33 U.S.C. § 2235 — Construction of water resources development projects by non-Federal interests
Federal law — U.S. Code and appendices · legal_authorities
**(a) Water resources development project defined** In this section, the term “water resources development project” means a project recommendation that results from—
(1) a feasibility report, as such term is defined in section 2282d(f) 11 See References in Text note below. of this title;
(2) a completed feasibility study developed under [section 2231 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2231&num=0&edition=prelim); or
(3) a final feasibility study for water resources development and conservation and other purposes that is specifically authorized by Congress to be carried out by the Secretary.
**(b) Authority**
(1) **In general** — A non-Federal interest may carry out a federally authorized water resources development project, or separable element thereof—
(A) in accordance with a plan approved by the Secretary for the project or separable element; and
(B) subject to any conditions that the Secretary may require, including any conditions specified under [section 2231(c)(3) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2231/c/3&num=0&edition=prelim).
(2) **Conditions** — Before carrying out a water resources development project, or separable element thereof, under this section, a non-Federal interest shall—
(A) obtain any permit or approval required in connection with the project or separable element under Federal or State law, except as provided in paragraph (3); and
(B) ensure that a final environmental impact statement or environmental assessment, as appropriate, for the project or separable element has been filed.
(3) **Permit exception**
(A) *In general* — For a project described in subsection (a)(1) or subsection (a)(3), or a separable element ther
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2235
Stored review status: release_metadata_unconfirmed. A text match is a research starting point; applicability is not established.
Original supplied file — preserved unchanged
Download original Markdown file
File SHA-256: 06826476a4ae10b819c681c078c2651ec5b9c96af7fac3f14b385f1f169f3fc0. The original may include catalog metadata, neighboring provisions, or embedded records outside this collection's scope. Search shows only the selected federal record. Historical editions and unverified snapshots are not a statement of current law.
Authority boundary: historical or unconfirmed source not current law verified.
Open the recorded source website ↗
Record provenance
Stable record: federal_law:legal_authorities:record_usc_007e13994f6522fdb54e3a34
Source file: Laws/federal/codes/united-states-code/title-33/section-2235-construction-of-water-resources-development-projects-by-non-federal-inte--dbf7ecd8a9.md
Pages: Not recorded – Not recorded
Passage SHA-256: d5798663208301299dcd2e0f7cb0bd249d905ffa79d28411c21985908edcfe4e
Source location: Title 33, Chapter 36, § 2235; chapter-036-water-resources-development.md
Stored source content
**(a) Water resources development project defined** In this section, the term “water resources development project” means a project recommendation that results from—
(1) a feasibility report, as such term is defined in section 2282d(f) 11 See References in Text note below. of this title;
(2) a completed feasibility study developed under [section 2231 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2231&num=0&edition=prelim); or
(3) a final feasibility study for water resources development and conservation and other purposes that is specifically authorized by Congress to be carried out by the Secretary.
**(b) Authority**
(1) **In general** — A non-Federal interest may carry out a federally authorized water resources development project, or separable element thereof—
(A) in accordance with a plan approved by the Secretary for the project or separable element; and
(B) subject to any conditions that the Secretary may require, including any conditions specified under [section 2231(c)(3) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2231/c/3&num=0&edition=prelim).
(2) **Conditions** — Before carrying out a water resources development project, or separable element thereof, under this section, a non-Federal interest shall—
(A) obtain any permit or approval required in connection with the project or separable element under Federal or State law, except as provided in paragraph (3); and
(B) ensure that a final environmental impact statement or environmental assessment, as appropriate, for the project or separable element has been filed.
(3) **Permit exception**
(A) *In general* — For a project described in subsection (a)(1) or subsection (a)(3), or a separable element thereof, with respect to which a written agreement described in subparagraph (B) has been entered into, a non-Federal interest that carries out a project under this section shall not be required to obtain any Federal permits or approvals that would not be required if the Secretary carried out the project or separable element unless significant new circumstances or information relevant to environmental concerns or compliance have arisen since development of the project recommendation.
(B) *Written agreement* — For purposes of this paragraph, a written agreement shall provide that the non-Federal interest shall comply with the same legal and technical requirements that would apply if the project or separable element were carried out by the Secretary, including all mitigation required to offset environmental impacts of the project or separable element as determined by the Secretary.
(C) *Certifications* — Notwithstanding subparagraph (A), if a non-Federal interest carrying out a project under this section would, in the absence of a written agreement entered into under this paragraph, be required to obtain a certification from a State under Federal law to carry out the project, such certification shall still be required if a written agreement is entered into with respect to the project under this paragraph.
