Arkansas Legal Resource Navigator

14-317-130. Estimate of work completed — Payment of contractors.

Arkansas Code — all titles (historical 2020) · legal_authorities

14-317-130. Estimate of work completed — Payment of contractors.

14-317-130. Estimate of work completed — Payment of contractors. It shall be the duty of the board to have the amount of work done by any contractor estimated from time to time, as may be desirable by the engineer selected by the board. The board shall draw its warrants in favor of the contractor for not more than ninety percent (90%) of the amount of work so reported, reserving the remainder until it has been ascertained that the work is completed according to contract and is free from liens.

Source: Arkansas Code — historical release 78 (November 6, 2020) · 14-317-130

Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. A text match is a research starting point; applicability is not established.

Issuing source page ↗

Authority boundary: historical statutory source snapshot not current law.

Open the recorded source website ↗

Record provenance

Stable record: arkansas_code:legal_authorities:14-317-130
Source file: gov.ar.code.title.14.odt
Pages: Not recorded – Not recorded
Passage SHA-256: 0715bf10ce458e8f230900403cb0b08d0469fe2645fc005ec05527d4eb97b688

Source location: content.xml paragraph 56862

Stored source content

14-317-130. Estimate of work completed — Payment of contractors. It shall be the duty of the board to have the amount of work done by any contractor estimated from time to time, as may be desirable by the engineer selected by the board. The board shall draw its warrants in favor of the contractor for not more than ninety percent (90%) of the amount of work so reported, reserving the remainder until it has been ascertained that the work is completed according to contract and is free from liens.

Cross-references

Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.

No explicit source connection was found. This does not mean there are no relevant authorities.