10 U.S.C. § 6287 — Matters relating to critical decisions
Federal law — U.S. Code and appendices · legal_authorities
**(a) Post-critical Decision 2 Changes.—** After the date on which a plant project specifically authorized by law and carried out under Department of Energy Order 413.3B (relating to program management and project management for the acquisition of capital assets), or a successor order, achieves critical decision 2, the Administrator may not change the requirements for such project if such change increases the cost of such project by more than the lesser of $5,000,000 or 15 percent, unless—
(1) the Administrator submits to the congressional defense committees—
(A) a certification that the Administrator, without delegation, authorizes such proposed change; and
(B) a cost-benefit and risk analysis of such proposed change, including with respect to—
(i) the effects of such proposed change on the project cost and schedule; and
(ii) any mission risks and operational risks from making such change or not making such change; and
(2) a period of 15 days elapses following the date of such submission.
**(b) Review and Approval.—** The Administrator shall ensure that critical decision packages are timely reviewed and either approved or disapproved.
Source: Supplied U.S. Code snapshot — release unconfirmed · 10 U.S.C. § 6287
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: 40d744e2203c5a4fcb043bec4011f63d0d027fb84f9d58d4d00a86f3edac4392. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_10ab725b6dd27dde0696ee73
Source file: Laws/federal/codes/united-states-code/title-10/section-6287-matters-relating-to-critical-decisions--97108617ce.md
Pages: Not recorded – Not recorded
Passage SHA-256: 8db49641681c4f2ea0d017552540c463e12d51a4797cbdd7153def425149660a
Source location: Title 10, Chapter 607, § 6287; chapter-607-budget-and-financial-management-matters.md
Stored source content
**(a) Post-critical Decision 2 Changes.—** After the date on which a plant project specifically authorized by law and carried out under Department of Energy Order 413.3B (relating to program management and project management for the acquisition of capital assets), or a successor order, achieves critical decision 2, the Administrator may not change the requirements for such project if such change increases the cost of such project by more than the lesser of $5,000,000 or 15 percent, unless—
(1) the Administrator submits to the congressional defense committees—
(A) a certification that the Administrator, without delegation, authorizes such proposed change; and
(B) a cost-benefit and risk analysis of such proposed change, including with respect to—
(i) the effects of such proposed change on the project cost and schedule; and
(ii) any mission risks and operational risks from making such change or not making such change; and
(2) a period of 15 days elapses following the date of such submission.
**(b) Review and Approval.—** The Administrator shall ensure that critical decision packages are timely reviewed and either approved or disapproved.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
### Statutory Notes
Section 2744, Pub. L. 107–314, div. D, title XLVII, § 4704, formerly div. C, title XXXVI, § 3623, Dec. 2, 2002, 116 Stat. 2758; renumbered div. D, title XLVII, § 4704, by Pub. L. 108–136, div. C, title XXXI, § 3141(j)(2)(A)–(C), Nov. 24, 2003, 117 Stat. 1781, placed limits on construction projects, with some exceptions. See [section 6275 of Title 10](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section6275&num=0&edition=prelim), Armed Forces.
Section 2745, Pub. L. 107–314, div. D, title XLVII, § 4705, formerly div. C, title XXXVI, § 3624, Dec. 2, 2002, 116 Stat. 2758; renumbered div. D, title XLVII, § 4705, by Pub. L. 108–136, div. C, title XXXI, § 3141(j)(2)(A)–(C), Nov. 24, 2003, 117 Stat. 1781, provided certain fund transfer authority to the Secretary of Energy. See [section 6276 of Title 10](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section6276&num=0&edition=prelim), Armed Forces.
Section 2746, Pub. L. 107–314, div. D, title XLVII, § 4706, formerly div. C, title XXXVI, § 3625, Dec. 2, 2002, 116 Stat. 2759; renumbered div. D, title XLVII, § 4706, and amended Pub. L. 108–136, div. C, title XXXI, § 3141(j)(2)(A)–(C), (D)(ii), Nov. 24, 2003, 117 Stat. 1781; Pub. L. 113–66, div. C, title XXXI, § 3120, Dec. 26, 2013, 127 Stat. 1059; Pub. L. 114–328, div. C, title XXXI, § 3121, Dec. 23, 2016, 130 Stat. 2764; Pub. L. 117–81, div. C, title XXXI, § 3115(c), Dec. 27, 2021, 135 Stat. 2227, related to conceptual and construction designs for potential construction projects. See [section 6277 of Title 10](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section6277&num=0&edition=prelim), Armed Forces.
Section 2747, Pub. L. 107–314, div. D, title XLVII, § 4707, formerly div. C, title XXXV