(4) **Data sharing**
(A) *In general* — If a non-Federal interest for a water resources development project begins to carry out that water resources development project under this section, the non-Federal interest may request that the Secretary transfer to the non-Federal interest all relevant data and documentation under the control of the Secretary with respect to that water resources development project.
(B) *Deadline* — Except as provided in subparagraph (C), the Secretary shall transfer the data and documentation requested by a non-Federal interest under subparagraph (A) not later than the date that is 90 days after the date on which the non-Federal interest so requests such data and documentation.
(C) *Limitation* — Nothing in this paragraph obligates the Secretary to share any data or documentation that the Secretary considers to be proprietary information.
**(c) Studies and engineering**
(1) **In general** — When requested by a non-Federal interest carrying out a project or separable element of a project under this section, the Secretary shall undertake all necessary studies, engineering, and technical assistance on construction for any project or separable element of a project under this section, and provide technical assistance in obtaining all necessary permits for the construction, if the non-Federal interest contracts with the Secretary to provide funds to the United States for the studies, engineering, or technical assistance.
(2) **No waiver** — Nothing in this section may be construed to waive any requirement of [section 3142 of title 40](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title40-section3142&num=0&edition=prelim).
(3) **Limitation** — Funds provided by non-Federal interests under this subsection shall not be eligible for credit or reimbursement under subsection (d).
(4) **Impartial decisionmaking** — In carrying out this section, the Secretary shall ensure that the use of funds accepted from a non-Federal interest will not affect the impartial decisionmaking of the Secretary, either substantively or procedurally.
**(d) Credit or reimbursement**
(1) **General rule** — Subject to paragraph (3), a project or separable element of a project carried out by a non-Federal interest under this section shall be eligible for credit or reimbursement for the Federal share of work carried out on a project or separable element of a project if—
(A) before initiation of construction of the project or separable element—
(i) the Secretary approves the plan for construction of the project or separable element of the project by the non-Federal interest;
(ii) the Secretary determines, before approval of the plan, that the project or separable element of the project is feasible; and
(iii) the non-Federal interest enters into a written agreement with the Secretary under [section 1962d–5b of title 42](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section1962d–5b&num=0&edition=prelim), including an agreement to pay the non-Federal share, if any, of the cost of operation and maintenance of the project; and
(B) the Secretary determines that all Federal laws and regulations applicable to the construction of a water resources development project, and any conditions identified under subsection (b)(1)(B), were complied with by the non-Federal interest during construction of the project or separable element of the project.
(2) **Application of credit** — The Secretary may apply credit toward—
(A) the non-Federal share of authorized separable elements of the same project; or
(B) subject to the requirements of this section and [section 2223 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2223&num=0&edition=prelim), at the request of the non-Federal interest, the non-Federal share of a different water resources development project.
(3) **Requirements** — The Secretary may only apply credit or provide reimbursement under paragraph (1) if—
(A) Congress has authorized construction of the project or separable element of the project;
(B) the Secretary certifies that the project, discrete segment of the project, or separable element of the project has been constructed in accordance with—
(i) all applicable permits or approvals; and
(ii) this section; and
(C) in the case of reimbursement, appropriations are provided by Congress for such purpose.
(4) **Monitoring** — The Secretary shall regularly monitor and audit any water resources development project, or separable element of a water resources development project, constructed by a non-Federal interest under this section to ensure that—
(A) the construction is carried out in compliance with the requirements of this section; and
(B) the costs of the construction are reasonable.
(5) **Discrete segments**
(A) *In general* — The Secretary may authorize credit or reimbursement under this subsection for carrying out a discrete segment of a federally authorized water resources development project, or separable element thereof, before final completion of the project or separable element if—
(i) except as provided in clause (ii), the Secretary determines that the discrete segment satisfies the requirements of paragraphs (1) through (4) in the same manner as the project or separable element; and
(ii) notwithstanding paragraph (1)(A)(ii), the Secretary determines, before the approval of the plan under paragraph (1)(A)(i), that the discrete segment is technically feasible and environmentally acceptable.
(B) *Determination* — Credit or reimbursement may not be made available to a non-Federal interest pursuant to this paragraph until the Secretary determines that—
(i) the construction of the discrete segment for which credit or reimbursement is requested is complete; and
(ii) the construction is consistent with the authorization of the applicable water resources development project, or separable element thereof, and the plan approved under paragraph (1)(A)(i).
(C) *Written agreement*
(i) *In general* — As part of the written agreement required under paragraph (1)(A)(iii), a non-Federal interest to be eligible for credit or reimbursement under this paragraph shall—
(I) identify any discrete segment that the non-Federal interest may carry out; and
(II) agree to the completion of the water resources development project, or separable element thereof, with respect to which the discrete segment is a part and establish a timeframe for such completion.
