intelligence; or
(III) the purchase of supplies or m
Source: Supplied U.S. Code snapshot — release unconfirmed · 40 U.S.C. § 3701
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) In General.—** The Secretary of Labor shall prescribe reasonable regulations for contractors and subcontractors engaged in constructing, carrying out, completing, or repairing public buildings, public works, or buildings or works that at least partly are financed by a loan or grant from the Federal Government. The regulations shall include a provision that each contractor and subcontractor each week must furnish a statement on the wages paid each employee during the prior week.
**(b) Application.—** [Section 1001 of title 18](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title18-section1001&num=0&edition=prelim) applies to the statements.
Source: Supplied U.S. Code snapshot — release unconfirmed · 40 U.S.C. § 3145
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
The United States Court of Federal Claims shall have jurisdiction to render judgment upon any claim for liquidated damages withheld from a contractor or subcontractor under [section 3703 of title 40](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section3703&num=0&edition=prelim).
Source: Supplied U.S. Code snapshot — release unconfirmed · 28 U.S.C. § 1499
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Standard Workweek.—** The wages of every laborer and mechanic employed by any contractor or subcontractor in the performance of work on a contract described in [section 3701 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section3701&num=0&edition=prelim) shall be computed on the basis of a standard workweek of 40 hours. Work in excess of the standard workweek is permitted subject to this section. For each workweek in which the laborer or mechanic is so employed, wages include compensation, at a rate not less than one and one-half times the basic rate of pay, for all hours worked in excess of 40 hours in the workweek.
**(b) Contract Requirements.—** A contract described in [section 3701 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section3701&num=0&edition=prelim), and any obligation of the Federal Government, a territory of the United States, or the District of Columbia in connection with that contract, must provide that—
(1) a contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall not require or permit any laborer or mechanic, in any workweek in which the laborer or mechanic is employed on that work, to work more than 40 hours in that workweek, except as provided in this chapter; and
(2) when a violation of clause (1) occurs, the contractor and any subcontractor responsible for the violation are liable—
(A) to the affected employee for the employee’s unpaid wages; and
(B) to the Government, the District of Columbia, or a territory for liquidated damages as provided in the contract.
**(c) Liquidated Damages.—** Liquidated damages under subsection (b)(2)(B) shall be computed for each indi
Source: Supplied U.S. Code snapshot — release unconfirmed · 40 U.S.C. § 3702
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Condition of Contracts.—**
(1) **In general.—** — Each contract in an amount greater than $100,000 that is entered into under legislation subject to Reorganization Plan Numbered 14 of 1950 (eff. May 24, 1950, 64 Stat. 1267) and is for construction, alteration, and repair, including painting and decorating, must provide that no contractor or subcontractor contracting for any part of the contract work shall require any laborer or mechanic employed in the performance of the contract to work in surroundings or under working conditions that are unsanitary, hazardous, or dangerous to health or safety, as established under construction safety and health standards the Secretary of Labor prescribes by regulation based on proceedings pursuant to [section 553 of title 5](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section553&num=0&edition=prelim), provided that the proceedings include a hearing similar in nature to that authorized by [section 553 of title 5](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section553&num=0&edition=prelim).
(2) **Consultation.—** — In formulating standards under this section, the Secretary shall consult with the Advisory Committee created by subsection (d).
**(b) Compliance.—**
(1) **Actions to gain compliance.—** — The Secretary may make inspections, hold hearings, issue orders, and make decisions based on findings of fact as the Secretary considers necessary to gain compliance with this section and any health and safety standard the Secretary prescribes under subsection (a). For those purposes the Secretary and the United States district courts have the authority and jurisdiction provided by sections 6506 and 6507 of title 41.
(2) **Remedy when noncompliance found.—** — When the Secretary, aft
Source: Supplied U.S. Code snapshot — release unconfirmed · 40 U.S.C. § 3704
Stored review status: release_metadata_unconfirmed. Incoming connection: Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Page 144
TITLE 40—PUBLIC BUILDINGS, PROPERTY, AND WORKS
§ 3703
tractor or subcontractor in the performance of
work on a contract described in section 3701 of
this title shall be computed on the basis of a
standard workweek of 40 hours. Work in excess
of the standard workweek is permitted subject
to this section. For each workweek in which the
laborer or mechanic is so employed, wages in-
clude compensation, at a rate not less than one
and one-half times the basic rate of pay, for all
hours worked in excess of 40 hours in the work-
week.
(b) CONTRACT REQUIREMENTS.—A contract de-
scribed in section 3701 of this title, and any obli-
gation of the Federal Government, a territory of
the United States, or the District of Columbia in
connection with that contract, must provide
that—
(1) a contractor or subcontractor con-
tracting for any part of the contract work
which may require or involve the employment
of laborers or mechanics shall not require or
permit any laborer or mechanic, in any work-
week in which the laborer or mechanic is em-
ployed on that work, to work more than 40
hours in that workweek, except as provided in
this chapter; and
(2) when a violation of clause (1) occurs, the
contractor and any subcontractor responsible
for the violation are liable—
(A) to the affected employee for the em-
ployee’s unpaid wages; and
(B) to the Government, the District of Co-
lumbia, or a territory for liquidated dam-
ages as provided in the contract.
(c) LIQUIDATED DAMAGES.—Liquidated damages
under subsection (b)(2)(B) shall be computed for
each individual employed as a laborer or me-
chanic in violation of this chapter and shall be
equal to $10 for each calendar day on which the
individual was required or permitted to work in
excess of the standard work
Source: Supplied 2024 U.S. Code historical extraction · 40 U.S.C. § 3703