(a) The State Highway Commission may develop a Construction Manager-General Contractor Method of Procurement Pilot Program to test the utilization of the construction manager-general contractor method as a cost-effective option for constructing transportation projects.
(b)(1) During the term of the program the commission may select a total of five (5) transportation projects on which to utilize the construction manager-general contractor method.
(2)(A) The sum of the construction cost estimates prepared as required under § 19-11-1407 of all five (5) construction manager-general contractor method transportation projects shall not exceed two hundred million dollars ($200,000,000).
(B) A construction cost estimate of a construction manager-general contractor method transportation project shall not exceed one hundred million dollars ($100,000,000).
(c) The Director of State Highways and Transportation shall send written notice identifying the transportation project and the reasons for deciding to apply the construction manager-general contractor method to that specific transportation project to:
(1) The Chair of the House Committee on Public Transportation; and
(2) The Chair of the Senate Committee on Public Transportation, Technology, and Legislative Affairs.
(d) The program established under this subchapter shall terminate no later than June 30, 2024.
Source: Arkansas Code — historical release 78 (November 6, 2020) · 19-11-1404
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. A text match is a research starting point; applicability is not established.
Issuing source page ↗
Authority boundary: historical statutory source snapshot not current law.
Open the recorded source website ↗
Record provenance
Stable record: arkansas_code:legal_authorities:19-11-1404
Source file: gov.ar.code.title.19.odt
Pages: Not recorded – Not recorded
Passage SHA-256: c1ef71a6d84dd7856e362482f082fd86ab25ca443650e04172e043f65a1e0c07
Source location: content.xml paragraph 17860
Stored source content
19-11-1404. Construction Manager-General Contractor Method of Procurement Pilot Program — Creation.
(a) The State Highway Commission may develop a Construction Manager-General Contractor Method of Procurement Pilot Program to test the utilization of the construction manager-general contractor method as a cost-effective option for constructing transportation projects.
(b)(1) During the term of the program the commission may select a total of five (5) transportation projects on which to utilize the construction manager-general contractor method.
(2)(A) The sum of the construction cost estimates prepared as required under § 19-11-1407 of all five (5) construction manager-general contractor method transportation projects shall not exceed two hundred million dollars ($200,000,000).
(B) A construction cost estimate of a construction manager-general contractor method transportation project shall not exceed one hundred million dollars ($100,000,000).
(c) The Director of State Highways and Transportation shall send written notice identifying the transportation project and the reasons for deciding to apply the construction manager-general contractor method to that specific transportation project to:
(1) The Chair of the House Committee on Public Transportation; and
(2) The Chair of the Senate Committee on Public Transportation, Technology, and Legislative Affairs.
(d) The program established under this subchapter shall terminate no later than June 30, 2024.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
Arkansas Code — all titles (historical 2020) · legal_authorities
19-11-1407. Construction manager-general contractor selection.
(a) The Arkansas Department of Transportation shall:
(1) Prepare contract plans, specifications, special provisions, and other requirements composing the contract for construction of a transportation project elected for procurement using the construction manager-general contract method authorized by this subchapter;
(2) Prepare a detailed construction cost estimate to evaluate the appropriate price for the construction of the transportation project;
(3) If requested by the Director of State Highways and Transportation, have an independent third-party cost estimator prepare a detailed construction cost estimate to confirm the appropriate price for the construction of the transportation project;
(4) Include in the contract created by subdivision (a)(1) of this section a requirement that the construction manager-general contractor perform at least thirty percent (30%) of the total cost for construction, not including the preconstruction work performed by the construction manager-general contractor; and
(5)(A) Keep the construction cost estimates prepared under subdivisions (a)(2) and (3) of this section confidential and not subject to public disclosure until after the contract has been awarded.
(B) Construction cost estimates prepared under subdivisions (a)(2) and (3) of this section are confidential and exempt from public disclosure under the Freedom of Information Act of 1967, § 25-19-101 et seq., but only until after the contract has been awarded.
(b) A construction manager-general contractor shall submit to the department a guaranteed maximum price for the construction of the transportation project using the contract plans, specifications, special provisions, and other requirements prepared
Source: Arkansas Code — historical release 78 (November 6, 2020) · 19-11-1407
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. The source passage cites 19-11-1407. This identifies an authority to review, not proof of applicability.