(ii) *Remittance* — If a non-Federal interest fails to complete a water resources development project, or separable element thereof, that it agreed to complete under clause (i)(II), the non-Federal interest shall remit any reimbursements received under this paragraph for a discrete segment of such project or separable element.
(D) *Discrete segment defined* — In this paragraph, the term “discrete segment” means a physical portion of a water resources development project to be carried out, or separable element thereof—
(i) described by a non-Federal interest in a written agreement required under paragraph (1)(A)(iii); and
(ii) that the non-Federal interest can operate and maintain, independently and without creating a hazard, in advance of final completion of the water resources development project, or separable element thereof.
(6) **Exclusions** — The Secretary may not provide credit or reimbursement for—
(A) activities required by the non-Federal interest to initiate design and construction that would otherwise not be required by the Secretary; or
(B) delays incurred by the non-Federal interest resulting in project cost increases.
**(e) Notification of committees** If a non-Federal interest notifies the Secretary that the non-Federal interest intends to carry out a project, or separable element thereof, under this section, the Secretary shall provide written notice to the Committee on Environment and Public Works of the Senate and the Committee on Transportation and Infrastructure of the House of Representatives concerning the intent of the non-Federal interest.
**(f) Operation and maintenance**
(1) **Assumption of maintenance** — Whenever a non-Federal interest carries out improvements to a federally authorized harbor or inland harbor, the Secretary shall be responsible for operation and maintenance in accordance with [section 2211(b) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2211/b&num=0&edition=prelim) if—
(A) before construction of the improvements—
(i) the Secretary determines that the improvements are feasible and consistent with the purposes of this subchapter; and
(ii) the Secretary and the non-Federal interest execute a written agreement relating to operation and maintenance of the improvements;
(B) the Secretary certifies that the project or separable element of the project is constructed in accordance with applicable permits and appropriate engineering and design standards; and
(C) the Secretary does not find that the project or separable element is no longer feasible.
(2) **Federal financial participation in the costs of a locally preferred plan.** — In the case of improvements determined by the Secretary pursuant to paragraph (1)(A)(i) to deviate from the national economic development plan, the Secretary shall be responsible for all operation and maintenance costs of such improvements, as described in [section 2211(b) of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2211/b&num=0&edition=prelim), including costs in excess of the costs of the national economic development plan, if the Secretary determines that the improvements satisfy the requirements of paragraph (1).
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Congressional declaration of policy; purchase of indebtedness and loans to local interests to meet contribution requirements** In the prosecution of projects for rivers and harbors and other waterways for the benefit of navigation, the control of destructive flood waters, hurricane protection, beach erosion control, and for other purposes, authorized to be prosecuted under the direction of the Secretary of the Army under the supervision of the Chief of Engineers in accordance with plans adopted and authorized by the Congress, it is hereby declared to be the policy of the Congress, that whenever such projects are located wholly or partially within an area which is eligible for financial assistance under the Public Works and Economic Development Act of 1965 [[42 U.S.C. 3121](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section3121&num=0&edition=prelim) et seq.], the Secretary of Commerce is authorized to purchase evidences of indebtedness and to make loans for a period not exceeding fifty years to enable responsible local interests to meet the requirements of local cooperation pertaining to contributions toward the cost of construction of such projects within such areas.
**(b) Authorization of appropriations** There is hereby authorized to be appropriated to carry out this section, not to exceed $10,000,000 per fiscal year for the fiscal year ending June 30, 1966, and for each fiscal year thereafter through and including the fiscal year ending June 30, 1970.
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2223
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
For purpose of this subchapter—
(1) The term “act of God” means an unanticipated grave natural disaster or other natural phenomenon of an exceptional, inevitable, and irresistible character, the effects of which could not have been prevented or avoided by the exercise of due care or foresight.
(2) The term “Administrator” means the Administrator of the United States Environmental Protection Agency.
(3) The term “barrel” means forty-two United States gallons at sixty degrees Fahrenheit.
(4) The term “claim” means a demand in writing for a sum certain.
(5) The term “claimant” means any person who presents a claim for compensation under this chapter.
(6) The term “damages” means damages for injury or loss of natural resources as set forth in section 9607(a) or 9611(b) of this title.
(7) The term “drinking water supply” means any raw or finished water source that is or may be used by a public water system (as defined in the Safe Drinking Water Act [[42 U.S.C. 300f](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section300f&num=0&edition=prelim) et seq.]) or as drinking water by one or more individuals.
