11-5-307. Notification.
Arkansas Code — all titles (historical 2020) · legal_authorities
11-5-307. Notification.
(a)(1) When any person, firm, or corporation desires to temporarily carry on any function, activity, work, or operation in closer proximity to any energized overhead electrical line or conductor than permitted by this subchapter, the person or persons responsible for the work to be done shall promptly notify the Director of the Division of Labor and the operator or owner of the electrical lines in writing of the work to be performed and make appropriate arrangements with the operator of the electrical lines before proceeding with any work which would impair the clearances required by this subchapter.
(2) The written notice shall be given to the owner or operator of the electrical lines by submitting notification to the manager of the nearest local office of the operator or owner of the electrical lines with a copy forwarded to the director.
(b)(1) The work shall be performed only after satisfactory mutual arrangements have been negotiated between the owner and operator of the electrical lines and the person or persons responsible for the work to be done.
(2) The owner or operator of the electrical lines shall commence work on the mutual arrangements as provided herein within three (3) working days of the mutual arrangement. Once initiated, the clearance work will continue without unreasonable interruption to complete.
Source: Arkansas Code — historical release 78 (November 6, 2020) · 11-5-307
Stored review status: Historical 2020-11-06 source release; later amendments not reconciled; machine-extracted, not independently legally reviewed; source heading status: text_in_historical_source. A text match is a research starting point; applicability is not established.
Issuing source page ↗
Authority boundary: historical statutory source snapshot not current law.
Open the recorded source website ↗
Record provenance
Stable record: arkansas_code:legal_authorities:11-5-307
Source file: gov.ar.code.title.11.odt
Pages: Not recorded – Not recorded
Passage SHA-256: e942ffd6a4edb5fe4f59677710be041fa352767a6f5b0835756d9860d93d9303
Source location: content.xml paragraph 2068
Stored source content
11-5-307. Notification.
(a)(1) When any person, firm, or corporation desires to temporarily carry on any function, activity, work, or operation in closer proximity to any energized overhead electrical line or conductor than permitted by this subchapter, the person or persons responsible for the work to be done shall promptly notify the Director of the Division of Labor and the operator or owner of the electrical lines in writing of the work to be performed and make appropriate arrangements with the operator of the electrical lines before proceeding with any work which would impair the clearances required by this subchapter.
(2) The written notice shall be given to the owner or operator of the electrical lines by submitting notification to the manager of the nearest local office of the operator or owner of the electrical lines with a copy forwarded to the director.
(b)(1) The work shall be performed only after satisfactory mutual arrangements have been negotiated between the owner and operator of the electrical lines and the person or persons responsible for the work to be done.
(2) The owner or operator of the electrical lines shall commence work on the mutual arrangements as provided herein within three (3) working days of the mutual arrangement. Once initiated, the clearance work will continue without unreasonable interruption to complete.
Cross-references
Connections may be documented source relationships, shared citations or nearby passages. Each explains its basis; a connection alone does not establish applicability to your situation.
No explicit source connection was found. This does not mean there are no relevant authorities.