19-11-1405. Project selection.
Arkansas Code — all titles (historical 2020) · legal_authorities
19-11-1405. Project selection.
If the Arkansas Department of Transportation determines that a construction manager-general contractor method of procurement is appropriate for a transportation project, the department shall establish a procedure for awarding the contract for construction of the construction manager-general contractor method transportation project using the criteria listed in § 19-11-1406.
Source: Arkansas Code — historical release 78 (November 6, 2020) · 19-11-1405
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. A text match is a research starting point; applicability is not established.
Issuing source page ↗
Authority boundary: historical statutory source snapshot not current law.
Open the recorded source website ↗
Record provenance
Stable record: arkansas_code:legal_authorities:19-11-1405
Source file: gov.ar.code.title.19.odt
Pages: Not recorded – Not recorded
Passage SHA-256: bdc55fee646dfcd73a27dd28804f3198f12d464ce4eb1bd9393486c9e7d98c5c
Source location: content.xml paragraph 17875
Stored source content
19-11-1405. Project selection.
If the Arkansas Department of Transportation determines that a construction manager-general contractor method of procurement is appropriate for a transportation project, the department shall establish a procedure for awarding the contract for construction of the construction manager-general contractor method transportation project using the criteria listed in § 19-11-1406.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Arkansas Code — all titles (historical 2020) · legal_authorities
19-11-1406. Request for proposals.
(a) A request for proposals under this subchapter shall include without limitation the following:
(1) The minimum qualifications of the construction manager-general contractor;
(2) The procedures for submitting a proposal to the Arkansas Department of Transportation, the criteria for the evaluation of and selection of a construction manager-general contractor to perform preconstruction services, and the relative weight assigned for each criteria as indicated in a technical scoring matrix;
(3) The form of the contract to be awarded for preconstruction services;
(4) A listing of the types and scope of the preconstruction services that will be required;
(5) The scope of the intended contract;
(6) The budget limits for the transportation project and the preconstruction services;
(7) The method of payment and structure of fees for the preconstruction services;
(8) A requirement that the construction manager-general contractor submit relevant information regarding any licenses, registration, or credentials that may be required to construct the transportation project;
(9) A requirement that the construction manager-general contractor provide evidence that establishes that the construction manager-general contractor is capable of obtaining the required bonding and insurance;
(10) A requirement that the construction manager-general contractor submit information concerning the debarment or default from a federal, state, or local government transportation project within the past five (5) years;
(11) A requirement that the construction manager-general contractor provide information concerning the bankruptcy or receivership of any of its members, including information concerning any work completed by a surety;
(12) A requi
Source: Arkansas Code — historical release 78 (November 6, 2020) · 19-11-1406
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. The source passage cites 19-11-1406. This identifies an authority to review, not proof of applicability.