(8) The term “environment” means (A) the navigable waters, the waters of the contiguous zone, and the ocean waters of which the natural resources are under the exclusive management authority of the United States under the Magnuson-Stevens Fishery Conservation and Management Act [[16 U.S.C. 1801](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title16-section1801&num=0&edition=prelim) et seq.], and (B) any other surface water, ground water, drinking water supply, land surface or subsurface strata, or ambient air within the United States or under the jurisdiction of the United States.
(9) The term “facility” means (A) any building, st
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 9601
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Requests for credits** With respect to an authorized flood damage reduction project, or separable element thereof, that has been constructed by a non-Federal interest under section 701b–13 11 See References in Text note below. of this title, or an authorized coastal navigation project that has been constructed by the Corps of Engineers pursuant to [section 561 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section561&num=0&edition=prelim) before October 23, 2018, the Secretary may provide to the non-Federal interest, at the request of the non-Federal interest, a credit in an amount equal to the estimated Federal share of the cost of the project or separable element, in lieu of providing to the non-Federal interest a reimbursement in that amount or reimbursement of funds of an equivalent amount, subject to the availability of appropriations.
**(b) Application of credits** At the request of the non-Federal interest, the Secretary may apply all or a portion of such credit to the share of the cost of the non-Federal interest of carrying out other flood damage reduction and coastal navigation projects or studies.
**(c) Application of reimbursement** At the request of the non-Federal interest, the Secretary may apply such funds, subject to the availability of appropriations, equal to the share of the cost of the non-Federal interest of carrying out other flood damage reduction and coastal navigation projects or studies.
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2231
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Resiliency assessment**
(1) **In general** — Not later than 180 days after December 27, 2020, and in conjunction with the development of procedures under [section 1962–4 of title 42](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section1962–4&num=0&edition=prelim), the Secretary is directed to review, and where appropriate, revise the existing planning guidance documents and regulations of the Corps of Engineers on the assessment of the effects of sea level rise or inland flooding on future water resources development projects to ensure that such guidance documents and regulations are based on the best available, peer-reviewed science and data on the current and future effects of sea level rise or inland flooding on relevant communities.
(2) **Coordination** — In carrying out this subsection, the Secretary shall—
(A) coordinate the review with the Engineer Research and Development Center, other Federal and State agencies, and other relevant entities; and
(B) to the maximum extent practicable and where appropriate, utilize data provided to the Secretary by such agencies.
**(b) Assessment of benefits from addressing sea level rise and inland flooding resiliency in feasibility reports**
(1) **In general** — Upon the request of a non-Federal interest, in carrying out a feasibility study for a project for flood risk mitigation, hurricane and storm damage risk reduction, or ecosystem restoration under [section 2282 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title33-section2282&num=0&edition=prelim), the Secretary shall consider whether the need for the project is predicated upon or exacerbated by conditions related to sea level rise or inland flooding.
(2) **Addressing sea level rise and inland flooding
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2283
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Allotment from appropriations for construction** The Secretary of the Army is authorized to allot from any appropriations hereafter made for rivers and harbors not to exceed $62,500,000 for any one fiscal year for the construction of small river and harbor improvement projects not specifically authorized by Congress which will result in substantial benefits to navigation and which can be operated consistently with appropriate and economic use of the waters of the Nation for other purposes, when in the opinion of the Chief of Engineers such work is advisable, if benefits are in excess of the cost.
**(b) Limitation on allotment** Not more than $15,000,000 shall be allotted for the construction of a project under this section at any single locality and the amount allotted shall be sufficient to complete the Federal participation in the project under this section.
**(c) Lands, easements, and rights-of-way; indemnification; assurances of local cooperation** Local interests shall provide without cost to the United States all necessary lands, easements and rights-of-way for all projects to be constructed under the authority of this section. In addition, local interests may be required to hold and save the United States free from damages that may result from the construction and maintenance of the project and may be required to provide such additional local cooperation as the Chief of Engineers deems appropriate. A State, county, municipality or other responsible local entity shall give assurance satisfactory to the Chief of Engineers that such conditions of cooperation as are required will be accomplished.
**(d) Sharing of costs by non-Federal interests** Non-Federal interests may be required to share in the cost of the project to the extent that the Chief of Engineer
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 577
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) Application.—** The advertised specifications for every contract in excess of $2,000, to which the Federal Government or the District of Columbia is a party, for construction, alteration, or repair, including painting and decorating, of public buildings and public works of the Government or the District of Columbia that are located in a State or the District of Columbia and which requires or involves the employment of mechanics or laborers shall contain a provision stating the minimum wages to be paid various classes of laborers and mechanics.
