23-4-406. Test periods to justify new rates.
Arkansas Code — all titles (historical 2020) · legal_authorities
23-4-406. Test periods to justify new rates.
For the purpose of justifying the reasonableness of a proposed new rate schedule, a utility may utilize either a historical test period of twelve (12) consecutive calendar months or a forward-looking test period of twelve (12) consecutive calendar months consisting of six (6) months of actual historical data derived from the books and records of the utility and six (6) months of projected data which together shall be the period or test year upon which fair and reasonable rates shall be determined by the Arkansas Public Service Commission. However, the commission shall also permit adjustments to any test year so utilized to reflect the effects on an annualized basis of any and all changes in circumstances which may occur within twelve (12) months after the end of the test year where such changes are both reasonably known and measurable.
Source: Arkansas Code — historical release 78 (November 6, 2020) · 23-4-406
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. A text match is a research starting point; applicability is not established.
Issuing source page ↗
Authority boundary: historical statutory source snapshot not current law.
Open the recorded source website ↗
Record provenance
Stable record: arkansas_code:legal_authorities:23-4-406
Source file: gov.ar.code.title.23.odt
Pages: Not recorded – Not recorded
Passage SHA-256: 276efdfc6d62056459bfcb87e78534159bc0b3619e55fd045e200661005940e7
Source location: content.xml paragraph 3292
Stored source content
23-4-406. Test periods to justify new rates.
For the purpose of justifying the reasonableness of a proposed new rate schedule, a utility may utilize either a historical test period of twelve (12) consecutive calendar months or a forward-looking test period of twelve (12) consecutive calendar months consisting of six (6) months of actual historical data derived from the books and records of the utility and six (6) months of projected data which together shall be the period or test year upon which fair and reasonable rates shall be determined by the Arkansas Public Service Commission. However, the commission shall also permit adjustments to any test year so utilized to reflect the effects on an annualized basis of any and all changes in circumstances which may occur within twelve (12) months after the end of the test year where such changes are both reasonably known and measurable.