**(b) Based on Prevailing Wage.—** The minimum wages shall be based on the wages the Secretary of Labor determines to be prevailing for the corresponding classes of laborers and mechanics employed on projects of a character similar to the contract work in the civil subdivision of the State in which the work is to be performed, or in the District of Columbia if the work is to be performed there.
**(c) Stipulations Required in Contract.—** Every contract based upon the specifications referred to in subsection (a) must contain stipulations that—
(1) the contractor or subcontractor shall pay all mechanics and laborers employed directly on the site of the work, unconditionally and at least once a week, and without subsequent deduction or rebate on any account, the full amounts accrued at time of payment, computed at wage rates not less than those stated in the advertised specifications, regardless of any contractual relationship which may be alleged to exist between the contractor or subcontractor and the laborers and mechanics;
(2) the contractor will post the scale of wages to be paid in a prominent and easily accessible place at the site of the work; and
(3) there may be withheld from the contractor so much of accrued pay
Source: Supplied U.S. Code snapshot — release unconfirmed · 40 U.S.C. § 3142
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
In the preparation of projects under this and subsequent river and harbor acts and after the project becomes operational, unless otherwise expressed, the channel depths referred to shall be understood to signify the depth at mean lower low water, as defined by the Department of Commerce for nautical charts and tidal predictions, in tidal waters tributary to the Atlantic and Gulf coasts and at mean lower low water, as defined by the Department of Commerce for nautical charts and tidal predictions, in tidal waters tributary to the Pacific coast and the mean depth for a continuous period of fifteen days of the lowest water, as defined by the Department of Commerce for nautical charts and tidal predictions, in the navigation season of any year in rivers and nontidal channels, and and 11 So in original. after the project becomes operational the channel dimensions specified shall be understood to admit of such increase at the entrances, bends, sidings, and turning places as may be necessary to allow of the free movement of boats.
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 562
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
The Council is authorized to delegate to any member or employee of the Council its administrative functions under [section 1962a–4 of this title](https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section1962a-4&num=0&edition=prelim) and the detailed administration of the grant program under subchapter III.
Source: Supplied U.S. Code snapshot — release unconfirmed · 42 U.S.C. § 1962d–5b
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
**(a) In general** Subject to subsection (b), the Secretary may carry out an authorized water resources development project on Federal land that is under the administrative jurisdiction of another Federal agency where the cost of the acquisition of such Federal land has been paid for by the non-Federal interest for the project.
**(b) MOU required** The Secretary may carry out a project pursuant to subsection (a) only after the non-Federal interest has entered into a memorandum of understanding with the Federal agency that includes such terms and conditions as the Secretary determines to be necessary.
**(c) Applicability** Nothing in this section alters any non-Federal cost-sharing requirements for the project.
Source: Supplied U.S. Code snapshot — release unconfirmed · 33 U.S.C. § 2232
Stored review status: release_metadata_unconfirmed. Explicit cross-reference supplied in source Markdown; currentness and applicability require review.
Federal law — U.S. Code and appendices · legal_authorities
Page 725
TITLE 33—NAVIGATION AND NAVIGABLE WATERS
§ 2236
(g) Progress reports
Six months before the final date of the sched-
ule, the Secretary shall provide to Congress a
written progress report for each navigation
project for a harbor or inland harbor subject to
this section. The Secretary shall transmit the
report to the Committee on Public Works and
Transportation of the House of Representatives
and the Committee on Environment and Public
Works of the Senate. The report shall summa-
rize all work completed under the agreement
and shall include a detailed work program that
will assure completion of all remaining work
under the agreement.
(h) Final decision
Not later than the final day of the schedule,
the Secretary shall notify the non-Federal inter-
est of the final decision on the project and
whether the permit or permits have been issued.
(i) Report on timesavings methods
Not later than one year after November 17,
1986, the Secretary shall prepare and transmit to
Congress a report estimating the time required
for the issuance of all Federal, State, and local
permits for the construction of navigation
projects for harbors or inland harbors and asso-
ciated activities. The Secretary shall include in
that report recommendations for further reduc-
ing the amount of time required for the issuance
of
those
permits,
including
any
proposed
changes in existing law.
(Pub. L. 99–662, title II, § 205, Nov. 17, 1986, 100
Stat. 4101.)
Statutory Notes and Related Subsidiaries
CHANGE OF NAME
Committee on Public Works and Transportation of
House of Representatives treated as referring to Com-
mittee on Transportation and Infrastructure of House
of Representatives by section 1(a) of Pub. L. 104–14, set
out as a note preceding section 21 of Title